ML19225D046

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-329/79-10 & 50-330/79-10 on 790514-17. Noncompliance Noted:Failure to Properly Translate FSAR Design Requirements Into Specs & Procedures
ML19225D046
Person / Time
Site: Midland
Issue date: 06/01/1979
From: Gallagher E, Hayes D, Eric Lee
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19225D040 List:
References
50-329-79-10, 50-330-79-10, NUDOCS 7908030633
Download: ML19225D046 (11)


See also: IR 05000329/1979010

Text

.

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-329/79-10; 50-330/79-10

'

Docket No. 50-329; 50-330

License No. CPPR-81; CPPR-82

Licensee:

Consumers Power Company

1945 West Parnall Road

Jackson, MI

49201

Facility Name: Midland Nuclear Power Plant, Units 1 and 2

Inspection At: Midland Site, Midland, Michigan

Inspection Conducted: May 14-17, 1979

Inspectors:

E. J. Gallaghe

d #!D

4W& ~v[+n(-

hE.W.K. Lee

_ '/7 7

.

/

_a

,

Approved By:

D. W. Ilayes, C

[, /

$

-

Engineering Support Section 1

/

'

Inspection Summary

Inspection on May 14-17, 1979 (Reports No. 50-329/79-10; 50-330/79-10)

Areas Inspected: Reactor coolant pressure boundary and safety

related piping; pipe welding work activities; containment prestressing

work procedure, work activities and quality records (Units 1 and 2);

status of soils work activities; concrete expansion anchor installation

procedure ("aits 1 and 2).

The inspection invoised a total of 44

inspector-hours by two NRC inspectors.

Results:

Four areas were inspected.

One item of noncompliance was

identified in the areas inspected.

(Infraction - failure to properly

translate FSAR design requirements into specifications and procedures.)

440

og

2908eW

.

.

DETAILS

P-

an- Contact

-

Principal Licensee Employees (CPCo)

,

  • D.

B. Miller, Site Project Manager

  • T. C. Cooke, Project Superintendent
  • D. R. Keating, QA Group Supervisor
  • D. E. Horn, QA Engineer
  • R. G. Wollney, QA Group Supervisor
  • B. H. Peck, Construction Supervisor

R. Ostrowski, QA Engineer

Bechtel Power Corporation

  • W.

L. Barclay, Project Field QC Engineer

  • E.

Smith, Quality Assurance

  • 0. H. Holman, Field Superintendent
  • R. W. Shope, QC Supervisor
  • A.

Ozeroff, QA Engineer

  • A.

J. Boos, Field Engineer

NRC Resident Inspector

  • R.

J. Cook

kDenotes those present at the exit meeting.

Functional or Program Areas Inspected

Details of functional and program areas inspected are documented in

Sections I and II of this report.

.

s440

O!8

-2-

~

Section I

Prepared by E. J. Gallagher

Reviewed by D. W. Hayes, Chief

Engineering Support

_

Section 1

1.

Review of FSAR Containment Prestressing System Commitments

(Units 1 and 2)

The inspector reviewed FSAR Section 3.8.1.6.3 (Prestressing

System) in order to verify consistency with the site implementing

procedures.

The following apparent conflicts exist between the

FSAR commitments to the NRC and site procedures and specifica-

tions for the prestressing system:

a.

The FSAR states, " Tendon sheating is galvanized, spiral

wrapped, semi-rigid, corrugated tubing conforming to the

material requirements of ASTM A-513, Type 1, Grade 1010-

1020 or ASTM A-53, Type E or S, Grade B.

Contrary to the FSAR statement, Bechtel specification C-2,

Rev. 11, dated November 16, 1978, Section 11.1 requires

" material of shea* Ss shall conform to ASTM A366-66 or 68,

22 gauge cold rol.ed carbon steel."

In addition, the

Inryco Quality Control Manual C2-146 requires sheathing to

be of ASTM A366 material as well.

b.

FSAR Table 3.8-25 indicates the maximum allowable chemical

limits for the tendon cerrosion protective grease to be

2 ppm for chlorides, 4 ppm for nitrates and 2 ppm for sulfides.

Contrary to the above, FSAR Section 3.8.1.6.3.1 permits

the maximum allowable limits for chlorides, nitrates and

sulfides to be 5 ppm.

