g - pg
!'g ",,,,/ [ [j
,y,(f
,%-
REGION 11
,
'
101 MARIETTA ST., NW, sulTE 31op f
-
s
o, 4
ATLANT A, GEORGIA 30303
' b-
g
,
.....
AUG 7
1979
./
/
In Reply Refer To:
s
RII:MSK
50-338/79-31
50-339/79-39
Virginia Electric and Power Company
ATTN:
W. L. Proffitt
Senior Vice President, Power
P. O. Box 2t'66
Richmond, VA 23261
Gentlemen:
This refers to the inspection conducted by M. S. Kidd of this office on June 25 -
July 13, 1979, of activities authorized by NRC License No. NPF-4 and Construction
Permit No. CPPR-78 for the North Anna Unit I and 2 facilities, and to the discus-
sion of our findings held with W. R. Cartwright and other members of your staff
periodically during the inspection.
Areas exar ined during the inspection and our findings are discussed in the
enclosed inspection report. Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
Within the scope of this inspection, no items of noncompliance were disclosed.
We have examined actions you have taken with regard to previously reported
unresolved items. The status of these items is discussed in the enclosed
report.
In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room.
If this
report contains any information that you (or your contractor) believe to ?;e
proprietary, it is necessary that you make a written application within 20 days
to this office to withhold such information from public disclosure. Any such
application must include a full statement of the reasons on the basis of which
it is claimed that the information is proprietary, and should be prepared so
that proprietary information identified in the application is contained in a
separate part of the document.
If we do not hear from you in this regard within
the specified period, the report will be placed in the Public Document Room.
7 9100 20 M 3
1072
144
9
.
Virginia Electric and Power
-2-
g7
3979
Company
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
E.c.
R. C. Lewis, Acting Chief
Reactor Operations and Fuclear
Support Branch
Enclosure:
Inspection Report Nos. 50-338/79-31
and 50-339/79-39
cc w/ enc 1:
W. R. Cartwright, Station Mar.ager
Box 402
Mineral, VA 23117
P. G. Perry
Senior Resident Engineer
P. O. Box 38
Mineral, VA 'J3117
.