Letter Sequence Acceptance Review |
---|
|
|
MONTHYEARML19254F6912019-09-10010 September 2019 NRR E-mail Capture - LIC-109 Acceptance of Point Beach Nuclear Plant, Unit 2 Relief Request 2-RR-17 - EPID L-2019-LLR-0084 Project stage: Acceptance Review ML19270D0262019-10-0101 October 2019 Request for Withholding Information from Public Disclosure for Point Beach Nuclear Plant, Unit 2 - Relief Request 2-RR-17, Extension of the Primary Nozzle Dissimilar Metal (DM) Weld Inspection Interval Project stage: Withholding Request Acceptance ML19339H7472019-12-13013 December 2019 Approval of Relief Request 2-RR-17 Regarding Steam Generator Primary Nozzle Dissimilar Metal Welds Inspection Interval Project stage: Other 2019-12-13
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML23271A1542023-09-28028 September 2023 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program ML23208A3072023-07-27027 July 2023 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Relief Requests Regarding I6-RR-1, I6-RR-2, and I6-RR-3 (EPIDs L-2023-LLR-0030, L-2023-LLR-0031, L-2023-LLR-0032) ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23136A2782023-05-0505 May 2023 Email to R Coffey Point Beach SLRA Second Annual Update - Request for Additional Information Set 1 ML23122A0132023-05-0101 May 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding Risk-Informed Approach to Address GSI-191 ML23109A1862023-04-19019 April 2023 and Turkey Point Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23033A0292023-01-31031 January 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI (Volume 2) - License Amendment Request Regarding TSTS-505 ML22354A1612022-12-20020 December 2022 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding TSTS-505 ML22291A3692022-10-18018 October 2022 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of License Amendment Request to Use Beacon Power Distribution Monitoring System ML22249A0052022-09-0202 September 2022 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of License Amendment and Exemptions Regarding Risk-Informed Approach to Address GSI-191 ML22229A1052022-08-17017 August 2022 Response to Questions Regarding Point Beach Nuclear Power Plant with Attachment ML22229A1022022-07-18018 July 2022 Original Request - Questions Regarding Point Beach Nuclear Power Plant ML22196A0062022-07-15015 July 2022 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Requested Licensing Action TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - RITSTF Initiative 4b ML22094A0802022-04-0404 April 2022 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-366 ML22006A2762022-01-0606 January 2022 SLR - FW: Subsequent License Renewal of Point Beach Nuclear Plant Unit Numbers 1 and 2, Manitowoc County, Wisconsin ML22006A1952022-01-0606 January 2022 SLR - FW: (External_Sender) 3 Additional Organizations Endorsing the Coalition (Now 50 Organizations, and 27 Individuals) Public Comments NRCs Dsgeis on NextEra Point Beach Nuclear Power Plant Subsequent License Renewal, D ML22006A2012022-01-0606 January 2022 SLR - FW: Comments of Michael J Keegan on Dseis Point Beach ML22004A1672022-01-0404 January 2022 SLR - Ref: Point Beach ML22004A3192022-01-0404 January 2022 SLR - FW: Point Beach ML22004A0012022-01-0404 January 2022 SLR - FW: Comments of Michael J Keegan on Dseis Point Beach ML22006A1942022-01-0404 January 2022 SLR - (External_Sender) 3 Additional Organizations Endorsing the Coalition (Now 50 Organizations, and 27 Individuals) Public Comments NRCs Dsgeis on NextEra Point Beach Nuclear Power Plant Subsequent License Renewal, Docke ML22004A3212022-01-0404 January 2022 SLR - FW: Comments of Michael J Keegan on Dseis Point Beach ML22004A3202022-01-0404 January 2022 SLR - FW: (External_Sender) 3 Additional Organizations Endorsing the Coalition (Now 50 Organizations, and 27 Individuals) Public Comments NRCs Dsgeis on NextEra Point Beach Nuclear Power Plant Subsequent License Renewal, D ML22004A1732022-01-0404 January 2022 SLR - FW: (External_Sender) 3 Additional Organizations Endorsing the Coalition (Now 50 Organizations, and 27 Individuals) Public Comments NRCs Dsgeis on NextEra Point Beach Nuclear Power Plant Subsequent License Renewal, D ML22004A3182022-01-0404 January 2022 SLR - FW: EPA Comment Letter - Point Beach SEIS ML22006A1992022-01-0303 January 2022 SLR - (External_Sender) Comments of Michael J Keegan on Dseis Point Beach ML22004A3172021-12-21021 December 2021 SLR - (External_Sender) EPA Comment Letter - Point Beach SEIS ML21362A6822021-12-17017 December 2021 SLRA Safety RAIs Set 14 Final Email ML21362A6712021-12-15015 December 2021 SLRA Safety RAIs Set 13 Final Email ML22006A2752021-12-0202 December 2021 SLR - (External_Sender) Subsequent License Renewal of Point Beach Nuclear Plant Unit Numbers 1 and 2, Manitowoc County, Wisconsin ML21341A6102021-11-16016 November 2021 SLRA Safety RAI Set 12 Final Email ML21314A4212021-11-10010 November 2021 Fws to