In addition, Bechtel specification

C-49, Rev. 2, Section 6.2.2 specifies the chemical limita-

tions for protective grease to be 5 ppm for the above

chemicals.

However, contrary to the Bechtel specification,

Inryco Quality Control Manual C2-146 requires the protective

grease to have chemical limits the same as FSAR Table

3.8-25,

i.e. 2, I. and 2 ppm for chlorides, nitrates and

sulfides, respectively.

- 3-

4

440

039

-

.

Based on the above", measures did not assure the design basis

included in design specifications were translated into the

license application which resulted in inconsistencies between

design documents and the FSAR.

This is considred an item of

noncompliance with 10 CFR 50, Appendix B, Criterion III.

(329/79-10-01; 330/79-10-01)

_

2.

Review of QC Inspector Qualifications for Containment Prestressing

System Work Activities (Units 1 and 2)

The inspection requests to review the personnel qualifications

of the Bechtel QC inspectors who would be inspecting the pre-

stressing system work activities.

The following was determined

after reviewing six personnel qualifications:

a.

It was apparent from the personnel work experience records

that none of the six inspectors had any prior experience

with prestressing systems.

b.

Training of the six inspectors was given by an individual

that likewise had no prior experience on prestressing

systems.

The above deficiency in personnel training and qualifications

was also identified by the licensee quality assurance group as

an item to be resolved prior to performing any further work

activities on the prestressing system.

Th . area will continue

to be reviewed in followup inspections of the prestressing

system.

3.

Review of Quality Records for Containment Prestressing System

(Unit 2)

The inspector reviewed the following quality records relative

to the containment prestressing system.

a.

Material Certification

(1) Tendon Wire - a review of the physical and chemical

test results was performed on tendon wire heat Nos.

9399, 9582, 9521, 9578, 9507 and 9476.

The results

meet the requirements of ASTM A421, " Uncoated Stress-

Relieved Wire for Prestressed Concrete."

(2) Tendon Bearing Flates - beat codes GL, GS, GM, GR and

GN were found to meet the requirements of ASTM A-36,

" Specification for Structural. Steel."

4-

440

040

.

,

(3) Tendon Sheathing - the tendon sheathing records were

acceptable according to the requirements of ASTM

A366-66, 22 gauge, cold rolled sheathing.

(4) Tendon Shop Head Anchorage - heat No. 53215 meet the

requirements of ASTM A-322-64, " Hot Rolled Alloy

Steel Bars."

~

(5) Tendon Bush'.ngs - heat Nos. 55984, 7836 and 15008

were reviewed and found acceptable to the requirements

of ASTM A-322 using material AISI 4142.

b.

Performance Tect_s

Construction specification C-2, Rev. 11, required the

following quality tects to be performed and submitted

prior to fabrication of the prestressing system. The test

results were not available onsite at this time.

The

licensee indicated that these quality records would be

made available during the next NRC inspection.

(1) Section 10.1 requires certified testing at low

temperatures to substantiate that the anchorage

assembly including bearing plate is capable of trans-

mitting the ultimate load of the tendon to the structure

without brittle failure. The lowest service temperature

for the anchorage is -20 F.

(2) Section 10.3 requires the sheathing filler retaining

caps to be tested to substantiate that the cap will

not fail or leak when test to 150% of required

pumping pressure.

(3) Section 14.6 requires button head rupture tests from

each reel of wire to be submitted a quality control

record.

Since the above three items were not available for review,

this item is considered unresolved pending submittal of

the records.

(329/79-10-02; 330/79-10-02)

4.

Observation of Containment Prestressing System (Unit 2)

During the course of the NRC inspection CPCo and Bechtel issued

a "Stop Work Order" on any further prestressing system work

activities. The reason for the stop work according to QA stop

-5-

b

0kl

'

work report No. 5 'was that the " status of Inryco furnished

Field Installation Manual which forms the basis for Bechtel

Field Procedure of Installation and Quality Control (PQCI) is

questionable." In order for work to resume, it was stipulated

that it would be necessary to resolve questions regarding

Project Engineering (Bechtel) level of approval for Inryco

furnished Field Installation Manual and establish approved

instruc; ions for installation and inspection including revising

,

Bechtel Field Procedure and Quality control instruction.

