ML19254F039
| ML19254F039 | |
| Person / Time | |
|---|---|
| Site: | Dresden |
| Issue date: | 09/25/1979 |
| From: | Fiorelli G NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Brian Lee COMMONWEALTH EDISON CO. |
| Shared Package | |
| ML19254F040 | List: |
| References | |
| NUDOCS 7911050430 | |
| Download: ML19254F039 (2) | |
See also: IR 05000010/1979018
Text
(
.* * t ooq'o'
UNITED STATES
U
.
!"
'n
NUCLEAR REGULATORY COMMISSION
3
$
.E
REGION lli
%
/[
A
o,
799 ROOSEVELT ROAD
I
JALEN ELLYN.1LLINOIS 60137
SEP 2 51979
Docket No. 50-10
Docket No. 50-237
Docket No. 50-249
Commonwealth Edison Company
ATTN:
Mr. Byron Lee, Jr.
Vice President
P. O. Box 767
Chicago, IL 60690
Gentlemen:
This refers to the inspection conducted by Mr. I. T. Yin of this office
on September 12, 1979, of activities at Dresden Nuclear Power Station
authorized by NRC Operating Licenses No. DPR-2, No. DPR-19 and No. DPR-25
and to the discussion of our findings with Mr. R. Ragan and others at the
conclusion of the inspection.
The enclosed copy of our inspection report identifies areas examined
during the inspection. Within these areas, the inspection consisted of a
selective examination of procedures and representative records, obsermtions,
and interviews with personnel.
No items of noncompliance with NRC requirements were identified during
the course of this inspection.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the
enclosed inspection report will be placed in the NRC's Public Document
Room, except as follows.
If this report contains information that you or
your contractors believe to be proprietary, you must apply in writing to
this office, within twenty days of your receipt of this letter, to
withhold such information from public disclosure. The application must
include a full statement of the reasons for which the information is
considered proprietary, and should be prepared so that proprietary
information identified in the application is contained in an enclosure to
the application.
1268 218
1268
7'
7 '9 1 10594-30
.
Comonwealth Edison Company
-2-
SEP " " N7']
We will gladly discuss any questions you have concerning this
inspection.
Sincerely,
A
Y
af **
'Gaston Fiorelli,' Chief
Reactor Construction and
Engineering Support Branch
Enclosure:
IE Inspection
Reports No. 50-10/79-18,
No. 50-237/79-21 and
No. 50-249/79-19
cc w/ encl:
Mr. B. B. Stephenson, Station
Superintendent
Central Files
Reproduction Unit NRC 20b
Local PDR
Anthony Roisman, Esq.,
Attorney
Mr. Dean Hansell, Office of
Assistant Attorney General
1268 219