ML19241C028

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-409/79-10 on 790501-04 & 21-24.No Noncompliance Noted.Major Areas Inspected:Licensee Activities in Response to IE Bulletin 79-08 Re Operability & Availability of Engineering Safety Features
ML19241C028
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 05/31/1979
From: Boyd D, Ridgway K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19241C025 List:
References
50-409-79-10, NUDOCS 7907260264
Download: ML19241C028 (6)


See also: IR 05000409/1979010

Text

.

.

U.S. .HUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION ANI) EhTORCEMENT

FIGION III

.,

Report No. 50-409/79-10

'

Docket No. 50-409

License No. DPR-45

Licensee:

Dairyland Power Cooperative

2615 East Avenue - South

La Crosse, WI 54601

Facility Name:

La Crosse Boiling Water Reactor

Inspection At:

La Crosse Site, Genoa, WI

Inspection Conducted:

May 1-4 and 21-24, 1979

/d/*$ ibsw; \\

i

_f ,y /76

Inspector:

K. R. Ridgway s'

L.tl[ / 'I

. ,', .O, /

Approved By:

D. C. Boyd," Acting Chief

- /

Reactor Projects Section 3

Inspection Sux.rrv

.

Inspec:.on on May_l-4 and 21-24, 1979 (Report No. 50-409/79-10)

Areas Inspected:

S; ecial, unannour.ced inspect on of licensee

activities in response to IE Bulletin 79-08 including their response

to the bulletin and the operability and availability of engineered

safety features (ESF), administrative control of Ear, verification

of ESF status, operating procedures, surveillance tests ar.d operator

training.

The inspection involved 66 inspector-hours onsite by one

NT<C inspecto r .

Results: No items of noncompliance or deviation were identified in

any of the areas inspected.

79072601b

h

466

PP!

.

.

.

DETAIL _S

1,

Persons Contacted

'

  • R.

Shimshak, Plant Superintendent

  • J. Parkyn, Assistant Plant Superintendent
  • G. Boyd, Operations Supervisor

P. Wiley, Assistant to Operations Supervisor

R. Prince, Radiation Protection Engineer

L. Krajewski, Health and Safety Supervisor

H. Towsley, Quality Assurance Supervisor

S. Rafferty, Reactor Engineer

L. Papworth, Operations Engineer

M. Polsean, " lift Supervisor

N. Hoefert, Mechanical Engineer

L. Kelley, Security and Fire Protection Supervisor

P. Gray, Supervisor, Mechanical Maintenance

D. Kabachinsky, Operator

G. Whynaucht, Operator

W.

Fuller, Operator

G. Gadow, Operatar

P Crandall, Operator

G. Holmstadt, Operator

D. Stalsberg, Operator

In addition, the inspector observed and held discussions with

other engineers, plant equipment operators, reactor operators,

assistants, and plant attendants,

kDenotes those

at at the exit interviews.

,

2.

General

This inspection was cond2cted to review tne response by the

licensee to Inspection and Enforcement Bulletin 79-08 " Events

Relevant to Boiling Water Power Reactors Identified During

Three Mile Island Incident" and to verify that the actions

requested in the bulletin with respect to operator training,

NRC telecommunications, and reviews of engineered safety

features (E3i) had been completed.

In addition, the inspection

consisted of an independent examination of ESF systems to

verify that the systems were operable according to technical

specifications by review of procedures, administrative controls,

valve / breaker / switch checkoff lists, piping and instrument

diagrams, and the actual alignments of valves, breakers and

switches.

_2-

466

?22

.

s

The following systems were considered to be Engineered-Safety

Systems in this inspection:

Emergency Core Spray (High and Low Pressure) (ECS)

Alternate Core Spray (Low Pressure) (ACS)

J

-

Shutdown Condenser System (SCS)

Boron Injection System (BIS)

Emergency Diesel Generators (EDG)

Containment

The reactor protection actuation circuitry was also r2 viewed

briefly as were portions of the nuclear steam system.

3.

Engir.eered Safety features (ESF) Availability and Operability

The inspection included a review of ESF alignment procedures

against current piping and instrument diagrams to verify that

the procedural alignments do not compromise the availability or

operability of safety related components.

Normal sta rtup

procedures from both cold and hot shutdown conditions require

the completion of valve checklists before the startup can

progress.

This inspection also i,cluded a review of any sur-

veillance, special, and maintenance procedures to establish

that valves, breakers and/or switches in the ESF systems are

returned t, pretest conditions or that a normal prestartup

check sheet verification would be completed before the system

eperabild y is required.

The licensee uses alignment checklists following extended

outages or extensive maintenance i

to assure proper lineup

'

of valves and valve s itches.

Ali

slignments can be

verified by indicator lights in the

n

room and in addition

.

any open breakers, out of normal positic.2 valves and switches

are ca r: :od in the " lock and tag" procedure which is under the

control

-f the Shift Supervisor.

The checklists along with

operating procedures, surveillance test procedures, special

procedores and maintenance procedures were compared with piping

and instrument line drawings to verify correct positioning of

valves and switches following tests and during normal operations.

