Responds to NRC Re Violations Noted in IE Insp Rept 50-312/79-20.Corrective Actions:Plant Review Committee Notes Will Be Reviewed by Key Members of Mgt Safety Committee
ML19257C937
Person / Time
Site: Rancho Seco
Issue date: 12/03/1979
From: Mattimoe J
SACRAMENTO MUNICIPAL UTILITY DISTRICT
To: Engelken R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
Shared Package
ML18044B026 List:
References
NUDOCS 8001310104
Download: ML19257C937 (2)


Text

4 e a u

J SACRAVENTO MUNICIPAL UTILITY DISTRICT O 6201 s Street Box 15a30, sacramento, californ'a 95813; (916) 452-3211 December 3, 1979 5

0 EECEr/E0

[' DEC 4 wyg

.].

(

Mr. R. H. Engelken

[

Director of Inspection ch and Enforcement i'

U. S. fluclear Regulatory Corrais: ion

'I 1990 ft. California Boulevard Walnut Creek, California 94596 IE Inspection Report flo. 50-312/79-20

Dear Mr. Engelken:

We have reviewed the notice of violation that one of our activi-ties clas not in full compliance with the condition of our license:

Technical Specifications 6.5.2.7.i requires that the MSRC review reports and minutes of the Plant Review Corrmittee.

The Charter of the Plant Review Corrmittee requires a copy of all proceedings to be sent to the Manager of f uclear Operations, Plant Superinten-dent and the Chairman of the MSRC.

In addition, the Quality Assurance Director is on distribution and annually audits the minutes of the PRC for conformance to the charter and Technical Specifications requirenents.

Any item of concern is brought to the attention of the MSRC by the above four members of the MSRC.

In addition, the Chairman of the PRC is also the Secretary of the MSRC and routinely places on the MSRC agenda any item of disagreement by any member of the PRC that involves a proposed change involving a conflict with or change to the Technical Specifications, or involves an unreviewed safety question as defined by 10CFR50.59.

The Quality Assurance Direct'r via a June 17, 1977 letter expressed his concern on this sarre issue.

Discussions were held in the MSRC and the above stated review prooram was accepted as an adequate review by the MSRC of the PRC.

This action is documented on the August 1,1977 minutes of the MSRC.

Documentary evidence is available by the initialling of the PRC minutes by the Chairman of the MSRC.

Any item that is of concern by the PRC is discussed by the Secretary of the MSRC when he covers the item at the MSRC rrecting.

1843 2b8 8001310 /04 AN ELECTRIC SYSTEY S E RVIN G MORE THAN 600,000 IN THE HEART OF calif 0fN!A v.16

Mr. R. H. Engelken Decerber 3, 1979 It is the position of the District that we meet the intent of this commitment and do not agree that the finding has substance,

e welcome the NRC inspector's review of our approach and look forward to discussions regarding this issue.

Sincerely yours, "lrA

. />M, [we J, J. Matticoe Assistant General Manager and Chief Engineer 1843 269 i