ML19225A149

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-546/79-03 & 50-547/79-03 on 790403-06. Noncompliance Noted:Failure to Properly Control Deviations to Design Documents,Failure to Adequately Insp Concrete Work,Failure to Properly Train post-tensioning QC Personnel
ML19225A149
Person / Time
Site: Marble Hill
Issue date: 05/03/1979
From: Hawkins F, Knop R, Schweibinz E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19225A130 List:
References
50-546-79-03, 50-546-79-3, 50-547-79-03, 50-547-79-3, NUDOCS 7907180474
Download: ML19225A149 (18)


See also: IR 05000546/1979003

Text

.

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-546/79-03; 50-547/79-03

Docket No. 50-546; 50-547

License No. CPPR-170; CPPR-171

Licensee:

Public Service of Indiana

1000 East Main Street

Plainfield, IN 46168

Facility Name:

Marble Hill Nuclear Generating Station Units 1 and 2

Inspection At:

Marble Hill Site, Jefferson County, Indiana

Inspection Conducted:

April 3-6, 1979

E dww

<0,,

b-

,

,

7

Inspectors:

E.

R.

Schweibinz

1

70

43f

/

'

J.

F. Suerma

[ '-

h

'

Accompanying Personnel:

D. W.

Hayes

U

'nop,Chie}b

[l

,

Approved By:

R. C.

,f

Projects Section

Inspection Summary

Inspection on April 3-6, 1979 (Report No. 50-546/79-03; 50-547/79-03)

Areas Inspected: Radiographic examination procedures for containment

liner plate; structural concrete work (Unit 1); post-tensioning work

and related quality records (Units 1 and 2); and quality records for

Unit 2 basemat.

This inspection involved a total of 76 inspector-hours

onsite by three inspectors.

.

M sults: Of the four areas inspected, no items of noncompliance or

destations were found in one area; three apparent items of noncompliance

were identified in three areas (inf raction - f ailure to properly control

deviations to design documents - Section I, Paragragph 2.b; infraction -

failure to adequately inspect concrete work activities - Section II,

Paragraphs 1.a and 1.c.(2); infraction - failure to adequately

indoctrinate and train post-tensioning QC inspection personnel - Section

II, Paragraph 2.b); One apparent deviation was identified in one

area (deviation - failure to use proper penetrameter for radiograpny

of containment liner plate - Section I, Paragraph 2.a).

~7907180y7p

DETAILS

Persons Contacted

Public Service of Indiana (PSI)

-

  • R. M. Brown, Construction Project Superintendent
  • W.

T.

Smith, Construction Field Office Supervisor

  • C. E. Chmielewski, Quality Assurance Operations Supervisor
  • T. L. McLarty, Quality Assurance Construction Supervisor
  • D.

L. Shuter, QC Engineer

  • T.

J. Geyman, QC Engineer

  • S.

T. Crumbo, Senior QC Engineer

  • W.

C. Minick, QC Inspector - Civil

W.

A.

Muenstermaa, Senior Construction Project Engineer

S. K. Farlow, Site Design Group Coordinator

Newberg - Marble Hill

  • T.

L. Kueck, Quality Assurance Supervisor

  • J.

W.

Ball, QC Engineer

J. Moore, Field QC Inspector

W.

Smith, Second Shif t Project Superintendent

Whalen - Chilstrom

  • R.

W. Noyes, Quality Assurance Supervisor

The inspectors also contacted and interviewed other licensee and

contractor personnel, including craftsmen, QA/QC, technical and

engineering staff members.

  • Denotes those attending the exit meeting.

Licensee Action on Previous Inspection Findings

(Closed) Noncompliance (546/78-08-01; 546/79-02):

Failure to follow the

procedures in the handling of NSSS equipment.

That portion of this

item had previously remained open was that the licensee had committed

to conduct training on ANSI N45.2.2 and the requirements of Regula:ory

Guide 1.38, and to change the lesson plan for training on ANSI standards

to reflect the requirements of Regulatory Guides. The inspector

reviewed the training sesson records of the training conducted

on March 19 and March 26, 1979, on the subject of ANSI N45.2.2 and

Regulatory Guide 1.38.

Lesson plan titled " Lesson Plan for ANSI Standard

and Applicable Nuclear Regulatory Guide Training Sessons" was reviewed

and found to be acceptabic.

This item is closed.

-2-

34/

00

(Closed) 10 CFR 50.55(e) (546/79-02-01):

10 CFR 50.55(e) report

on cubicle coolers supplied by the Trane Company.

The following

documentation was reviewed:

A letter f rom ".rane Company to the

Director, RIII, USNRC, dated April 3, 1979, describing the repair

and retest of the cubicle coolers; and the final report on this

item f rom Public Service of Indiana in their letter dated March 8,

1979. Evaluation of the above has determined the reports to

be acceptable. The inspector observed that four of the seven cubicle

coolers have been returned to the Marb]c Hill site and was informed

by the licensee that the other three coolers were in transit to the

site.

This item is closed.

