B ALTIMORE G AS At4D ELECTRIC CCMPANY "O.
BOX 1475 D A LTIM O R E. M A R YL A N D 21203 ARTMun E. LU N OVALL,JR.
vics p.esios=e s..a February 27, 1979 U.S. Nuclear Regulatory Commission Docket Nos.
50-317/50-318 Region I License Nos. DPR-53/DPR-69 631 Park Avenue King of Prussia, Pennsylvania 19406 Attention:
George H. Smith, Chief Fuel Facility and Materials Safety Branch Gentlemen:
This refers to your Inspection Report 50-317/79-02; 50-318/79-02, which transmitted items of apoarent noncompliance with NRC require-ments. Enclosure (1) to this letter is a written statement in reply to the items noted in your letter of February 5,1979.
Should you have further questions regarding this reply, we will be pleased to discuss them with you.
Very truly our
.1 A. E. Lundvall, Jr.
Vice President - Supply AEL/AJK/dds Enclosure 7904020205
ENCLOSURE (1)
REPLY TO APPENDIX A 0F NRC INSPECTION REPORT 50-317/79-02; 50-318/79-02 In response to your finding regarding the incompleteness of the Twelve Month Release Rate Calculation Sheet for the months of November and December 1978, the following actions have been taken.
The procedure which implements the requirement to perform the calcula-tion and complete the sheet, RCPl-207, did not provide a specific time limit to insure completion of this calculation. Therefore, we have revised the procedure to require that the calculation be completed and the results recorded on the sheet within one month following the completion of any twelve consecutive months.
We have given this item particular attention in that the Radiation Safety and Chemistry Engineer will require a monthly report on all release rate calculations to insure compliance with the specifications in RCP1-207.
This action will avoid a further item of noncompliance.
Full compliance is considered to have been achieved.