Due to the above work stoppage, observation of the prestressing

work activities could not be performed. This matter will

continue to be inspected to verify an adequate procedure and

inspection program is in effect for the containment prestressing

system work activities.

5.

Status of Safety Related Soils Work Activities

Safety related soils work is not preceeding until certain

corrective actions are taken in order to resolve a number of

previously identified deficiencies.

Some of the licensee's

corrective actions include:

a.

Identifying all conflicts within the PSAR or between PSAR

and FSAR.

b.

Identify all conflicts between PSAR/FSAR and site procedures.

c.

Re-evaluate the use of Zone 2 random fill material as a

backfill material.

d.

Assure that interpretations to the specifications are resolved.

Establish a single soils engineer responsible for the

e.

soils work activities.

f.

Re-evaluate the capability of the equipment being used to

meet compaction requirements.

g.

Assure proper tests are performed to document acceptability

of in place soils.

h.

Assure each nonconformance report is properly dispositioned.

During this inspection, the NRC inspector observed air bubbles

percolating f rom the ground in the safety related tank farm

area.

A closer inspection indicated that air and water was

.

-6-

440

042

'

.

being moved through the previously compacted soil mater:als in

this area.

It was observed that soil materials were being

moved by this condition and leaving voids beneath concrete

foundations for the tank structures.

This condition was brought to the attention of CPCo project

manager on May 16, 1979. On May 17, 1979, the project manager

and superintendent responded by visually observing this condition.

,

They concurred with the NRC inspector that the condition was

serious and that denage to the compacted soils may have occurred.

The extent of the movement of materials was not known.

The NRC inspector indicated to the licensee that in order to

substantiate that the materials and compaction of the soils had

not been disturbed, additional soil borings and test pits would

need to be performed. The NRC took photos to document the soil

condition and movement of soil materials.

It was also brought to the NRC's attention that CPCo QA department

had brought this condition to Bechtel QC months earlier, however,

no corrective action had been taken to correct these adverse

conditions.

During the exit meeting the CPCo site superintendent gave a

copy of a letter to the NRC requiring the contractor to relocate

the air line embedded in the fill and turn off the air to the

existing line. This letter also indicated to map the location

of all air seepage areas so that additional soil borings could

be taken in these areas.

6.

Review of Procedure and Observation of Testing Concrete Expansion

Anchors

The inspecter reviewed specification C-305, Rev. 8, " Installation

and Testing of Expansion Tn.. Concrete Anchors" and Quality

Control Instruction (QCI) -1.50, Rev. 4.

In addition, Field

Change Notices C-1835 and C-1846 to specification C-305 were

also reviewed. The following specific observations were made:

a.

As of this inspection, the specification did not require a

means of inspecting or identifying the embeddment length

of the bolt.

CPCo had identified this item in QA request

for evaluation on July 28, 1978. Bechtel then issued SCN

C-305-9002 to require a permanent length identifier to be

stamped on the bolt.

CPCo required Bechtel to develop a

procedure for ultrasonic testing to reinspect the length

of the bolts installed prior to this time.

-7-

<

h43

b.

Specification ~C-305, Table 4.1, lists certain test torques

for acceptance of concrete expansion anchor installation.

The inspector requested to review the test data which

demonstrates that the torque values specified develop a

tensite capacity equal to or greater than the design load

as required by IE Bulletin 79-02.

This data was not

readily available and will be followed up on subsequent

,

inspection as per the requirements of IE Bu.lecin 79-02.

i

c.

Specification C-305, Table 3.2, indicates the allowable

design loads for the Hilti HDI Drop-in anchors (shell type

anchors) and the required tensile test load. The test

load specified is only approximately two times the design

load.

For example, 3/4" anchor in 4000 psi concrete the

allowarie design load is 3.2 kips while the tensile test

load it 6.0 kips.

IE Bulletin 79-02 states that the licensee should verify

that the ultimate load for shell type anchors is five

times the design load.

This was indicated to Mr. W. Bird

via telecon.

This will continue to be reviewed as per IE

Bulletin instructions.

During this inspection, the h7C inspector had a telecon

with the CPCo QA supervisor relative to the requirements

of IE Bulletin 79-02.

