ML19241B215

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-482/79-04 on 790305-08 & 15.Noncompliance Noted:Failure to Follow Procedures Re Spectrographs of Chemical & Physical Properties
ML19241B215
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 04/10/1979
From: Crossman W, Oberg C, Rosenberg A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19241B213 List:
References
50-482-79-04, 50-482-79-4, NUDOCS 7907130139
Download: ML19241B215 (15)


See also: IR 05000482/1979004

Text

U.S.fJUCLEARREGULATORYCOMMISSIUN~

OFFICE OF IrlSPECTION AND E

0RCEMEilT

,

REGION IV

Report f40. STN 50-482/79-04

Docket No. STN 50-482

Category A2

Licensee:

Kansas Gas & Electric C mpany

.

Post Office Box 208

Wichita, Kansas

67201

Facility Name: Wolf Creek, Unit No.1

Inspection at:

Burlington, Kansas

Inspection conducted: Marci; 5-8 and 15, 1979

Inspectors:

/ -

%d -

Y/> 79

C. R. Oberg, Reactort/ Inspector, Projects Si ction

Date

h R Puccl

w/a/79

A. B. Rosanberg, Reactor Inspector, Engineering -

Date '

&

Support Section

J

h 3 Osco N

N 5!7R

A. B. Beach, Reactor Inspector, Engineering Support

Date '

Section

7

Approved:

b6

Y//6[77

e

W. A. Crossman, Chief, Projects Section

Date

f4%$~w

V//W7 9

.

E'. Hall, Chief, Engineering Support Section

Date

' 07 {30 ./ J,y

cp

V

(

,.<!

J .; c

'

Inspection Summary:

-

Inspection on March 5-8 and 15,1979 (Report tio. STil 50-482/79-04)

.

Areas Insoected:

Routir a, unannounced inspection involving follow up of

unresolved items relat'ng to the containment base mat concrete (Inspection

Report flo. STf4 50-482/78-13). This report alsc includes information on

flRC visits to PCA to observe testing of cylinder fragment cubes and cement

sample cubes, and results of a ineeting between KG&E and Region IV on matters

relating to a PCA report.

The inspection involved seventy-four inspector-

hours on site by three f4RC inspectors.

Results: One item of noncompliance (infraction - failure to follow procedures)

was identified during the inspection.

-2-

gg

$g3

,

.

.

DETAILS I

SITE If1$PECTION, MARCH 5-8, 1979

.

,

.

.)

l/

.. .

'J

DETAILS I

,_

l.

Persons Contacted

-

,.

Principal Licensee Personnel

g nsas Gas & Electric Company (KG&E)

"G. L. Koestar, Vice President, Operations

  • J. O. Arterburn, Superintendent, fluclear Development
  • M. E. Clark, Manager, Quality Assurance, Site
  • G. W. Reeves, QA Engineer

+D, W. Prigel, QA Engineer

  • T. C. Newman, QA Engineer
  • R. Ayres, QA Engineer

Kansas City Power & Light (KCP&L)

  • D. Crawford, Construction Engineer

Bechtel

  • G. flutwell, Lead Site Liaison Engineer

Ash Grove Cement Company (Chanute Plant)

J. McMechin, Plant Superintendent

J. D. Shea, Chief Chemist

Daniel International Corporation (DIC)

  • L. R. Smith, Regional Manager
  • W.

E. Hitt, Project Manager

  • V. J. Turner, Project QA Manager
  • I. Hussain, Assistant to Project Manager
  • denotes those present at the exit interview.

2.

Licensee Action on Previous Inspection Findings

Closed) Unresolved Item (No.1)1/ (STN 50-482/78-13):Adequacy of

t

Depth and Scope of KG&E and DIC Audit Program in Area of Concrete

Production and Control.

After review of audit and surveillance

reports and discussions with licensee and constructor QA personnel,

the IE inspector concluded that the depth and scope of the audit

program, in the area of concrete production and contro!, is adequate.

