ML19256D040

From kanterella
Jump to navigation Jump to search
Forwards for Review NRC 760323 Memo Re Licensee Acceptance Criteria for Initial Core Loading.Requests Examination of Routine Opening Force Tests of Vent Valves During Refueling Outages
ML19256D040
Person / Time
Site: Oconee, Davis Besse  Duke Energy icon.png
Issue date: 03/29/1976
From: Knop R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Seyfrit K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
Shared Package
ML19256D037 List:
References
NUDOCS 7910160765
Download: ML19256D040 (1)


Text

.

  • ~

UN11ED STATES NUCLEAR REGULATORY COMMISSION REGION lit 799 ROOSEVELT Ro AD CLEN ELLYN, ILLINOl$ 60137 March 29, 1976 K. V. Seyfrit, Chief, Reactor Technical Assistance Branch Office of Inspection and Enforcement, Headquarters G. Fiorelli, Chief, Reactor Operations and Nuclear Support Branch INTERNAL VENT VALVE REQUIREYINTS It is requested that you review the attached letter from R. D. tiartin to determine if the acceptance criteria being used by the licensee is acceptable for initial core loading.

In addition, it is requested that you pursue with NRR the desirability of routine opening force tests of these vent valves during subsequent refueling outages.

h M'

R. C. Knop, Chief Reactor Projects Section 1

Attachment:

As stated cc w/ attachment:

B. H. Grier, IE:HQ D. Thompson, IE:HQ G. W. Roy, IE:HQ R. F. Warnick, Regional Coordinator

(

1446 04E 59101607[3 G

=-

3

/

m R. C. Knop March 23, 1976 1.

I will inform the licensee that he should obtain sufficient design information and acceptance criteria guidar.ce from B&W to enable the evaluation of the proper performance of these valves using the lift forces measured or to provide an alternate testing method which will demonstrate their operability.

2.

Headquarters should be informed of this problem to determine if:

a.

Specific acceptance criteria should be included in the Davis-Besse Technical Specifications for the 18 month testing of these valves.

b.

Similar requirements exist or should be added to other B&W facilities using internals vent valves.

Unless I hear to the contrary, I will inform the licensee of the need for additional information.

Other actions will await your decision to bring this matter to the attention of Headquarters.

.~dR R. D. Martin Reactor Inspector Reactor Projects Section 1

/

4 5 l wp --*