QA Program Insp Rept 99900502/79-02 on 790507-11.No Noncompliance Noted.Major Areas Inspected:Implementation of 10CFR50,App B & Topical Rept B&R-002A,including Design Change Control & Action on Previous Insp Findings
ML19246C207
Person / Time
Issue date: 05/23/1979
From: Donna Anderson, Hale C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19246C204 List:
References
REF-QA-99900502 99900502-79-2, NUDOCS 7907230736
Download: ML19246C207 (8)


Text

-

U. S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT REGION IV Report No.

99900502/79-02 Program No.

51200 Company:

Brown and Root, Incorporated Power Engineering 4100 Clinton Drive Post Office Box 3 Houston, Texas 77001 Inspection Conducted: May 7-11, 1979 O

fhf b

9 Inspector:

N t

D. G. Gystersdn, Prin'cTp9 }nspector, Vendor Date 1

Inspection Branch Approved by:

dh C. J.

, Chief, Pro'gra'c-Evaluation Section Date Vendo spection Branch Summary Inspection on May 7-11, 1979 (99900502/79-02)

Areas Inspected:

Implementation of Title 10 CFR 50, Appendix B, and Topical Report, B&R-002A, including design change control and action on previous inspection findings. The inspection involved thirty-seven (37) inspector hours on site by one (1) USNRC inspector.

Results:

In the two (2) areas inspected, no deviations from commitment or unresolved items were identified.

7 9 07 2 3 0 7 SG, 359 254

2

/

Details Section A.

Persons Contacted

  • T. H. Gamon, Quality Assurance Manager
i. K. Ghosh, Senior Engineer H. C Huang, Senior Structural Engineer M. J. Meyer, Senior Project Engineer
  • B. F. Mitchell, Project Quality Engineer
  • J. E. Paden, Project Quality Engineer L. B. Patc1, Containment Internals Supervisor
  • R. W. Peverley, Assistant Engineering Project Manager S. P. N. Singh, Discipline Project Engineer M. K. Wanchoo, Containment Supervisor
  • Indicates those present at the exit meeting.

3.

Action on Previous Inspection Findings 1.

(Closed) Deviation (Report No. 79-01); Two (2) calculations performed for a safety related structure either did not include the date of approval or references for two (2) sets of design input. The inspector verified that corrective action as referenced in the B&W letter of response dated March 6, 1979, had been completed.

In particular, each of the calculations were corrected and a training program was con-ducted for those disciplines involved.

2.

(Open) Unresolved Item (Report No. 79-01): Response spectra for the reactor containment structure, as identified in a B&R report, appears to differ from that reported in the FSAR for the South Texas Project.

The inspector t viewed the B&R evaluation of this item with respect to possible inclusion of the non-conservative response spectra in B&R design documents.

It appears that the only safety related items impacted by this error were the specifications for the reactor con-tainment fan coolers and the design of the shield structure for the containment building equipment hatch. This item will remain open pending NRR/ DSS verification of the redesign of the shield structure.

(See paragraph D. below for additional information).

C.

Design Change Control 1.

Objectives The objectives of this area of the inspection were to verify that:

Procedures have been established and implemented for controlling a.

changes to approved design documents.

359 255

3 b.

Design changes are reviewed for the impact of the change, docu-mented as to the action taken, and transmitted to all affected persons and organizations.

c.

The design changes are justified and subjected to review and approval by the same groups or organizations as for the original design.

d.

When responsit.ity has been changed, the designated organization shall have access to the pertinent information, competence in the specific area of design, and an understanding of the require-ments and intent of the original design.

2.

Method of Accomplishment The preceding objectives were accomplished by:

a.

A review of the Brown and Root Topical Report, B&R-002A, Section 17.3, Design Control, which summarizes the methods used by Brown and Root, Power Engineering Group, to describe their activities related to design change control. The design change control process is defined, implemented, and enforced according to the following procedures:

(1) The Brown and Root Quality Assurance Manual, Section 3.8, Design Change.