The review of system lineups and test procedures did not idertify

any instances of improper lineup control, such that the operability

or a-

lity of ESF systems would be compromised.

A number

of iu

.encies between test procedures and data sheet

checkoft were noted.

In all cases the procedures required the

proper return to service of valves and switches but the data

-3-

466

?9<

~us

.

sheets of the tests did not provide documentation that-the

systems had been returned to normal. A list of the incon-

sistencies were provided to the licensee for his followup.

No items of noncompliance were identified.

-

4.

Administrative Control of Engineered Safety Features

'

Licensee administrative controls to assure proper return to

service of ESF systems and components following maintenance or

test activities and at the conclusion of extended outages are

and have been subject to continuing review by the NRC inspector.

These areas were cursorily reviewed during this inspection to

determine if any changes had been made that might reduce the

effectiveness of ACP 15.2, Equipment Lock and Tag Control; ACP

17.3, Maintenance Requests; ACP 2.1, Authorities and Responsi-

bilities for LACBWR Operation and Shutdown; ACP 2.3, Shift

Transition (turnover) Shift Conduct; ACP 6.2, Procedure Adherence

and Temporary Changes; and ACP 15.1, Installation and Removal

of Jumpers, Lif ting and Replacement of Leads.

Based on this review, administrative controls are considered

adequate to assure proper return to service.

Discussions with licensee personnel concerning independent

verification of system lineups indicates that the lineup checks

are made by qualified operators (licensed or unlicensed); the

lineups and test data sheets are not reverified, but the sheets

are approved by the Shift Supervisor and reviewed by the Operations

Supervisor to verify completeness and accuracy of data.

Licensee tagging practice and procedures to provide control of

equipment, was reviewed during this inspection. The purpose of

the review was to determine the potential for tags to obscure

position indicators, meters or alarm lights.

It was noted that

tags were either bent or held in place by rubber bands so that

significant indicators would not be obscured.

The inspector also reviewed the recent surveillance tests of

ESF systems to verify completeness and conformance to Technical

Specifications.

No items of noncompliance were identified.

-4-

bbb

')< c'3 A9

,

5.

Current Status of. Engineered Safety Features

This inspection included a verification by the inspector of the

current valve, switch and breaker lineup of ESF systems.

At

the time of the inspection, the plant was concluding ap eight

y

week refueling - m intenance outage and startup preparations

were in prc gt ess.

Lineups were verified with checklists for

-

normal operatang conditions. The only valves to be found out

of operational alignment ere five in the Decay Heat System as

maintenance work was in progress and the Decay Heat System is

normally in operation during startup.

During the ..igane;' ve ificativa, it was noted that there were

-

inctnsistencier in locked "alves bet een procedures, check' sts

and actu

ace L

There were several valves which the

-

insnec or . --'edsd should be added to checklists.

One valve

identific' ion was missing because of recent maintenance work.

A l'st

i, e inconsistencies was given to the licensee to

t

bring proceceres, test data sheets and lineup checklists into

agreeme t.

This is considered an open item and will be reviewed

during a subsequent inspection.

No items of noncompliance were identified.

6.

Staff Training

The inspector reviewed the training actions taken by the licensee

in response to IE Bulletin 79-08, by reviewing records and

interviewing licensed operators.

All operations personnel had

reviewed IE Bulletin 79-05 and the licensee's response to IE

Bulletin 79-08, dated May 2, 1979.

Operations Memo, DPC-75

dated May 16, 1979 concerning manual override of automatic

actions of ESF systems had been issued and reviewed by all

operations personnel.

Operations Memo, DPC-76 dated May 24,

1979 concerning immediate and uninterrupted telecommunications

with NBC in the event of uncontrol' ?d or unexpected reactor

conditions had been issued and reviewed by all personnel.

No items of noncompliance were identified.

7.

Operations Review

The inspector observed plant outage conditions, removal of the

peripheral shroud for replacement, control room manning, lock

and tag status of equipment, and valve / breaker / switch alignments

of safety related systems for startup.

Additionally, the

-5-

466

??c

-ea

.

.

following records,Jor the month of May 1979 to determine

compliance with Technical Specifications and regulations and to

determine if Night Order and Operational Memos conflicted in

any way with operation of requirements:

.

a.

Night Order Instruction Book

b.

Shift Supervisors Log

c.

Outstanding Maintenance Orders

-

d.

New Operational Memos

No items of noncompliance were identified.

8.

Management Interviews

Management interviews (as shown in Paragraph 1) were conducted

on May 4, 1979 and at the conclusion of the inspection on

May 24, 1979. The inspector discussed the scope and findings

of the inspection.

The following items were discussed:

a.

The inspector advised the licensee that the independent

review of the ESF systems procedures, lineups and admin-

istrative controls had not identified any condition that

would jeopardize ESF availability or operability.

b.

Notes made by the inspector relating to inconsistencies

and apparent inaccuracies in procedures, test data sheets,

and lineup checksheets were provided to the licensee. The

inspector stated that the resolution of the list would be

reviewed during a subsequent inspection.

-6-

466

226