Responds to NRC 790911 Ltr Re Violations Noted in IE Insp Repts 50-424/79-14 & 50-425/79-14.Corrective Actions:Proper Testing for Concrete QA re-emphasized.Monitoring of Concrete Operations Increased
ML19254F583
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 10/05/1979
From: Dutton D
GEORGIA POWER CO.
To: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19254F581 List:
References
NUDOCS 7911120076
Download: ML19254F583 (2)


Text

i Georgia Power Cornpany Post Office Box 4545 Atlanta, Georgia 303o2 b

Telephone 404 522-606o p n, Vogtle Proj.ect

.i U Southern Cornpany Services, Inc.

Post Offce Box 2625 Barrmngharn, Alabarna 35202 Telephone 205 870-60n Octobee 5, 1979 United States Nuclear Regulatory Commission

REFERENCE:

Office of Inspection and Enforcement IE: II: MDH Region II - Suite 3100 50-424/79-14 101 Marietta Street 50-425/79-14 Atlanta, GA 30303 File: X7BG10 Log: GM-508 Attention: Mr. C. E. Murphy Gentlemen:

The Georgia Power Company wishes to submit the following information concerning the noncompliance discussed in your inspection report number 50-424/79-14 and 50-425/79-14.

Our response to inspection report 50-424/425/78-9 outlined the method Plant Vogtle would use for collecting concrete test samples. Quality Control personnel were trained and have implemented this method.

The proper testing procedure for concrete has been re emphasized to the Civil Q. C. Inspection Supervisor responsible for Quality Control activities for paur Nos. A-080-135 and A-080-153. All Civil Q.C. Personnel were informed of the noncompliance and reminded of the need for studying and following all applicable procedures in the inspection of the work. Quality Assurance has increased their monitoring of concrete operations to assure that concrete sam-pling complies with the procedures. Full compliance to concrete placement and testing procedures was accomplished October 4, 1979.

Neither the in"pection report nor this reply contain any proprietary information and may be placed in the NRC's Public Documer.t Rooms.

Very truly yours, Doug Dutton Project General Manager CWH:tp

.7 1 7, L?. L-9 7911120 O M 790/(g k FlCIA ,,

P United States fluclear Regulatory Commission Mr. C. E. Murphy October 5. 1979 Page 2 xc: fi. D. Hunt - Region II J. H. f1 iller, Jr.

W. E. Ehrensperger F. G. Mitchell, Jr.

C. F. Whitmer R. J. Kelly R. E. Conway R. U. Staffa C.11. Hayes W. fl. Johnston, Jr.

C. R. fiiles, Jr.

D. L. ficCrary R. A. Thomas J. A. Bailey J. L. Leamon H. A. Sindt B. L. Lex K. fi. Gillespie E. D. Groover 1311 323