Forwards IE Insp Rept 50-348/79-05 on 790122-24.No Noncompliance Noted
ML19261C085
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 02/21/1979
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Clayton F
ALABAMA POWER CO.
Shared Package
ML19261C083 List:
References
NUDOCS 7903140542
Download: ML19261C085 (2)


See also: IR 05000348/1979005

Text

e

..

  1. "00

UNITED STATES

%'o

NUCtEAR REGULATORY COMMISSION

,

[

REGloN il

5

E

101 MARIETTA STREET. N.W.

'8

ATLANTA, GEORGIA 30303

\\*****/

FEB 2119/3

In Reply Refer To:

RII:RVL

50-348/79-05

Alabama Power Company

Attn:

Mr. F. L. Clayton, Jr.

Senior Vice President

Post Office Box 2641

Birmingham, Alabama 35291

Gentlemen:

This refers to the inspection conducted u,.'ir. R. Vogt-Lowell of this

office on January 22-24, 1979 of activities authorized by NRC License

No. NPF-2 for the Farley facility, Unit 1, and to the discussion of our

findings held with Mr. W. G. Hairston at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in

the enclosed inspection report. Within these areas, the inspection

consisted of selective examinations of procedures and representative

records, interviews with personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were

disclosed.

In accordance with Section 2.790 of the NRC's " Rules of Practice",

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's Public

Document Room.

If this report contains any information that you (or

your contractor) believe to be proprietary, it is necessary that you

make a written application within 20 days to this office to withhold

such information from public disclosure. Any such application must

include a full statement of the reasons on the basis of which it is

claimed that the information is proprietary, and should be prepared so

that proprietary information identified in the application is contained

in a separate part of the document.

If we do not hear from you in this

regard within the specified period, the report will be placed in the

Public Document Room.

7903140541

.

.

.

Alabama Power Company

-2-

FEB 'd I1979

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

/?'.l:.

.

R. C.

ewis, Acting Chief

Reactor Operations and

Nuclear Support Branch

Enclosure:

Inspection Report No. 50-348/79-05

cc w/ enclosure:

Mr. A. R. Barton

Executive Vice President

Alabama Power Company

Post Office Box 2641

Birmingham, Alabama 35291

Mr. H. O. Thrash

Manager-Nuclear Generation

Alabama Power Company

Post Office Box 2641

Birmingham, Alabama 35291

Mr. C. Biddinger, Jr.

Manager-Corporate Quality Assurance

Alabama Power Company

Post Office Box 2641

Birmingham, Alabama 35291

Mr. W. G. Hairston, III

Plant Manager

Farley Nuclear Plant

Drawer 470

Ashford, Alabama 35312

Mr. R. E. Hollands, Jr.

Quality Assurance Supervisor

Farley Nuclear Plant

Post Office Box U

Ashford, Alabama 35312