This item is considered closed.

1/ Items No. refers to list of unresolved item in Inspection

-

,

i

,

Report STf4 50-482/78-13

' 4. ; b

Jld

~

_4

.

Closed) Unresolved Item (No. 2) (STtt 50-482/78-13):

Review of User

Test Break Sheets for 'JT #10 through 24.

During inspection 50-482/78-13,

.

summary information for cement cube user tests were reviewed.

During

this inspection, the cube test break sheets and logs were reviewed for

User Tests 10 through 24 and found to be in accordance with site pro-

cedures and ASTM C-150, with the exception of two items of noncompliance

previously identified in report No. STN 50-482/78-13 and NCR I-146-C.

The nonconformance report was reviewed with no further questions.

This item is considered closed.

(0 pen) Unresolved Item (No. 6) (STfl 50-482/78-13):

Determine if Change

in Admixture Properties Occurred.

During a previous inspection, QA

certifications, which did not reveal chemical or physical properties,

were reviewed for the water reducing admixture (WRA) (Master Builders

type 300N) and air-entraining admixture (AEA), MB-VR standard.

During

this inspection, the manufacturer supflied spectrographs for the ad-

mixtures were reviewed. All the WRA spectrographs reviewcd appeared

to be consistent. The AEA spectrographs

differences.

(2)themaximalat3100cm91at3400cm~{eve

Specificallys (1) the minim

varies approximately 24%;

- ofthegraphstartingat1600cmgroximately12%;and(3)tne

varies ap

cm ] where the variation is approximai.ely 15%.

tai

diverges to the point 600

The significance or

meaning of these variations is not yet determined.

Tnis matter remains

unresolved pending the determination of the significance of these

variations by the licensee and/or the vendor.

(Closed) Unresolved Item (No. 7) (STN 50-482/78-13):

Review of Cylinder

Break Sheets for Batch Plant Mixer Qualification.

During a previous

inspection, batch plant and truck mixer qualification and unifonnity

tests were reviewed.

During this inspection, the cylinder break sheets

for the mixer uniformity tests werc reviewed and results were found to

be in ac'ordance with requirements of ASTM C-94.

This matter is

considerad closed.

(Closed) Unresolved Item (No. 8) (STN 50-482/78-13):

Review of Computer

User Manual for Statistical Analysis of Cylinder Break Data.

The lE

inspector reviewed the " Compressive Test of Concrete Cylinders System

User Manual" issued by DIC Management Services, Greenville, South

Carolina, on April 4, 1977.

No itels of noncompliance or deviations

were identified. This item is considered closed.

(Closed) Unresolved Item (No. 9) (STN 50-482/78-13):

Review of

Compression Test Report for Cylinder Set No. 567.

During a previous

inspection, a possible transcribing error was identified on the data

sheet for cylinder set 567,

During this inspe-tion, a corrected

compression test reoort was filed with the original report.

This

matter is considered closed.

-5-

_

.

t

(Closed) Unresolved Item (flo.10) (STri 50-482/78-13):

Review of Type

of Breaks Experienced on the Test Cylinders.

During a previous in-

spection, it was determined that the description of the type of breaks

.

identified by DIC are at vagjance the type of breaks identified by

PCA for the same cylinders.H

During this inspection, a comparison of

type of break identified by PCA, DIC and f4RQ,was made of forty-eight

cylinders shipped to PCA December ll,1978.H

PCA

DIC

NRC (only observed 45)

Cone

2

47

3

Diagonal

35

1

26

Transverse and/or

Longitudinal

11

-

9

Liot Identified

-

-

7

' lumber Same

33 of 38

as PCA

48

3

identified

A review of ACI and ASTM standards failed to reveal specific guidance

for determining the type of break or their significance.

Therefore,

due to the subjectivity of this matter, this item is considered closed.

