Appendix A NOTICE OF DEVIATION Toledo Edison Company Docket No. 50-346 Based on the inspection conducted on June 12-15, 1979, it appears that certain of your activities were not in accordance with commitments, codes, standards, guides or acceptable practices, as noted below.
Section 6.2 of the Emergency Plan and Implementing Procedures Manual states in part that, "The Station Review Board will review the Emergency Plan annually."
Contrary to this commitment, the licensee failed to conduct this review for the period ending April 25, 1979.
i k
<g )
,9o9130 0
_1_2 _
JUL 2 5 079 Toledo Edison Company 2_
i We will gladly discuss any questions you have concerning this inspecticn.
Sincerely, (1 Gou a A. B. Davis, Chief Fuel Facility and Materials Safety Branch
Enclosures:
1.
Appendix A, Notice of Deviation 2.
IE Inspection Report No. 50-346/79-14 cc w/encls:
Mr. T. D. Murray, Station Superintendent Central Files Reproduction Unit NRC 20b PDR Local PDR NSIC TIC Harold W. Kohn, Power Siting Commission Helen W. Evans, State of Ohio k
\\