Forwards IE Insp Rept 50-322/79-19 on 791114-15.No Noncompliance Noted
ML19257D019
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 12/11/1979
From: Galen Smith
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Wofford A
LONG ISLAND LIGHTING CO.
Shared Package
ML19257D020 List:
References
NUDOCS 8001310217
Download: ML19257D019 (2)


See also: IR 05000322/1979019

Text

%

'

~

, , , , ,

UNITED STATES

Do

NUCLEAR REGULATORY COMMisslON

3"

' ,$

R EGION I

$

639 PARK AVENUE

f

KING OF PRUS$1 A, PENNSYLV ANIA 19406

\\...../

Docket No. 50-322

g

g3

Long Island Lighting Company

ATTN: Mr. Andrew W. Wofford

Vice President

175 East Old Country Road

Hicksville, New York 11801

Gentl emen:

Subject:

Inspection 50-322/79-19

This refers to the inspection conducted by Mr. D. R. Neely and Mr. J. P. Stohr

of this office on November 14-15, 1979 of activities authorized by NRC License

No. CPPR-95 and to the discussions of our findings held by Mr. D. R. Neely and

Mr. J. P. Stohr at the Shoreham Nuclear Power Station, Unit 1, Shoreham, New

York with Mr. J. Taylor and other members of your staff at the conclusion of the

inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter.

Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations by the

inspector.

Within tha scope of this inspection, no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room.

If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure. Any such application must be

accompanied by an affidavit executed by the owner of the information, which

identifies the document or part sought to be withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparcgraph (b) (4) of Section 2.790.

The information sought to be withheld shall be incorporated as far as possible

into a separate part of the affidavit.

If we do not hear from you in this

regard withiri the specified period, the report will be placed in the Public

Document Room.

1845

168

I

8 0013$ 0 217

ffiLwwf

.

Long Island Lighting Company

2

DEC 111973

No reply to this letter is required; however, should you have any questions

concerning this inspection, we will be pleased to discuss them with you.

Sincere

,

~8 f

[g ' George H. Smith, Chief

Fuel Facility and Materials

Safety Branch

Enclosure: Office of Inspection and

Enforcement Inspection Report Number

50-322/79-19

cc w/ enc):

J. P. Novarro, Project Manager

Edward M. Barrett, Esquire

Edward J. Walsh, Esquire

T. F. Gerecke, Manager, Engineering

QA Department