Forwards Insp Repts 50-424/78-06 & 50-425/78-06 on 780828-29.No Noncompliance Noted
ML19256A084
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 10/02/1978
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
Shared Package
ML19256A083 List:
References
NUDOCS 7811030047
Download: ML19256A084 (2)


See also: IR 05000424/1978006

Text

e

.

,

e

UNITED sT ATES

ja5 *f 4q'c,

NUCLE AR REGULATORY COMMISSION

[j

8

" _

?'

REGION !!

$-

$

101 M AR IE TT A ST R E E T . N.W

f

ATt. ANT A. GE oRGI A 30303

OCT 0 2 T378

'

'

  • ...*

In Reply Refer To:

Ell:JKR

50-424/76-6

50-425/78-6

_

-

Georgia Power Company

Attn:

Mr. J. H. Miller, Jr.

Executive Vice President

270 Peachtree Street, N. W.

Atlanta, Georgia

30303

Gentlemen:

This refers to the inspection conducted by Mr. J. K. Rausch of this

office on August 28-29, 1978, of activities authorized by NRC Construction

Permit Nos. CPPR-108 and CPPR-109 for the Alvin W. Vogtle Nuclear Plant,

Units 1 and 2 facilities, and to the discussion of our findings held

with Mr. K. Gillespie at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in

the enclosed inspection report. Within these areas, the inspection

consisted of selective examinations of procedures and representative

records, interviews with personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were

disclosed.

We have examined actions you have taken with regard to previously

identified unresolved items. The status of these items is discussed in

the enclosed report.

One new unresolved item resulted from this inspection and is discussed

in the enclosed report. This item will be examined during subsequent

inspections.

In accordance with Section 2.790 of the NRC's " Rules of Practice",

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's Public

Document Room.

If tais report contains any information that you (or

your contracter) believe to be proprietary, it is necessary that you

..

a

&

.

.,

.

.

.

.

OCT C $ 1973

Georgia Power Company

-2-

make a written application within 20 days tc this office to withhold

such information from public disclosure.

Any such application must

include a full statement of the reasons on the basis of which it is

claimed that the information is proprietary, acd should be prepared so

, that proprietary information identified in the application is contained

in a separate part of the document.

If we do not hear from you in this

regard within the specified period, the report will be placed in the

Public Document Room.

Should you have any questions concerning this letter, we will be glad

to discuss them with you.

Sincerely,

C. E. Murphy, j& Chief!

Reactor Construction and

Engineering Support Branch

Encle;ure.

Inspection Report Nos.

50-424/78-6 and 50-425/78-6

cc w/ encl:

Mr. W. M. Johnston

Project Construction Manager

Vogtle Nuclear Plant

P. O. Box 282

Waynesboro, Georgia 30830

..