(Closed) Unresolved Item (flo.11) (STN 50-482/78-13):

Review of Batch

Plant Production Rate and Adequicy of Mixing.

During previous inspec-

tions, the mixer qualification test and the concrete production rate

for the base mat concrete were examined.

During this inspection, the

mixer qualifications were re-examined for Design Mix 42-C-1 A-N prior

to the time this mix design was upgraded to a 5000 psi mix at 90-days.

It was observed that a mix time of 45 seconds was consistently used.

There are no further questions at this time.

(Closed) Unresolved Item (No. 12, sSTri 50-482/78-13):

Review of Initial

Test Cylinder Curing Temperature.

During a previous inspectior., tem-

perature documentation for the first twenty-four hours of the base mat

cylinders curing could not be found.

During this inspection, it was

determined that temperatures were not " logged," since the DIC procedure

2/PCA (Shideler) letter to DIC (Phillips), dated April 19, 1978

~3fPCA (Shidelce) letter to KG&E (Koester), dated February 27, 1979

3g

3j2

-6-

did not require logging.

However,reviewofD[Cmemo,T.A.Greento

W. Hiti., dated December 13, 1978, indicated that the newly cast cy-

.

linders were initially stored in heated sheds near the placement.

The

temperature was monitored periodically by personnel with hand held

thermometers to verify compliance to ASTM C-31.

The results of these

measure"ents were not specifically recorded.

This ma *er is considered

closa'

(Closed) Unresolved Item (flo.13 & 14) (STri 50-482/78-13):

Review of

Lack of Curing Room Temperature Records and I;CRs on Curing Room

Temperatures.

During a previous inspection, curing room temperature

records revealed several occasions,whgre the curing room temperatures

U

exceeded allowable limits (73.4 F - 3 F) und one period where no

records exist.

The NCRs relating to some of the out of limit tem-

peratures were reviewed.

During this inspection,flCRs concerning

curing room temperature were reviewed for the period November 1977,

through March 1978.

Three recorded periods of temperatures below

specification and one period where no temperatures were recorded, and

no flCRs or deviation notices were initiated.

The period of no record

occurred over a holiday weekend and was apparently caused by the

recorder pen running out of ink.

Failure to identify discrepant and/or indeterminate conditions indi-

cate an item of ncncompliance with 10 CFR 50, Appendix B, Criterion V,

failure to follow procedures and with the requirements of Daniel

Procedure QCp-1-04, paragraph 3.5, Rev. O.

3.

Stop-Work Order for Safety Related Concrete

On March 8,1979, the IE inspector was infomed by the licensee that

a stop-work order had been imposed on all safety related concrete

on the Wolf Creek site.

The stop-work order was effective at 1:35 p.m.

and had been issued as a result of Daniel QC personnel observing and

reporting that concrete was moved more than five feet with a vibrater

contrary tu specifications.

On March 7,1979, during the initial steps

of an auxiliary building internal wall placement (0C 135 WO6), a tremie

vecamo plugged and ruptured.

The special placement plan was abandoned

b, the foreman and the placement was completed using an alternate tremie.

D2 ring the last of the 18 inch lifts, before topping off, concrete was

noved by vibrators 6 feet from the point of deposition.

The speci-

fication limit is 5 feet.

Placement OC 135 WO6 is a 14 foot, 8 inch

long x 2 foot wide x 12 foot hi9n wall in the main steam penetration

area.

4.

Testing of 28-Day Cylinder Fragments

_

During the inspection, the IE inspector was informe1 that twenty c .x

base mat cylinder fragment. had been transported to PCA for cube

.

,y

testing, and for petrographic and chemical testing.S/ Cubes will

be formed from as many fragments as possible.

Sixteen fragments

will be given petrographic and chemical analysis.

All fragments

.

are the results of the 28-day compression tests.

The following

fragments were identified to the inspector:

Cylinder No.