(2) Engineering Procedures; STP-DC-002-I, Engineering Procedure for Drawing Control, May 15, 1978.

STP-DC-005-H, Preparation and Control of Specifications, February, 7, 1978.

STP-PM-005-F, Interface Control, November 4, 1977.

STP-DC-007-G, Preparation and Control of System Design Design Descriptions (SDD), August 22, 1978.

STP-DC-008-G, Calculations, February 3, 1978.

STP-DC-009-G, File and File Storage, February 14, 1978.

STP-DC-012-G, Final Safety Analysis Report (FSAR) Change Control, June 14, 1978.

STP-DC-013-C, Document Change Notice Control, January 24, 1978.

STP-DC-014-E, Document Comment Porocess, January 10, 1978.

359 256

4 STP-DC-015-G, Design Verification, January 29, 1979.

STP-DC-017-C, Computer Program Documentation, July 27, 1978.

b.

Review of STP Form 200.29, Document Change Notices, which documents the review of the design change, the impact of the change, and the action taken and accompanies each of the following documents:

(1) Document Change Notices for Calculations:

DCN No. 2N129RC005-DCN, February 19, 1979, Safety Injection System Low Head Pump Discharge, Reanalysis Revision D to Revision E; DCN No. 2N129RC006-DCN, February 16, 1979, ECCS Low Head Pump Discharge Piping-Train B, Reanalysis Revision C to Revision D; DCN No. 2N129RC007-DCN, February 16, 1979, ECCS Low Head SI Pump Discharge-Train C; DCN No. 2N129RC008-DCN, February 19, 1979, ECCS High Head SI Pump Discharge, Train A; DCN No. 2N129RC009-DCN, February 16, 1979, ECCS Higb Head SI Pump Discharge, Train B; DCN No. 2N129RC010-DCN, February 16, 1979, ECCS High Head SI Pump Discharge, Train C; DCN No. 2N129RC011-DCN, February 19, 1979, Contain-ment Spray System, Train A; DCN No. 2N129RC012-DCN, February 19, Containment Spray Additiva. p tam, Pump A; DCN Jo. 2N129RC013-DCN, February 16,1/1, Containment

~

Spray Pump Discharge, Trains B and C; l~:N No 2N129RC014-DCN, February 19, 1979, ECCS Containment Spraj aouitive. Train B; DCN No. 2C011SC040-B-DCN, May 7, 1979, Addition of Response Spectrum Curves; DCN No. 2C101SC019B-DCN, April 25, 1979, Crane Girder Analysis and Design; DCN No. 2C091SC014B-DCN, May 3, 1979, Equipment Hatch Analysis and Design.

(2) Document Change Notices for Specifications:

DCN No. 3Z1492S001E-DCN, October 25, 1978, Area Radiation Monitoring System; DCN No. 2V211VS001E-DCN, April 10, 1979, Design Verification of RCB HVAC System Cooling Load Calculation, update of earthquake response spectrum curves; DCN No. 3V279VS007E-DCN, May 2, 1979, clarification to seismic response spectra; DCN No. 2R099RC124A-DCN, May 2, 1979, correction to specification; Reactor Incore Instrumentation Guide Tubes; DCN No. 2C269SS006G-DCN, Feb rua ry 12, 1979, incorporate correct floor derign spectra for EAST-WEST SSE elevations 37', 68', and 108'.

(3) Document Change Notices for Reports:

DCN No. 3N160SR043B-DCN, March 7,1979, fourteen (14) response spectra are revised to make then compatible with calculatica package 2C011SC040B.

359 2Sif

5

/

(4) Documeut Change Notices for the following drawings:

2N171R0301H, Stress Isometric ECCS Pump Discharge Train A, Feb ruary 16, 1979.

