UNITED STATES t
NUCLEAR REGULATORY COMMISSION
, j REGION lli e
g 799 ROOSEVELT ROAD GLEN E LLYN, ILLINolS 60137 FEB. 23.1979 Docket No. 50-373 Docket No. 50-374 Commonwealth Edison Company ATIN:
Mr. Byron Lee, Jr.
Vice President P. O. Box 767 Chicago, IL 60690 Gentlemen:
This is in response to your letter dated January 29, 1979, informing us of the steps you have taken to correct the noncom-pliance identified in our letter dated December 26, 1978.
With respect to item 1, we have reviewed the supplemental infor-mation in your response and continue to consider the noncompliance valid. We are unable to conclude that the requirements for the mechanical snubbers were specified in purchase specification J-2918 or any other documents available at the ! %e of the inspection.
We will examine your corrective action during a future inspection.
Sincerely, A-James G. Keppl'er __
Director cc:
Mr. L. J. Burke, Site Project Superintendent Mr. T. E. Quaka, QA Supervisor cc w/ltr dtd 1/29/79:
Central Files Reproduction Unit NRC 20b PDR Local PDR NSIC l
TIC Mr. Dean Hansell, Office of Assistant Attorney General 79030705s6