ML19260C253
| ML19260C253 | |
| Person / Time | |
|---|---|
| Site: | Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png |
| Issue date: | 09/18/1979 |
| From: | Brunner E NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Counsil W CONNECTICUT YANKEE ATOMIC POWER CO. |
| Shared Package | |
| ML19260C250 | List: |
| References | |
| NUDOCS 7912260118 | |
| Download: ML19260C253 (2) | |
See also: IR 05000213/1979011
Text
i
T.
UNITED STATES
Sn stoq,}o
.
NUCLEAR REGULATORY COMMisslON
[
R EGloN I
c.
$
$
631 PARK AVENUE
f
KING OF PRUSSI A. PENNSYt.VANIA 19406
0
.... 9
Docket No. 50-213
SEP 181973
Connecticut Yankee Atomic Power Company
ATTN: Mr. W. G. Counsil
Vice President - Nuclear
Engineering and Operations
P. O. Box 270
Hartford, Connecticut 06101
Gentlemen:
Sub, ject:
Inspection 50-213/79-11
This refers to the inspection conducted by Dr. Bettenhausen of this office
on July 17-20, 1979, at the Haddam Neck Plant of activities authorized by
NRC License No. DPR-61 and to the discussions of our findings held by Dr.
Bettenhausen with Mr. Graves of your staff at the conclusion of the inspection,
and to a subsequent telephone discussion between Mr. Graves and Dr. Bettenhausen
on July 26, 1979.
Areas examined during this inspection are described in the Office of
Inspection and Enforcement Inspection Report which is enclosed with this
letter. Within these areas, the inspection consisted of selective examinations
of procedures and representative records, interviews with personnel, and
observations by the inspector.
Based on the results of this inspection, it appears that certain of your
activities were not conducted in full compliance with NRC requirements, as
set forth in the Notice of Violation, enclosed herewith as Appendix A.
These items of noncompliance have been categorized into the levels as
described in our correspondence to you dated December 31, 1974.
This
notice is sent to you pursuant to the provisions of Section 2.201 of the
NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.
Section 2.201 requires you to submit to thb office, within twenty (20)
days of your receipt of this notice, a written statement or explanation in
reply including:
(1) corrective steps which have been taken by you and the
results achieved; (2) corrective steps which will be taken to avoid further
items of noncompliance; and (3) the date when full compliance will be
achieved.
1616
195
- 79122601/8
.
.
Corinecticut Yankee Atomic Power Company
2
SEP 18 M9
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, code of Federal Regulations, a copy of this letter and the enclosures
will be placed in the NRC's Public Document Room.
If this report contains
any information that you (or your contractor) believe to be proprietary, it
is necessary that you make a written application within 20 days to this
office to withhold such infonr.ation from public disclosure. Any such
application must be accompanied by an affidavit executed by the owner of
the information, which identifies the document or part sought to be withheld,
and which contains a statement of reasons which addresses with specificity
the items which will be considered by the Comission as listed in subparagraph
(b)(4) of Section 2.790. The information sought to be withheld shall be
incorporated as far as possible into a separate part of the affidavit.
If
we do not hear from you in this regard within the specified period, the
report will be placed in the Public Document Room.
Should you have any questions concerning this inspecticn, we will Le
pleased to discuss them with you.
Sincerely,
.
-
s
E,
n J. Brunner, Chief
Re ctor Operations and Nuclear
S'upport Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Office of Inspection and Enforcement Inspection Report
Number 50-213/79-11
cc w/encls:
R. Graves, Plant Superintendent
D. G. Diedrick, Manager of Quality Assurance
J. R. Himmelwright, Licensing Safeguards Engineer
1616
196