2N171R0302E, Stress Isometric ECCS Pump Discharge Traia B, February 16, 1979.

2N171R0303E, Stress Isometric ECCS Pump Discharge Train C, Feb rua ry 16, 1979.

c.

The documentation referenced in C.2.b above was also accompanied by STP Form 200.52, Document Transmittal Order, which transmits design changes to cognizant groups or to the same organizations who performed the original design. This assurers that design changes are subjected to review and approval by the group who performed the original design or if responsibility has changed, it assures that the newly designated organization has competence in the particular area of design.

3.

Findings In this area of the inspection, no deviations from commitment or unresolved items were identified.

D.

Follow-up on Unresolved Item-Seismic Response Spectra During Inspection No. 79-01, an unresolved item was identified which related to a discrepancy between seismic response spectra for the containment building as reported in the South Texas Project FSAR and an engineering report generated by Brown and Root. During Inspection No. 79-02, the inspector ' ollowed up on Brown and Root's evaluation of this discrepancy.

T1 e Quality Engineering group of Brown and Root performed a systematic i'Avestigation of all documents, i.e., specifications,- calculations,

engineering reports, and erternal transmittals, to assure that design input contai.ing the non-conservative seismic response spectra has not been incorporated into coayanents being supplied or structures being supplied or structures being fabricated at the South Texas Project.

The inspector reviewed the following documentation related to this investigation:

1.

Specifications:

Structural-2C269SS006-G, Steel Liner Work for Reactor Containment Structure; 3F269SS034-D, Stainless Steel Pool Cate System; Stress-2R099RC124-A, Re'.ctor Incore Instrumentation Guide Tubes; 3R209RS004-D, Elex Hose For Reactor Coolant Pump Auxiliary Piping; 3V279RQ009-B, HVAC Ductwork Structural Design Data; 3V279RC019-A, HVAC Duct Support Deflection Analysis; 1N1790RQ001-C, Piping Stress Analysis Criteria; 359 258

6 HVAC-3V279VS007-E, Safety Class Ductwork; 3V289VS008-F, Safety Class Dampers; 2V211VS001-E, Reactor Containment Fan Coolers; Mechanical-2C099NS054-D, Mechanical Penetrations (Containment);

7C109NS052-D, Containment Polar Crane; Piping and Valves-1L529TS100-D, ASME Section III, Gate, Globe and Check Valves 2 " and Larger; IL529TS101-D, ASME Section III Gate, Globe and Check Valves 2" and Smaller; IL529TS102-D, ASME Section III Ball and Plug Valves; 2L529TS103-D, ASME Section III Butterfly Valves; IL529TS104-D, ASME Section I7I Bellows Seal or Packless Metal Diaphragm Valves 2" and Smaller; 2L359PS505-D, ASME Section III Metalic Expansion Joints; IL360PS102-E, ASME Section III Pipe Hangers and Supports; Instrumentacion and Controls-224392S210-D, ASME Section III Control Valves; 2Z449ZS006-D, ASME Section III Solenoid Valves; 3Z149ZS001-E, Radiation Monitoring System; 3Z169Z-S070-D, Containment Hydrogen Monitoring; 2Z4592S230-D, Class 2 and 3 Pressure Safety and Relief Valves; and Electrical-3E209ES031-E, Electrical Penetration Assemblies; 3E509ES039-C, Class IE AC/DC Distribution Panels.

2.

Calculations:

Structural-2C011SC040-C, Seismic Analysis of the Reactor Containment Building; 3D011SC104-A, Seismic Analysis of the Diesel Generator Building; 3M011SC089-B, Seismic Analysis of the Mechanical Electrical Auxiliary Building; 3F011SC126-A, Final Seismic Analysis of the Fuel Handling Building; 2C011SC037-E, Final Calculations Concrete Floors; 2C011SC044-E, Final Calculations Miscellanious; 2C101SC019-B, Crane Girder and Bracket Analysis and Design; and Seismic-2C011SC040-A&B, Seismic Analysis of the Reactor Containment Building.

