r.
d*
[pn arcq
o
UNITED STATES
! }
3 .,,
NUCLEAR REGULATORY COMMISSION
'
,
e
REGION 11
o.
8
101 MARIETT A sT . N.W., SUITE 3100
ATLANTA, GEORGIA 30303
- ...*
In Reply Refer To:
M 29 M
-
-
RII:TDG
50-370/79-15
Duke Power Company
Attn:
W. O. Parker, Jr.
Vice President, Steam Production
Post Office Box 2178
Charlotte, North Carolina 28242
Gentlemen:
This refers to the inspection conducted by T. D. Gibbons of this office
on August 8-10, 1979 of activities authorized by NRC Construction Permit
No. CPPR-84 for the McGuire Nuclear Plant facility, Unit No. 2, and to
the discussion of our findings held with G. W. Grier at the conclusion
of the inspection.
Areas examined during the inspection and our findings are discussed in
the enclosed inspection report. Within these areas, the inspection
consisted of selective examinations of procedures and representative
records, interviews with personnel, and observationt by the inspector.
During the inspection, it was found that certain activities under your
license appear to be in noncompliance with NRC requirements. This item
and references to pertinent requirements are listed in the Notice of
Violation enclosed herewith as Appendix A.
This notice is sent to you
pursuant to the provisions of Section 2.201 of the NRC's " Rules of
Practice", Part 2, Title 10, Code of Federal Regulations. Section 2.201
requires you to submit to this office, within 20 days of your receipt of
this notice, a written statement or uplanation in reply including:
(1)
corrective steps which have been taken by you, and the results achieved;
(2) corrective steps which will be taken to avoid further noncompliance;
and (3) the date when full compliance will be achieved.
In accordance with Section 2.790 of the NRC's " Rules of Practice,"
Part 2, Title 10, Code of Federal Regulations, a copy of this letter and
the enclosed inspection report will be placed in the NRC's Public Document
Room.
If this report contains any information that you (or your contractor)
believe to be proprietary, it is necessary that you make a written
application within 20 days to this office to withhold such information
from public disclosure. Any such application must include a full statement
of the reasons on the basis of which it is claimed that the information
is proprietary, and should be prepared so that proprietary information
identified in the application is contained in a separate part of the
'
1209
312
=
7910250 @
-
.
.
Duke Power Company
-2-
AUG 2 91979
.
document.
If we do not hear from you in this regard within the specified
period, the report will be placed in the Public Document Room.,
'.
Should you have any questions con _erning this letter, we will be glad to
discuss them with you.
Sincerely,
,
.'
,
C. E. Murph ,
ief
Reactor Construction and
Engineering Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report No. 50-370/79-15
cc w/ enclosure:
M. D. McIntosh, Plant Manager
Post Office Box 488
Cornelius, North Carolina 28031
J. C. Rogers, Project Manager
Post Office Box 33189
Charlotte, North Carolina 28242