6411

6513

6604

6700*

6424*

6514

6640*

6706

6448

6531*

6651*

6717*

6483*

6543*

6664

6718*

-

6484

5561*

6735*

6490*

6580

6752*

6496

6886*

6771*

6794*

  • Petrographic & Chemical Analysis

The results of the PCA testing will be reported to the NRC.

5.

Exit Interview

The IE inspectors met with licensee representatives (denoted in

paragraph 1) at the conclusion of the inspection on March 8,1979.

The IE inspectors summarized the purpose and scope of the inspection

and the findings.

'ihe licensee representative acknowledged the item

of noncompliance.

4/KG&E (Koester) letter to DIC (Hitt), dated Fe.'uary 15, 1979

-8-

1

=

i ., b

l I

.. . __

.

_

W

,-

.

.

-

_

-

.

m

2

]

_

s

.

t

-

R

L

_

DETAILS II

j -

.

_

KC&E/flRC MEETIflG, MARCH 15, 1979

..

-

-

E

1

.

{

"

_

.

3

_

m

_

E

. .

...

4

_:

E

> .;' '

_

-

I;; c

-

M

_,c

j; . _

,/

i

-

-

,

.,

-

-

<___ __--_.

-

DETAILS II

--

.

Management Meeting

Kansas Gas and Electric Company requested a meeting with Region IV

personnel to discuss the latest PCA report (dated February 27,1979)

transmitted to the Region IV office on February 28, 1979.

The m eting

was held March 15, 1979, with the following attendeen:

Licensee Personnel

G. L. Koester, Vice President-0perations, .G&E

E. W. Creel, Director Quality Assurar.ce, KG&E

J. L. Sippel, Assistant Project Engineer, Kansas City Power & Light

W. R. Waugh, Consultant

J. Shideler, Director Administrative and Technical Services, PCA

_N. R__C.

K. V. Seyfrit, Director, Region IV (attended for opening remarks only)

W. C. Seidle, Chief, Reactor Construudon and Engineering Support Branch

W. A. Crossman, Chief, Projects Section

R. C. Hall, Chief, Engineering Support section

C. R. Oberg, Reactor Inspector, Projects Section

A. B. Rosenberg, Reactor Inspector, Engineering Support Section

J. I. Tapia, Reactor Inspector, Engineering Support Section

R. C. Hamm, Consultant

The meeting specifically at. dressed and discussed several quastions and

areas of concern by the NRC.

Each specific area was discussed individually

and with KG&E making the following commitments:

a.

Make a programmatic statement relating the testing of concrete

cubes to acceptance criteria of the concrete specifications.

b.

Make a statement relating the sand to coarse aggregate ratio, as

determined petrographically, to the concrete specification.

c.

Furnish copies of ali photographs relative to the PCA testing

program to the NRC.

d.

Provide a conversion factor for 2 inch cube strength cut from the

bottoin of cylinder fragnents developed by KG&E's consultant based

on literature search.

e.

Provide a conversion factor for 2 inch cube strength cut from the

bottom of cylinder fragments developed from field tests.

,'

.-,

-10-

'

'

.

f.

Examine approximately ten additional fragments 'petrographically

where the 90-day strength was lower than the 28-aay strength.

.

9

Make a statement indicating that the cube: were tested wet and

in the vertical position.

h.

Provide individual cube strengths for the mortar ctLe tests.

The licensee agreed to provide the additional information as a supplement

to the PCA report of February 27, 1979.

.

t

-

.

.

DETAILS III

SUMMARY OF INSPECTION VISITS MADE TO PCA DURING THE

PERIOD JANUARY 17, 1979, THROUGH FEBRUARY 9,1979

.

62 &

OMO

E.J{GallagheQ(RIII)

'

4

D

-hn

t'

5/d/71

1;. C. Hawkins LRIII)

,

b

f4LL

Sb5 /79'

g. R. liarris (.RII)

'

.

g/

.

.

DETAILS III

- - ~

.

1.