NRC, Concurrence with ESA Determination for Point Beach Subsequent License Renewal ML21307A1522021-11-0909 November 2021 NRC to Fws, Request for Concurrence with Endangered Species Act Determinations for Point Beach Subsequent License Renewal ML21287A0852021-10-14014 October 2021 SLRA Safety RAI Set 11 Final Email ML21279A1202021-10-0505 October 2021 Email: Wi Shpo Review Point Beach Nuclear Plant SLR ML21286A6032021-10-0505 October 2021 SLRA Safety RAIs Set 10 Final Email ML21273A0232021-09-0202 September 2021 SLRA Safety RAI Set 9 Final Email ML21242A2282021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 ML21242A2292021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 Email ML21242A2462021-08-26026 August 2021 SLRA Safety RAIs Set 8 Final Email ML21242A2222021-08-23023 August 2021 SLRA Draft Safety RAI Set 8 ML21242A2232021-08-23023 August 2021 SLRA Draft Safety RAI Set 8 Email ML21242A2192021-08-20020 August 2021 SLRA Safety RAI Set 7 Final Email ML21242A2132021-08-13013 August 2021 SLRA Safety RAIs Set 7 Draft Email ML21242A2142021-08-13013 August 2021 SLRA Safety RAIs Set 7 Draft ML21242A2042021-08-12012 August 2021 SLRA Safety RAIs Set 5 Final Email ML21224A2042021-08-12012 August 2021 LTR-21-0225-1-RIII. Time Sensitive: Request for Further Inspection ML21242A0142021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final Email ML21242A2382021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final Email ML21242A0112021-08-0909 August 2021 SLRA Draft Safety RAIs Set 6 Email 2023-09-28
[Table view] |
Text
NRR-DRMAPEm Resource From: Chawla, Mahesh Sent: Tuesday, September 10, 2019 5:05 PM To: Schultz, Eric Cc: Catron, Steve (Steve.Catron@fpl.com); Mack, Jarrett; Schneider, Thomas
Subject:
LIC-109 Acceptance of Point Beach Nuclear Plant, Unit 2 Relief Request 2-RR EPID L-2019-LLR-0084
Dear Mr. Schultz:
By letter dated August 29, 2019 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML19241A492), NextEra Energy Point Beach, LLC (NextEra) (the licensee) submitted a relief request for Point Beach Nuclear Plant (PBNP), Unit 2. Pursuant to 10 CFR 50.55a(z)(1), NextEra is requesting Nuclear Regulatory Commission (NRC) approval of the proposed extension to Code Case N-770-2, Table 1, Inspection Item A-2, volumetric examination from every 5 years and Inspection Item B, volumetric examination from every second inspection period not to exceed 7 years. The extension requested is for a period not to exceed one refueling outage. The examination will be performed no later than the Fall 2021 refueling outage (U2R38), approximately 9 years from the previous examination (U2R32 in November 2012).
The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Pursuant to Sections 50.55a(z)(1) and 50.55a(z)(2) of Title 10 of the Code of Federal Regulations (10 CFR),
the applicant shall demonstrate that the proposed alternatives would provide an acceptable level of quality and safety, or that compliance with the specified requirements of Section 50.55a would result in hardship or unusual difficulty without a compensating increase in the level of quality or safety. The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.
1
Based on the information provided in your submittal and discussions during the pre-application public teleconference held on August 14, 2019 (see ADAMS Accession No. ML19246A624 for meeting summary),
the NRC staff has estimated that this licensing request will take approximately 200 hours8.333 days <br />1.19 weeks <br />0.274 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months, which is August 13, 2020. The completion date is based on NRCs normal timeline for review of relief requests in 12 months. However, since licensees requested date in the application is December 31, 2019, NRC staff will make every effort to meet this date to support the upcoming refueling outage for PBNP Unit 2. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, and unanticipated addition of scope to the review.
If you have any questions, please contact me, at (301) 415-8371.
Sincerely, Mahesh Chawla, Project Manager LPL3 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-301 2
Hearing Identifier: NRR_DRMA Email Number: 195 Mail Envelope Properties (BN6PR09MB1265DBAE3EFB26B283CBB58EF1B60)
Subject:
LIC-109 Acceptance of Point Beach Nuclear Plant, Unit 2 Relief Request 2-RR EPID L-2019-LLR-0084 Sent Date: 9/10/2019 5:04:44 PM Received Date: 9/10/2019 5:04:00 PM From: Chawla, Mahesh Created By: Mahesh.Chawla@nrc.gov Recipients:
"Catron, Steve (Steve.Catron@fpl.com)" <Steve.Catron@fpl.com>
Tracking Status: None "Mack, Jarrett" <Jarrett.Mack@fpl.com>
Tracking Status: None "Schneider, Thomas" <Thomas.Schneider@nexteraenergy.com>
Tracking Status: None "Schultz, Eric" <Eric.Schultz@nexteraenergy.com>
Tracking Status: None Post Office: BN6PR09MB1265.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 4096 9/10/2019 5:04:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: