ML19249B214
| ML19249B214 | |
| Person / Time | |
|---|---|
| Site: | Vogtle |
| Issue date: | 05/31/1979 |
| From: | Murphy C NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | John Miller GEORGIA POWER CO. |
| Shared Package | |
| ML19249B203 | List: |
| References | |
| NUDOCS 7909040115 | |
| Download: ML19249B214 (2) | |
See also: IR 05000424/1979009
Text
_
mL -
-
-
-
[pa asog'o
UNITED STATES
8'
.
gc' t
NUCLEAR REGULATORY COMMISSION
.
'
$ ,g "# ( [b
REGION ll
o, -Jf.
[Q
101 M ARIETT A sT., N.W., sulTE 3100
- p'
AT LANT A, G EORGI A 30303
%v
- ....
In Reply Refer To:
MAY 311979
RII:MDH
50-424/79-t,9
50-425/79-09
Georgia Power Company
Atta:
J. H. Miller, Jr.
Executive Vice President
270 Peachtree Street
Atlanta, Georgia 30303
Gentlemen:
This refers to the inspection conducted by M. D. Hunt of this office on
May 15-16, 1979 of activities authorized by hTtC Constructica Permit Nos.
CPPR-108 and CPPR-109 for the Alvir W. Vogtle Nuclear Plant :.acility,
Units 1 and 2, and to the discussion of our findings held with K. M. Gillespie
at the cocclusion of the inspection.
Areas examined during the inspection and our findings are discussed in
the enclosed inspection report. Within these areas, the inspection
consisted of selective examinations of procedures and representative
records, interviews with personnel, and observations by the inspector.
One new unresolved item resulted from this inspecti a and is discussed
in the enclosed report. This item vill be examined during subsequent
inspections.
During the inspection, it was found that certain activities under your
license appear to be in noncompliance with NRC requirements. This item
and references to pertinent requirements are listed in the Notice of
Violation enclosed herewith as Appendix A.
This notice is sent to you
pursuant to the provisions of Section 2.201 of the NRC's " Rules of
Practice", Part 2, Title 10, Code -f Federal Regulations.
Section 2.201
requires you to submit to this office, within 20 days of your receipt of
this notice, a written statement or explanation in reply including:
(1)
corrective steps which have been taken by you, and the results achieved;
(2) corrective steps which will be taken to avoid further noncompliance;
and (3) the date when full compliance will be achieved.
In accordance with Section 2.790 of the NRC's " Rules of Practice,"
Part 2, Title 10, Code of Federal Regulations, a copy of this letter and
the enclosed inspection rtport will be placed in the NRC's Public Document
Room.
If this report contains any information that you (or your contractor)
believe to be proprietary, it is necessary that you make a written
application within 20 days t o this of fice to withhold such information
from public disclosure. Any such application must include a full statement
3CICd
7509040 //6
'
MAY 311979
-
-
.
Georgia Power Comptny
-2-
of the reasons on the basis of which it is claimed that the information
is proprietary, and should be prepared so that proprietary information
identified in the application is contained in a separate part of the
document.
If we do r.ot hear from you in this regard within the specified
period, the report will be placed in the Public Document Rooru.
Should you have any questions concerning this letter, we will be glad to
discuss them with you.
Sincerely,
em
-
.
Charles E. Murphy, Chief
Reactor Construction and
Engineering Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report Nos. 50-424/79-9
and 50-425/79-9
cc w/ enclosures:
K. M. Gillespie
Construction Project Manager
Post Of fice i;x 282
Waynesboro, Geargia 30830
E. D. Grover
QA Site Supervisor
Post Office Box 282
Waynesboro, Georgia 30830
OC1 COO