3.

Feports:

2N160SR043-C, Seismic Analysis of the Reactor Containment Building; 3N160SR044-C, Seismic Analysis of the Category 1 Structures.

4.

Procedures:

IN019RQ004-C, Qualificatica Procedure for Seismic Category 1 Equipment.

5.

Transmittals:

ST-BR-ED-0132, Relative Displacement Criteria, February 4,1976.

b9 h

L

7 6.

Consultants Reports:

Y310XR069, Soil Structure Interaction Analysis Woodward-Clyde Consultants, Transmitted to Brown and Root, January 5,1976, ST-WC-BR-0428.

In addition to these investigations, Brown and Root performed a survey through their resident engineer at EDS Nuclear, a consulting firm that is responsible for piping analyses under contract to Brown and Root.

The following SUPERPIPE computer runs were checked for response spectra input:

CS-01, Revision 1, October 21, 1976.

FC-01, Revision 0, January 26, 1977.

CC-05, Revision 0, July 26, 1976.

CV-02-03, Revision 3, October 25, 1978.

MS-03, Revision 3, May 12, 1977.

FW-02, Revision 1, April 19, 1977.

The results of this intensive investigation were that the majority of the purchase and engineering specifications were generated using the c3nservative spectra. One (1) specification and one (1) calculation using nonconservative spectra have been re-evaluated with the following results:

Specification: 2V211VSC01-E, Reactor Containment Fan Coolers. The incorrect response spectra had been incorporated into the specification, t 1 wever, in tests performed at Joy Manufac-turing, the sup; '.ier, a seismic load of 10g was used.

Since the spe-ijied loads fo~ the South Texas Project une lg horizontal,.nd 0.67 vertical, the tested loadings ou the Reactor Contai' ment Fan Cooler System appear to be quite conservative.

Calculation:

2C091SC014-B, Equipment Hatch Shelf Analysis and Design.

The inspector was notified that a less conservative seismic response spectra was used in the original desiga of the structure which supports saielding to prevent radiation streaming through the equipment hatch. This support structure is attached to the containment building shell by means of imbedments. The results of the analysis were that stiffening of the structure would be required, however, the inspector was concerned that if the imbedments originally met the non conservative response spectra, then should not the Dnbedment design be reviewed to assure that 359 260

8 the shield structure would remain intact under increased loads. These calculations are being forwarded to NRR/ DSS for independent design verification and this item will remain open pending completica of this verification.

Based upon the material reviewed by the inspector and discussicas with Brown and Root personnel involved in this investigation, it appears that.

evaluation was organized, conducted, and reported in sufficient detail to assure that the non-conservative response spectra have not been used in the acquisition, design, or fabrication of safety rie ated structures or cceponents at the South Texas Project.

Of the large volume of documents reviewed, only the two noted above appear to have required further consideration.

E.

Exit Meeting An exit meeting was conducted with Brown and Root management personnel at the conclusion of the inspection on May 11, 1979. Those individuals indicated by an asterisk in paragraph A above were in attendance.

In additi.n, the following were present:

E. H. Bomke, Senior Vice President, Power Engineering K. M. Broom, Vice President, Engineering L. E. Hayden, Jr., Engineering Project Manager R. G. Helms, Project Quality Engineer H. Paperno, Assistant Quality Assurance Manager, W. N. Phillips, Projects Quality Assurance Manager, Hoston Lighting and Power Company J. Shuckrow, Lead Audit..

K. A. Swarts, Engineering Manager This inspector discussed the scope of the inspection and indicated that no findings had been identified during the inspection. The inspector noted, however, that the unresolved itea related to incorrect response spectra will remain open until design verification of the calculation fcr equipment hatch shield support design has been completed by NRR/ DSS.

Management representatives of Brown and Root acknowledged the statements by the inspector.