The following is a sumnary of that

discussion:

(1) The licensee is required to identify base plates that

are considered flexible according to the criteria set

forth, i.e.

if the unstiffened distance from the

attachment to the edge of the plate is greater than

two times the thickness of the plate it is considered

flexible and requires evaluation for adequacy.

(2) The licensee must verify that the ultimate load for

wedge type anchors is four times the allowable design

load and the ultimate load for shell type anchors is

five times the design load.

(3) The design requirements for the anchor bolts should

be described for cyclic loading conditions.

(4) Verify that design requirements have been met through

existing QC documentation that (a) cyclic loads were

considered and (b) bolts installed are the specified

design size and type.

-8-

440

044

.

.

The following is the NRC's understanding of testing requirements:

The essential requirement is that the licensee justify the

adequacy of proposed testing program.

IE Bulletin 79-02 suggests

an acceptable sampling program to test one anchor bolt in each

base plate. Other approaches including a statistical sample to

provide a 95% confidence level that fewer than 5% defective

anchors are installed are equally acceptable.

It is suggested

that any test sampling program chosen should be on an individual

-

system basis when a significant failure rate is found, an

increased sample size must be taken or 100% testing may be

required to assure systems capability.

-9-

'

440

045

.

.

Section II

Prepared by E. W. K. Lee

Reviewed by D. H. Danielson, Chief

Engineering Support

,

Section 2

1.

Reactor Coolant Pressure Foundary Piping - Observation of Work

and Work Activities (Unit 2)

The inspector observed the two installed hot legs and the

installed Reactor Coolant Pump No. 2P51B section.

It was

determined that the pipe runs were installed in accordance with

the drawings.

No items of noncompliance or deviations were identified.

2.

Safety Related Piping - Observation of Work and Work Activities

(Unit 2)

The inspector observed weld end preparation of weld No. 83 on

sketch No. 2FCB36-S611-4-4.

It was determined that work activities

were performed in accordance with the applicable procedures and

good construction practices were adhered to.

No items of noncompliance or deviations were identified.

3.

Safety Related Piping - Observation of Welding Activities

(Units 1 and 2)

The inspector observed the following welding activities:

a.

Unit 1 Main Steam System Weld No. 15 on drawing no. M631,

sheet 1;

b.

Unit 1 Decay Heat Removal Discharge System

'B' Weld No.

110 v:. ucawing No. M610, sheet 6;

c.

Unit 1 Reactor Building Heating Ventilating and Air Condi-

tioning System Weld No. 25 on drawing no. M512, sheet 3;

d.

Unit 2 Decay Heat Removal Discharge System

'A' Weld No. 18

on drawing no. M611, sheet 4.

- 10 -

.

Ih r$ k

0kh

.

.

It was determined that (1) work was conducted in accordance

with traveler; (2) proper welding materials were useJ; (3)

welding procedure requirements were met; (4) work area was free

of weld rod-stubs and (5) physical appearance was acceptable.

No items of noncompliance or deviations were identified.

4.

'

Reactor Coolant Pressure Boundary Piping - Special Welding

Applications (Unit 2)

The inspector observed the following repair work activities:

Grinding and etching of cladding repair on weld no. WJI-1.

a.

b.

Weld repair of classing on weld no. WJ4-4.

It was determined that (1) work was conducted in accordance

with traveler; (2) proper materials were used and (3) procedure

requirements were met.

No items of noncompliance or deviations were identified.

5.

Safety Related Piping - Weld Heat Treatment (Units 1 and 2)

While observing welding activities for items stated in Paragraph 3

of this report, the inspector determined that preheat met the

welding procedure requirements.

No items of noncompliance or deviations were identified.

6.

Reactor Coolant Pressure Boundary and Safety Related Piping _-

Welder Qualification (Units 1 and 2)

The inspector reviewed qualifications records of welders who

performed welds identified in Paragraphs 3 and 4 of this report.

It was determined that ASt1E B&PV Code Section IX requirements

were met.

No items of noncompliance or deviations were identified.

Exit Irterview

The inspectors met with licensee representatives (denoted under

Persons Contacted) on May 17, 1979. The inspectors summarized the

scope and findings of the inspection. The licensee acknowledged the

findings as reported.

- 11 -

,

0kl