Forwards IE Insp Rept 50-267/79-11 on 790521-25.Notice of Violation Withheld (Ref 10CFR2.790)
ML19248D048
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 07/10/1979
From: Madsen G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Millen C
PUBLIC SERVICE CO. OF COLORADO
Shared Package
ML19248D049 List:
References
NUDOCS 7908010667
Download: ML19248D048 (2)


See also: IR 05000267/1979011

Text

o

l

t"

[pn M c

k'

UNITED ST ATES

'

S %, - f' h

NUCLEAR REGULATORY COMMISSION

% . C C d/ . <

REGION IV

gl.k

g

11 HYAN PL AZA DFuVE,5UlTE 1000

g

y

ARUNG TON, T E X AS 76012

  • ....

July 10, 1979

In Reply Refer To:

Docket No.

50-267/79-11

Public Service Coupany of Colorado

ATTN:

Mr. C. K. Millen

Senior Vice President

P. O.

Box 840

Denver, Colorado

80201

Centlene1:

This rcfers to the inspection conducted by Mr. h. A. Caldwell and

Ms. C. Abigail Evans of this of fice on May 21-25, 1979, of activities author-

ized by NRC I 4. cense No. DPR-34 and to the discussions of our findings with

the members of your staff at the conclusion of the inspection.

The area examined during this inspection was your program for protecting ag11nst

industrial sabotage and safeguarding special nuclear mata lal pursuant to appli-

cable provisions of 10 CFR 50, " Licensing of Production and Utilization Facilities";

Part 73, " Physical Protection of Plants and Materials"; and specific requirements

of Fort St. Vrain physical security plan.

Within this area, the inspection

consisted of selective examinations of procedures and records, interviews with

personnel, observations by the inspecters, and a review of the Fort St. Vrain

physical security plan of October 31, 1977, and all changes made on April 10, 1978,

and on August 30, 1978.

Within the scope of this inspection, three infractions in the physical security

protection for four plant were observed, as set forth in the Notice of Violation,

enclosed with this letter.

This notice is sent to you pursuant to the provisions

of Section 2.201 of the NRC's Rules of Practice," Part 2, Title 10, Code of Federal

Regulations.

Sectica 2.201 requires you to summit to this office within twenty

(20) days of your receipt of this notice, a written statement or ex,lanation in

reply including:

(1) corrective steps which will be taken, and the results

achieved; (2) corrective steps which will be taken to avoid further noncompliance;

and (3) the date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC Rules of Practice, Part 2, Title 10,

Code of Federal Regulations, documentation or findings of your control and

accounting procedures for safeguarding special nuclear materials and your facility

security procedures are exempt from disclosure; therefore, the inspection report

will not be placed in tha Punlic Docuuent Room and will receive limited distribution.

405

310

_

Q1

@

7908010 bb 7

Public Service Company of Colorado

2

July 10, 1979

Should you have any questions concerning this letter, we will be pleased te

discuss them with you.

Sincerely,

fJWTib-

G. L. Madsen, Chief

Reactor Operation and

Nuclear Support Branch

Enclosure:

1.

Notice of Violation

2.

IE Inspection Report No. 50-267/79-11

ccw/enclo surer,:

D. W. Warcabourg, Nuclear Production

Manager

Fort St. Vrain Nuclear Station

P. O. Box 368

Platteville, Colorado

80651

L. Brey, Manager, Quality Assnrance

(Same Address)