Forwards IE Insp Repts 50-352/79-06 & 50-353/79-06 on 790618-20 & Notice of Violation
ML19262A161
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 08/28/1979
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Boyer V
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
Shared Package
ML19262A159 List:
References
NUDOCS 7910260458
Download: ML19262A161 (2)


See also: IR 05000352/1979006

Text

s

e

UNITED STATES

ga ng

,

o

NUCLEAR REGULATORY CoMMis5 ION

[

{o

R EGION I

$

/ ,, $

631 PARK AVENUE

f

KING OF PRUS$1A. PENNSYLVANIA 19406

%...../

Docket Nos. 50-352

Al!G 2 0 m g

50-353

Philadelph'. ,.lectric company

ATTN: Mr. V. S. Boyer

Vice President

Engineering and Research

2 M 1 Market Street

Philadelphia, PA 19101

Gentlemen:

Subject:

Inspection 50-352/79-06; 50-353/79-06

This refers to the inspection conducted by Mr. J. Mattia of this office on

June 18-20,1979, at the Limerick Generating Station Units 1 and 2, in

Limerick, Pennsylvania, of activ1

3s authorized by NRC License Nos. CPPR-

106 and CPPR-107 and to the discussions of our findings held by Mr. Mattia

with Mr. Corcoran and others of your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of

Inspection and Enforcement Inspection Report which is enclosed with this

letter. Within these areas, the inspection consisted of selective examinations

of procedures and representative records, interviews with personnel, and

observations by the inspector.

Based on the results of this inspection, it appears that one of your activities

was not conducted in full compliance with NRC requirements, as set forth in

the Notice of Violation, enclosed herewith as Appendix A.

This item of

noncompiiance has been categorized into the levels as described in our

correspondence to you dated December 31, 1974. This notice is sent to you

purse.nt to the provisions of Section 2.201 of the NRC's " Rules of Practice,"

Pac

2, Title 10, Code of Federal Regulations. Section 2.201 requires you

to submit to this office, within thirty (30) days of your receipt of this

notice, a written statement or explanation in reply including (:

(1) corrective

steps which have been taken by you and the results achieved; 25 orrective

steps which will be taken to avoid fur +.her items of noncompliance; and (3)

the date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosures

will be placed in the NRC's Public Document Room.

If this report contains

any information that you (or your contractor) believe to be proprietary, it

7

264

'"

Ur]

7910260

J

.

.

Philadelphia Electric Company

2

is neces c y that you make a written application within 20 days to this

office to withhold such information from public disclosure. Any such

application must be accompanied by an affidavit executed by the owner of

the information, which identifies the document or part sought to be withheld,

anu .iich contains a statement of reasons which addresses with specificity

the items which will be considered by the Comission as listed in subparagraph

(b)(4) of Section 2.790. The information sought to be withheld shall be

incorporated as far as possible into a separate part of the affidavit.

If

we do not hear from you in this regard within the specified period, the

report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be

pleased to discuss them with you.

Sincerely,

flW)i

C

Robert T. Carl

n Chief

Reactor Construction and Engineering

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Office of Inspection and Enforcement Inspection Report

Number 79-06