UNITED STATES
I")
NUCLEAR REGULATORY COMM!SSION
~
o
$
S
REGION 11
n
o,
[
101 MARIETTA ST., N.W.. SUITE 3100
- [
%/
ATLANTA, GEORGIA 30303
Nov - 61979
In Reply Refer To:
RII:JDW
50-416/79-21
50-417/79-21
Mississippi Power and Light Company
ATTN:
N. L. Stampley
Vice President of Production
.P. O. Box 1640
Jackson, MS 39205
Sbd
}22
t
.v-
Gentlemen:
This refers to the special inspection conducted by J. D. Wilcox, Jr. of this
office on August 21 through September 7, 1979 of activities authorized by NRC
Construction Permit Nos. CPPR-118 and CPPR-119 for the Grand Gulf Nuclear
facilities, and to the discussion of our findings held with T. E. Reaves at the
conclusion of the inspection.
Areas examined during the special inspection and our findings are discussed in
the enclosed special inspection report. Within these areas, the special inspec-
tion consisted of selective examinations of procedures and representative records,
interviews with personnel, and observations by the inspector.
Three new unresolved items resulted from this special inspection and are discussed
in the enclosed report.
These items will be examined during subsequent inspections.
During the special inspection, it was found that certain activities under your
license are in noncompliance with NRC requirements. This item and references to
pertinent requirements are listed in the Notice of Violation enclosed herewith
as Appendix A.
This notice is sent to you pursuant to the provisions of
Section 2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of
Federal Regulations.
Section 2.201 requires you to submit to this office,
within 20 days of your receipt of this notice, a written statement or
explanation in reply including:
(1) corrective steps whid have been taken by
you and the results achieved; (2) corrective steps which will be taken to avoid
further noncompliance; and (3) the date when full compliance will be achieved.
In accordance with Scction 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
special inspection report will be placed in the NRC's Public Document Room.
If
this report contains any information that you (or your contractor) believe to be
proprietary, it is necessary that you make a written application within 20 days
to this office to withhold such information from public disclosure. Any such
application must include a full statement of the reasons oc the basis of which
it is claimed that the information is proprietary, and should be prepared so
that proprietary information identified in the application is contained in a
separate part of the document.
If we do not hear frcm you in this regard within
the specified period, the report will be placed in the Public Document Room.
8002040 6 1
.
Mississippi Power and Light
-2-
NOV - 61979
,
Company
Should you have any questions concerning this letter, we will be 8 ad to
1
discuss them with you.
Sincerely,
f
r'
C. E. MurphyM
Reactor Construction and Engineering
Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Special Inspection Report Nos. 50-416/79-21
and 50-417/79-21
cc w/ encl:
C. K. McCoy, Plant Manager
P. O. Box 756
Port Gibson, MS 39150
1864
123