05000334/LER-1979-016-03, /03L-1 on 790608:discovered Cables on Pump Header Isolation Valves Incorrectly Routed Through Cable Trays. Caused by Failure of Const Personnel to Install & Verify Cable Routings Per Procedure.Routing Corrected

From kanterella
(Redirected from ML19247C972)
Jump to navigation Jump to search
/03L-1 on 790608:discovered Cables on Pump Header Isolation Valves Incorrectly Routed Through Cable Trays. Caused by Failure of Const Personnel to Install & Verify Cable Routings Per Procedure.Routing Corrected
ML19247C972
Person / Time
Site: Beaver Valley
Issue date: 08/02/1979
From: Werling J
DUQUESNE LIGHT CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML19247C971 List:
References
FOIA-81-159 LER-79-016-03L, LER-79-16-3L, NUDOCS 7908130462
Download: ML19247C972 (1)


LER-1979-016, /03L-1 on 790608:discovered Cables on Pump Header Isolation Valves Incorrectly Routed Through Cable Trays. Caused by Failure of Const Personnel to Install & Verify Cable Routings Per Procedure.Routing Corrected