Text
f0
'o,,
UNITED STATES
'O NUCLJAR REGULATORY COMMISSION n
4 g
e REGION ll o,
[
101 MARIETTA ST., N.W., SUITE 3100 ATLANTA, GEORGIA 30303 o
OCT 2 91979 In Reply Refer To:
RII:JPO 50-348 Alabama Power Company Attn:
F. L. Clayton Senior Vice President Post Office Box 2641 Birmingham, Alabama 35291 Gentlemen:
The enclosed Bulletin No. 79-17, Revision 1 is forwarded to you for action. A written response is required.
If you desire additional information regarding this matter, please contact this office.
Sincerely, O
,) y
_3 :
James P. O'Reilly Director
Enclosure:
IE Bulletin No. 79-17, Revision I w/ enc 1s.
s r
1336 321 7911150/3 I 9
OCT 2 91979 Alabama Power Company.
cc w/ enc 1:
A. R. Barton Executive Vice President Post Office Box 2641 Birmingham, Alabama 35291 J. T. Young Vice President-Production Post Office Box 2641 Birmingham, Alabama 35291 C. Biddinger, Jr.
Manager-Corporate Quality Tssurance Post Office Box 2641 Birmingham, Alabama 35291 H. O. Thrash Manager-Nuclear Generation Post Office Box 2641 Birmingham, Alabama 35291 H. G. Hairston, III Plant Manager Drawer 470 Ashford, Alabama 36312 R. E. Hollands, Jr.
QA Supervisor Post Office Bcx U Ashtcrd, Alabama 36312 1336 322
UNITED STATES SSINS No.: 6820 NUCLEAR REGULATORY COMMISSION Accession No.:
OFFICE OF INSPECTION AND ENFORCEMENT 79082201'57 WASHINGTON, D.C.
20555
.3 October 29, 1979 IE Bulletin No. 79-17 Revision 1 PIPE CRACKS IN STAGNANT BORATED WATER SYSTEMS AT PWR PLANTS Description of Circumstances:
IE Bulletin No. 79-17, issued July 26, 1979, provided informaticn on the cracking R1 experienced to date in safety-related stainless steel piping syste.n at PWR R1 plants. Certain actions were required of all PWR facilities with an operating R1 license within a specified 90-day time frame.
R1 After several discussions with licensee owner group representatives and inspection R1 agencies, it has been determined that the requirements of Item 2, particularly R1 the ultrasonic examination, may be impractical because of unavailability of R1 qualified personnel in certain cases to complete the inspections within the time R1 specified by the Bulletin. To alleviate thi situation and allow licensees the R1 resources of improved ultrasonic inspection capabilities, a time extension and R1 clarifications to the bulletin have been made. These are referenced to the R1 affected items of the original bulletin.
R1 During the period of November 1974 to February 1977 a number of cracking incidents have been experienced in safety-related stainless steel piping systems and por-tions of systems which contain oxygenated, stagnant or essentielly stagnant bor-ated water. Metallurgical investigations revealed these cracks occurred in the weld heat affected zone of 8-inch to 10-ir.n type 304 material (schedule 10 and 40), initiating on the piping I.D. surface and propagating in either an inter-granular or transgranular mode typical of Stress Corrosion Cracking. Analysis indicatad the probable corrodents to be chloride and oxygen contamination in the affected systems. Plants affected up to this time were Arkansas Nuclear Unit 1, R. E. Ginna, H. B. Robinson Unit 2, Crystal River Unit 3, San Onofre Unit 1, and Surry Units 1 and 2.
The NRC issued Circular No. 76-06 (copy enclosed) in view of the apparent generic nature of the problem.
During the refueling outage of Three Mile Island Unit I which began in February of this year, visual inspections disclosed five (5) through-wall cracks at welds in the spent fuel cooling system piping and one (1) at a weld in the decay heat removal system. These cracks were found as a result of local boric acid buildup and later confirmed by liquid penetrant tests. This initial identification of cracking was reported to the NRC in a Licensee Event Report (LER) dated May 16, 1979. A preliminary metallurgical analy section of cracked and leaking weld join DUPLICATE DOCUMENT R1 - Identifies those additions or revis Entire document previously entered into system und 1 }
suo7h.,igyygg/f7 13 o/