Forwards IE Insp Rept 50-395/79-30 on 791001-04 & Notice of Violation
ML19253C619
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 10/24/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Mary Johnson
SOUTH CAROLINA ELECTRIC & GAS CO.
Shared Package
ML19253C616 List:
References
NUDOCS 7912060587
Download: ML19253C619 (2)


See also: IR 05000395/1979030

Text

,

.

f

pnatog

'

jo

UNITED STATES

3

NUCLEAR REGULATORY COMMISSION

+r

REGION 11

.

o,

[

101 MARIETTA ST., N.W., SUITE 3100

          • g

ATLANTA, GEORGIA 30303

OCT 241979

In Reply Refer To:

RII:TEB

50-395/79-30

South Carolina Electric and Gas Company

ATTN:

M. C. Johnson, Vice President

Special Services and Purchasing

P. O. Box 764

Columbia, S C 29218

Gentlemen:

This refers to the inspection conducted by T. E. Burdette of this office on

October 1-4, 1979 of activities authorized by NRC Construction Permit No.

CPPR-94 for the Virgil C. Summer Nuclear facility, and to the discussion of our

findings held with E. H. Crews at the conclusion of the inspection.

Ar.-as examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

parsonnel, and observations by the inspectors.

We have examined actions you have taken with regard to previously reported

unresolved items. The status of these items is discussed in the enclosed

report.

During the inspection, it was found that certain activities under your license

appear to be in noncompliance with NRC requirements. This item and references

to pertinent requirements are listed in the Notice of Violation enclosed here-

with as Appendix A.

This notice is sent to you rursuant to the provisions of

Section 2.201 of the NRC's " Rules of Practice " Part 2, Title 10, Code of Federal

Regulations. Section 2.201 requires you to r.ab. nit to this office, within 20

days of your receipt of this notice, a written statement or explanation in reply

including:

(1) corrective steps which have been taken by you and the results

achieved; (2) corrective steps s .ch will be taken to avoid further noncom-

pliance; and (3) the date when full cc,mpliance will be achieved.

In accordance with Section 2.790 of the NRC'c " Rules of Practice," Part 2,

Title 10, Code of Jederal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application within 20 days

to this office to withhold such information from public disclosure. Any such

application must include a full statement of the reasons on the basis of which

it is claimed that the information is proprietary, and should be prepared so

that proprietary information identified in the application is contained in a

separate part of the document.

If we do not hear from you in this regard within

the specified period, the report will be placed in the Public Document Room.

1506 010

7912060

  1. 8PF

-

o

South Carolina Electric and Gas

-2-

-

Company

OCT 2 41979

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

9

'E. Nurp

v.

Reactor Construction and Engineering

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report No. 50-395/79-30

cc w/ encl:

T. B. Cenners, Jr.

Conners, Moore and Corber

1747 Pennsylvania Avenue, N. W.

Washington, D C 20006

A. A. Smith

Quality Assurance

P. O. Box 8

Jenkinsville, S C 29065

O. S. Bradham, Manager

1506 01i

Nuclear Operations

P. O. Box 8

Jenkinsville, S C 29065