(Closed) Noncompliance (546/78-08-02):

Inadequate inspection of

B-type cadwelds in No. 1 containment.

Training records of the U.S.

Testing QC Inspectors reflect that additional training was received

on cadwelds with emphasis applied to the calculation of void areas.

The NRC inspector reviewed several records indicating the previously

incorrect void areas were recalculated and the proper areas were

entered on the inspection records.

U.S. Testing Company cadweld

inspection records now contain a check point requiring porous metal

to be checked. This item is closed.

Functional or Prograr Areas Insr,ected

Details of functional or program areas inspected are documented in

Sections I,

11 and III as f ollows:

- 3-

)4/-

071

.

Section I

Prepared by E. R. Schweibinz

Reviewed by R. C. Knop, Chief

-

Projects Section

Radiographic Examination of Containment Liner Plate

1.

The following documentation was revicc,d:

e

a.

Marble Hill PSAR Paragraph 3. 8. 2. 6. 7, Nondestructive

Examination of Liner Plate Welds, which states, in part,

"All nondestructive examination will be performed by

personnel qualified in accordance with Section II of the

ASME B&PV Code and all examination procedures will be

in accordance with Appendix X to Section III and

Section V of the ASME BSPV Code."

b.

Appendix X to Section III of the 1971 addition of the ASME

Boiler and Pressure Vessel Code, Nondestructive Exam'. nation

Methods for Metal Containment Vessels.

(1) Paragraph X-3325, Penetrameters, Subparagraph X-3325.1,

Material, Size and Shape, states, in part, "The maximum

thickness of the penetrameter shall be as shown in

Table X-3325.1 '."

(2) Table X-3325.1-1, Standard Penetrameter Sizes, indicates

that "For a weld thickness between the range of over

1/4" through 3/8" the thickness of the penetraneter on

the source side shall be 0.0075" and the designation on

the penetraneter shall be Jo. 7."

(3)

Subsu'aarticle X-3330, Technique for Radiographic Examination

of Welded Joints, Paragraph X-3332, Required Sensitivity

of Radiographic Technique, states " Radiography shall be

performed with a technique which will have sufficient

sensitivity to indicate the features in X-3334.5 of a ,

penetrameter of the thickness specified for the thickness

of the weld being examined, as shown in Table X-3325.1-1."

(4)

Subparagraph X-3334.5, Images Which Shall Appear on

Radiographs, (a) "The images of the indentifying numbers

of the penetrameter outline and of the 2T hole are all

essential indexes of image quality on the radiograph and

they shall appear on the radiograph, except that for

penetrameters 5, 7, and 10, the slit shall appear clearly,

and hole need not appear."

-4-

34/

072

c.

Sargent and Lundy Specification No. Y-2725, Steel Liner Work

for Reactor Containment Structures Marble Hill Nuclear

Generating Station - Units 1 and 2, Division 8 - Inspection

and Testing, December 16, 1975, Division 802, Examination of

Welded Joints, Subparagraph 802.2 states that, " Examination

and testing of welds for steel liner work shal1~be in accordance

with the requirements of Standard Specification Forn STRI, with

the following modifications and as modified by Section II of

contractor's proposal:

Paragraphs 6.1.1,

as indicated

. .

below, shall be used in lieu of the same parts as specified in

Standard Specification Form STRI."

6.1.1.

Contractors shall perform all radiographic exami-

nation in accordance with che requirements of

Article 3, ASME Section V,

except that:

a.

Lead intensifying screens shall be used,

b.

Types 1 and 2 film shall be used,

c.

The minimum density for single viewing shall

be 1.5.

d.

Chicago Bridge and Iron (CB&I) Procedure No. RT2N, Rev.

3,

approved by Sargent and Lundy by a letter dated May 23, 1978,

from Kurtz to Kenyon titled " Spot Radiographic Examination

Procedure for Welds, for tne Containment and Pool Liners."

(1)

Section 3.0, References;

Subparagraph 3.1, 1974 ASME Boiler and Pressure Vessel

Code,Section III and Section V, Article 3, with the

following addenda:

S74, W74.

Subparagraph 3.2, S6L Specifications Y-2725 and Y-2766

(2) Section 4.8, Penetrameter:

The type, size and shape of

penetrameter shall be in accordance with pages 11 and

12 of this procedure.

Note:

There appears to be a typographical error as the

correct pages should be pages 12 and 13.

(3) Section 7.1.A, "The images of the identifying numbers,'

the penetrameter outline, and of the essential nole of

Table T-320 are all essential indexes of image quality

on the radiograph."

- 5-

347

073

(4) Section 7.1.B. "The film density through the veld metal

shall be 1.3 minimum for single viewing and 1.8 minimum for

composite viewing of double film exposures.

The maximum

film density through the weld shall be 3.8."

(5) Page 13 of 13, Thickness and ID of Penetraneters,

Table T-320, Thickness, Penetrameter Designations, and

Essential Holes, requires that for a single wall material

thickness of a range of over 1/4" through 3/8" the source

size penetrameter shall have a designation of No. 12 and

the essential hole shall be 4T.

