'4, UNITED STATES
[,,
- ,81 NUCLE AR REGULATORY COMMisslON j l)y j
WASHINGTON, D. C. 20555
%2L'/l
,,/
EARCH I 4 1979 Docket No. 50-293 Mr. G. Carl Andognini Boston Edison Company M/C NUCLEAR 800 Boylston Street Boston, Massachusetts 02199
Dear Mr. Andognini:
Your letter of June 13, 1974 advised us that you had suspended work on the Containment Atmospheric Dilution (CAD) System pending revision to Regulatory Guide 1.7, Control of Combustible Gas Concentrations in Containment Following a Loss-of-Coolant Accident.
Your proposed CAD system was described in Amendment No. 35 to the Pilgrim Nuclear Power Station (PNPS) Unit No.1 Final Safety Analysis Report (FSAR) submitted on January 28, 1974.
You indicated that the proposed CAD system would be reevaluated and modified as appropriate after issuance of the revised Regulatory Guide (RG).
Revision 1 to RG 1.7 was issued for conment in September 1976.
Revision 2 to RG 1.7 was issued in final status 11 November 1978.
Section 4.1.2c Cordrinment Atnosphere Control" of the Final Safety Evaluation Report (SER) for Pilgrim NL ; lear Power Station dated August 25, 1971 indicated that the sti.ff had concluded that a hydrogen control system Viould be provided at 8'NPS and that backfitting the Pilgrim facility in this regard would provide substantial additional protection requirca for the public he alth and safety.
The SER further pointed out that the design and installation of tM system should be achieved in a Feasonab'.e period of tine.
Accordingly, we request that you subrit, within 60.iays of your receipt of this letter, your schedule for the installation and testing of a CAD system at PNPS. Also include in your submittal, a detailed description of any design changes mace to the original FSAR submittal as a result of the revised regulator / guidance.
7 9 0 4 0 '2 01h
t Mr. G. Carl Andognini Your cooperation with us is appreciated.
Sincerely, i-
- l fa g4 [
gdmas "Ippolito, Chief T
Operating Reactors Branch #3 Division of Operating Reactors cc:
see next page
6 Boston Edison Company CC Mr. Paul J. McGuire Pilgrim Station Acting.Ma: auc.-
Boston Edison Company RFD F1, Rocky Hill Road Plymouth, Massachusetts 02360 Anthony Z. Roisman Natural Resources Defense Council 917 15th Street, N. W.
Washington, D. C.
20005 Henry Herrmann, Esquire fiassachusetts Wildlife Federation 151 Tremont Street Boston, Massachusetts 02111 Plymouth Public Library North Street Plymouth, Massachusetts 02360
.