Text
,
.
f
pnatog
'
jo
UNITED STATES
3
NUCLEAR REGULATORY COMMISSION
+r
REGION 11
.
o,
[
101 MARIETTA ST., N.W., SUITE 3100
- g
ATLANTA, GEORGIA 30303
OCT 241979
In Reply Refer To:
RII:TEB
50-395/79-30
South Carolina Electric and Gas Company
ATTN:
M. C. Johnson, Vice President
Special Services and Purchasing
P. O. Box 764
Columbia, S C 29218
Gentlemen:
This refers to the inspection conducted by T. E. Burdette of this office on
October 1-4, 1979 of activities authorized by NRC Construction Permit No.
CPPR-94 for the Virgil C. Summer Nuclear facility, and to the discussion of our
findings held with E. H. Crews at the conclusion of the inspection.
Ar.-as examined during the inspection and our findings are discussed in the
enclosed inspection report. Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
parsonnel, and observations by the inspectors.
We have examined actions you have taken with regard to previously reported
unresolved items. The status of these items is discussed in the enclosed
report.
During the inspection, it was found that certain activities under your license
appear to be in noncompliance with NRC requirements. This item and references
to pertinent requirements are listed in the Notice of Violation enclosed here-
with as Appendix A.
This notice is sent to you rursuant to the provisions of
Section 2.201 of the NRC's " Rules of Practice " Part 2, Title 10, Code of Federal
Regulations. Section 2.201 requires you to r.ab. nit to this office, within 20
days of your receipt of this notice, a written statement or explanation in reply
including:
(1) corrective steps which have been taken by you and the results
achieved; (2) corrective steps s .ch will be taken to avoid further noncom-
pliance; and (3) the date when full cc,mpliance will be achieved.
In accordance with Section 2.790 of the NRC'c " Rules of Practice," Part 2,
Title 10, Code of Jederal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room.
If this
report contains any information that you (or your contractor) believe to be
proprietary, it is necessary that you make a written application within 20 days
to this office to withhold such information from public disclosure. Any such
application must include a full statement of the reasons on the basis of which
it is claimed that the information is proprietary, and should be prepared so
that proprietary information identified in the application is contained in a
separate part of the document.
If we do not hear from you in this regard within
the specified period, the report will be placed in the Public Document Room.
1506 010
7912060
- 8PF
-
o
South Carolina Electric and Gas
-2-
-
Company
OCT 2 41979
Should you have any questions concerning this letter, we will be glad to
discuss them with you.
Sincerely,
9
'E. Nurp
v.
Reactor Construction and Engineering
Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report No. 50-395/79-30
cc w/ encl:
T. B. Cenners, Jr.
Conners, Moore and Corber
1747 Pennsylvania Avenue, N. W.
Washington, D C 20006
A. A. Smith
Quality Assurance
P. O. Box 8
Jenkinsville, S C 29065
O. S. Bradham, Manager
1506 01i
Nuclear Operations
P. O. Box 8
Jenkinsville, S C 29065