Forwards IE Insp Repts 50-321/78-33 & 50-366/78-41 on 781003-06 & Notice of Violation
ML19263B303
Person / Time
Site: Hatch  
Issue date: 11/17/1978
From: Long F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
Shared Package
ML19263B301 List:
References
NUDOCS 7901180007
Download: ML19263B303 (2)


See also: IR 05000321/1978033

Text

,

. .

.

.

UNITED sT ATEs

p* 88Gg

/b

NUCLE AR REGUL ATORY COMMISSION

9,

$

- /' $

REGION H

'

$

101 M ARIE T T A sT TE E T. N W

f.

% 'g

f

ATL ANT A. GE oRGI A 30303

s'

v.

.

NOV 17 1978

....."

In Reply Refer To:

RII:FSC

50-321/78-33 and 50-366/78-41

Georgia Power Company

ATTN:

M r . J . 11. M i l l e r , J r .

Executive Vice President

270 Peachtree Street, N.W.

Atlanta, Georgia

30303

Gentlemen:

This refers to the inspection conducted by Messrs. F. S. Cantrell, D. S.

Price and R. Vogt-Lowell, of this office on October 3-7, 1978, of activi-

ties authorized by NRC Nos. DPR-57 and NPF-5 for the E. 1. Hatch facility,

Units 1 and 2 and to the discussion of our findings held with Mr. M.

Manry at the conclusion of the inspection.

The inspection was an examination of the activities conducted under your

license as they relate to radiation safety and to compliance with the

Commission's rules and regulations and the conditions of your license

The inspection consisted of selective examinations of procedures and

representative records, interviews with personnel, and observations by

the inspector.

We have examined actions you have taken with regard to previously identi-

fied enforcement matters and unresolved items.

The status of these

items is discussed in the enclosed report.

Three new unresolved items resulted from this inspection and are discussed

in the enclosed report.

These items will be examined during subsequent

inspections.

During the inspection, it was found that certain activities under your

license appear to be in noncompliance with Nr.C requirem*nts.

These

items and references to pertinent requiremer ts are listed in the Notice

of Violation enclosed herewith as Appendix A.

This notice is sent to

you pursuant to the provisions of Section 2.201 of the NRC's " Rules of

Practice," Part 2, Title 10, Code of Federal Regulations.

Section 2.201

requires you to submit to this office, within 20 days of your receipt of

this notu e, a written statement or explanation in reply including:

(1)

corrective steps which have been taken by you, and the results achieved;

(2) corrective steps which will be taken to avoid further noncompliance,

and (3) the date when full compliance will be achieved.

In accordance with Section 2.790 of'the NRC's " Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

7 9 01 18 0 Oc) r

.

.

.

.

NOV1 7 77y

Georgia Power Company

-2-

believe to be proprietary, it is necessary that you make a written

application within 20 days to this office to withhold such informatiori

from public disclosure. Any such application must include a full state-

ment of the reasons on the basis of which it is claimed that the informs-

tion is proprietary, and should be prepared so t h.i t proprietary inform.i-

tien identified in the application is containevi in a separate part of

the document.

If we do not hear from you in this regard within the

specified period, the report will be placed in the Public Document Room.

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

,

-

Y

.

F. J. Long, Chief [

. _ Si

M'"

'

Reactor Operations and

Nuclear Support Branch

Enclosure:

Inspection Report Nos. 50-321/78-33 and

50-366/78-41

cc w/ enclosures:

Mr. C. E. Belflower

Site QA Supervisor

Plant E. 1. Hatch

Post Office Box 442

Baxley, Georgia 31513

Mr. M. Manry, Plant Manager

Plant E.

1. Hatch

Post Office Box 442

Baxley, Georgia 31513