Text
.
.
~.
'o
UNITED STATES
!
/n
NUCLEAR REGULATORY COMMISSION
3, )
);E
REGION 11
101 MARIETTA ST., N.W., SUITE 3100
o,
'
ATLANTA, GEORGIA 30303
o
NOV 2 31979
In Reply Refer To:
RII:TJD
50-369/79-36
Duke Power Company
Atta:
W. O. Parker, Jr.
Vice President, Steam Production
Post Office Box 2178
Charlotte, North Carolina 28242
Gentlemen:
This refers to the inspection conducted by Thomas J. Donat of this office on
October 9-11, 1979 of activities authorized by NRC Construction Permit No.
CPPR-83 for the McGuire facility, and to the discussion of our findings held
with M. D. McIntosh at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report. Within these areas, the inspection consisted of
selective. examinations of procedures and representative records, interviews with
personnel, and observations by the inspectors.
Within the scope of this inspection, no items of noncompliance were disclosed.
In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room.
If this
report contains any information that you (or your contractor) believe to be
proprietary, it is necessary that you make a written application within 20 days
to this office to withhold such information from public disclosure. Any such
application must include a full statement of the reasors on the basis of which
it is claimed that the informati n is proprietary, and should be prepared so
that proprietary information identified in the application is contained in a
separate part of the document.
If we do ncu hear from you in this regard within
the specified period, the report will be placed in the Public Document Room.
1648 347
7912280 /8 3
.
.
.
Duke Power Company
-2-
NOV 2 31979
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
,
2.C.
R. C.
ewis, Acting Chief
Reactor Operations and
Nuclear Support Branch
Enclosure:
Inspection Report No. 50-369/79-36
cc w/ enclosure:
M. D. McIntosh, Plant Manager
Post Office Box 488
Cornelius, North Carolina 28031
J. C. Rogers, Project Manager
Post Office Box 33189
Charlotte, North Carolina 28242
1648
348