Persons Contacted During PCA Inspections

PCA

J. J. Shideler, Director of Administrative and Technical Services

L. M. Meyer, Manager, Technical Services Section

D. H. Campbell, Petrographer

R. O'Neill, Assistant Research Petrographer

KG&E

W. R. Haugh, Consultant

Kansas Corporation Commission

R. D. Sundman, Utilities Engineer I

Daniel

Chris Phillips, Site Civil Engineer

L. R. Smith, Regional Manager

2.

OIE Representatives

Janut.ry 17, 1979 - E. J. Gallagher (RIII)

F. C. Hawkins (RIII)

January 30, 1979 - E. J. Gallagher (RIII)

Febraary 9,1979 - J. R. Harris (RII)

E. J. Gallagher (RIII)

3.

Observation af Base Mat Cylinder Fragments at Portland Cement

Association

PCA)

The IE inspectors visited PCA on January 17,1;'9, to observe the

conditions of the concrete test cylinder fragments from the Wolf Creek

project.

The following observations were made at thet time:

a.

Cylinder End Conditions

The cylinder ends showed no unusual conditions with respect to

parallel ends or planeness.

A PCA representative stated that

the cylinder ends met the ASTM requirements. Any minor irregu-

larities would be corrected by the capping compound.

-13-

5 ] /)

jj9

.

b.

Failure Plane

--

The IE inspector observed that approximately 70% of the cylinuers

,

failed diagonally. Another PCA representative stated that diagonal

breaks are sometimes attributed to eccentric loading.

c.

Storage of Cylinders

The cylinders were in a bascaent hallway on a flatbed.

PCA was

awaiting notification from KG&E/ Daniel to begin preparation for

tests and sawing of 2 inch cubes for compression tests.

.

No items of noncomp'.iance or deviations ware identified.

4.

Observation of 2 Inch Cube Tests at PCA

On January 30, 1979, the IE inspector witnessed cement mortar cube

tests and tests of concrete cubes from cylinder fragments at PCA.

a.

Cement Mortar Cube Tests

The IE inspector witnessad the 7-day tests for twelve mortar

cubes, thr.'e cubes from .ach of four samples of the Cement U',er

Tests (CUT).

CUT 15

CUT 18

CUT 2.

( jT 21

The results of tests observed met the strength requirements of

ASTM C-150.

These results were reported in the PCA report, dated

Feb uary 27, 1979. The tests were performed in acccrdance with

ASTM C-109.

b.

Sawed Cube Tests

The IE inspector witnessed the testing of twenty-seven sawed 2 inch

cubes.

These cubes were sawed from sixteen cylinder fragments

salvaged from the Wolf Creek base mat concrete tests.

The actual

cube strengths ranged from 6676 psi to 9331 psi, urcorrected. These

results must yet be corrected a factor yet to be c learly established.

,r;

h

t,

W

-14-

J9

.

c.

Test Machine Calibration

,_

Af ter the testing was complete, the IE inspector observed the

calibration of the test machine, Serial No. 57271.

The PCA

-

proving ring No. 212, traceable to the National Bureau of

Standards, was used. The machine was found to be within 1%

accuracy for all loads except 5000 pounds, where the machine

was 1.1% high.

No items of noncompliance or deviations were identified.

5.

Obset vation of Petrographic Examinations

On February 9, 1979, IE inspectors made an unannounced visit to the

PCA facilities to observe the petrographic examination of test

cylinder fragments. The examiaation included: visual examination

of the cylinder remnants; ste-/eoscopic examination of five to seven

inch long lapped side pieces cut parallel to the long axis of the

cylinder remnants; and petrographic examination of thin sections

taken from the laoped side pieces.

PCA personnel indicated no

conditions potentially dcieterious to concrete have been identified.

The results of these exaniinations were reported in PCA report, dated

February 27, 1979.

No items of noncompliance or deviations were identified.

-15-

7 q,

,

J.,u

.) -