ML19246C267

From kanterella
Jump to navigation Jump to search
Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Repts 50-373/79-13 & 50-374/79-10
ML19246C267
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 06/29/1979
From: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Brian Lee
COMMONWEALTH EDISON CO.
References
NUDOCS 7907240064
Download: ML19246C267 (3)


See also: IR 05000373/1979013

Text

c#

%

.

UNITED ST ATES

[

I/C[

,;

NUCLEAR REGULATORY COMMISSION

E ,t

j

REGION 111

bi@[p

f

'99 ROOSEVELT RO AD

S'a

H

f

.

GLEN E LLYN. ILLINOls 60137

%

%

.....

M 2 S IS/S

Docket No. 50-373

Docket No. 50-374

Commonwealth Edison Company

ATTN:

Mr. Byron Lee, Jr.

Vice President

P. O. Box 767

Chicago, IL 60690

Gentlemen:

This is in response to your letter dated June 1, 1979, informing us of

the steps you have taken to correct the noncompliance identified in our

letter dated May 1, 1979.

Regarding Item 1.A, the CECO response addressed Section 7.5.2.2.b.1 of

the La Salle FSAR. According to NRR, the exception identified in this

section does not exclude associated components (i.e., transmitters,

cables, etc.) from being classified as safety related. The exception

pertains to tue malfunction of recorders and indicators during a seismic

activity but not afterwards. The recorders and indicators must withstand

the seismic activity.

If you feel that the " safety related" aspects of

this matter as opposed to the seismic qualifications are still matters of

discussion with NRR, we will reconsider the appropriateness of our enforcement

action. We currently consider the noncompliance as valid.

Therefore,

submit to this office within thirty days of your receipt of this notice a

written statement or explanation in reply:

(1) corrective action taken

and the results achieved; (2) corrective action to be taken to avoid

further noncompliance; and (3) the date when full compliance will be

achieved.

Regarding Item 1.B, your response for corrective action to avoid further

noncompliance identified a review of all safety-related HVAC systems. We

will assume that yoar actions will encompass t.he identification and

control of similar situations for all safety-related components regardless

of systems.

With respect to item number 4, aur enforcement conclusion remains unchanged

based on the following observations:

363

iD3

79072400M

.

Commenwealth Edison Company

-2-

JUN 2 91979

1.

Your audit program is intended to ensure that timely inspections are

performed on ongoing activities and thereby assure the QA program

effectiveness.

Our inspection identified an area where timely

inspections were not performed and documented in a sequence compatible

with the work i.1 progress.

This inadequacy which involved the

installation of the various seismic category 1 nuclear steam supply

system panels, specifically identified that:

The projected lengths of embeded bolts, which hold down the

a.

NSSS panels and prevent them from being damaged in case a

seismic event takes place, were less than the specified

3".

b.

The clearance between some panel frames and the floor were

either less than the specified 1 1/2" or more than 2"

A reactor equipment drain line was installed through a seismic

c.

category 1 NSSS panel No. 1HP22P074.

d.

The storage condition of panel 1H22P009 installed at approximate

elevation 710' on the south side of the containment was not

protected after installation as were the other installed panels.

What's more, we feel the identified problems went undetected because

the activity war neither audited nor surveyed.

Therefore, we believe

that a mechanism to detect and correct inadequacies in a timely

manner was rendered ineffective in this case.

2.

Surveillances are included in the scope of your QA program.

Effective

surveillance of ongoing activities should have identified that the

Morrison Construction Company (MCC) inspection procedure PC-10 could

not be properly implemented for the following reasons:

Manufacturer's Instruction Manuals and or Special Instructions

a.

were not obtained and distributed to the installation / inspection

personnel as stipulated in Paragraph 2.1 of the procedure

PC-10.

b.

Verification, that the equipment base and the foundations are

compatible, was not performed as required in Paragraph 4.1 of

procedure PC-10.

As acknowledged in your response, no installation tolerances

c.

were specified for the panels, consequently, acceptance / rejection

criteria were absent for adequate inspections.

Records indicate

that the base mat was poured in October 1974.

363

186

.

Commonwealth Edison Company

-3-

JUN 2 9 E73

.

3.

Even though the sequence of the installation of the NSSS panels

includes work performed by Walsh Company who installed the foundation

bolts and poured the base mat in 1974, your proposed audit is being

limited to MCC's procedure PC-10.

The above discussion is presented as the basis for our concern that your

audit program which relies on surveillances and audits may not focus

sufficiently on interface activities whcre more than one contractor is

involved in the installation of equipment.

In addition to the above, we do not feel that you have addressed the

concerns expressed in our May 1, 1979, letter in which we requested your

planned efforts to inspect and ve:ify the adequacy of the installations

identified in noncompliance Items 1.C and 2.

We request that additional

information be forwarded to this office within 20 days.

If you have any questions concerning this matter, please contact this

office.

Sincerely,

%a..b ,Y

lb~

6 James G. Kep

er

Director

cc:

Mr. L. J. Burke, Site

Project Superintendent

Mr. T. E. Quaka, QA

Supervisor

Mr. R. H. Holyoak, Station

Superintendent

cc w/ltr dtd 6/1/79;

Cent.21 Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

LTIC

Mr. Dean Hansell, Office of

Assistant Attorney General

363

iB7