Note:

The thickness of a No. 12 penetrameter is 0.012".

e.

ASME Boiler and Pressure Vessel Code,Section V,

1974 edition,

Article 3, Radiographic Examination, Table T-320, Thickness,

Penetrameter Designations, and Essential Holes, requires

that for a single wall material thickness of the range of

over 1/4" through 3/8" that the source side penetrameter shall

be a size 12 with an essential hole of 4T.

Note: A size 12 penetrameter has a thickness of 0.012".

2.

Evaluation of the Above Documents

a.

The RIII inspector requested the licensee to explain the

apparent deviation between:

(1) The commitment in the PSAR to

have all nondestructive examintion procedures in accordance

with Appendix X to Section III of the ASPE Boiler and Pressure

Vessel Code, which requires the use of a 0.0075" thick pene-

trameter f or a weld thickness over 1/4" through 3/8" (the

liner plate is 1/4" thick) and; (2) The requirement of CB&I

Procedure No. RT2S to determine the thickness of the pene-

trameter in accordence with Table T-320 which requires a

penetrameter 0.012" thick for the same material thickness.

Table T-320 appears in the Chicago Bridge and Iron (CB&I)

procedure RT25.

The licensee contacted Mr. R. Kurtz from Sargent and Lundy

(S6L) for assista. ace.

Mr. Kurtz explained that CB&I had requested

to use Article 3 of Section V instead of Appendix X to Section

III of the ASME Boiler and Pressure Vessel Code.

An evaluation

of the two documents made by Sargent and Lundy, determined

Article 3 to ASME Section V could be used with some exceptions.

These exceptions were stated in the S6L Specificction Y-2725.

It

should be noted at this time that the No. 12 penetrameter

called for in Article 3 of Section V is 60% thicker than the

No. 7 penetrameter as called for in Appendix X to Section III.

Mr. Kurtz could not explain why the thicker penetrameter was

allowed to be used in lieu of the commitment in the PSAR.

-6-

347

0/4

.

This item is a deviation from a commitment in the PSAR.

(546/79-03-01:547/79-03-01)

Note:

The RIII inspector recognizes that Section III of the

ASME Boiler and Pressure Vessel Code does not require that

the containment liner plate seam welds be radiographed.

However, Regulatory Guide 1.19 does require that these seam

welds be spot radiographed.

Marble Hill PSAR Section 1.7

commits to Regulatory Guide 1.19, August 11, 1972, Non-

destructive Examination of Primary Containment Liner Welds.

Regulatory Guide 1.19: Paragraph C.1, Nondestructive

Examination of Liner Seam Welds, Subparagraph C.1.a requires

that welds be examined radiographically in accordance with

the techniques prescribed in Section V.

(ASME BLPV Code);

Subparagraph 7.a, Containment Liner Seam Welds Examined

by Radiography, states, "Where a spot in the seam weld is

judged acceptable in accordance with the referenced

standards of NE-5120 of Section III of the ASFE BLPV Code,

the entire weld test unit represented by this spot radio-

graph is considered acceptable."

Subarticle NE-5120, Examination Requirements cf Welded

Joints for Vessels, of Section III of the 1971 Edition of

the ASME B&PV Code states, " Examination in accordance with

the requirements of Section VIII, Division 1 of this Code

shall be made of welded joints for vessels as follows:

(a) Welded joints of Categories A and B as defined in

NB-3351 shall be radiographed in accordance with UW-51."

Subparagraph NB-3351.1 defines Category A welded joints

as longitudinal welded joints within the main shell.

Subparagraph NB-3351.2 defines Categorv B welded joints

as circumferential welded joints within the main shell.

UW-51 to Section VIII, Division 1 of the ASME Boiler and

Pressure Vessel Code, Table UW-51, Standard Penetrameter

Sizes, requires that a penetrameter for weld thickness

range of over 1/4" through 3/8" be of a thickness of

0.0075" and designated a No. 7 penetrameter.

The liner

plate is 1/4" thick. The commitment in the PSAR Paragraph

3.8.2.6.7 requires that all examination procedures will be

in accordance with Appendix X to Section III and Section V

of the ASMI Boiler and Pressure Vessel Code. Appendix X '

to Section III and Article 2 of Section V are acceptable

methods of meeting the requirements of Regulatory Guide 1.19, since their examination requirements are equivalent.

-7-

c

,4/

0,/J

.-

3

.

b.

Minimum Field Density

As required by Sargent and Lundy Specification Y-2725, the

minimum density for single viewing shall be 1.5.

CB6I procedure

No. RT2N states, "The minimum film density through the weld

metal shall be 1.3 minimum for single viewing,

."

It

. . .

_

was determined during the discussions with Mr. Kurtz that the

original issue of procedure No. RT2N did have the requirement

of the 1.5 minimum film density for single viewing but that

a later revision had revised the minimum film down to 1.3 in

that procedure which is contrary to the requirements of SEL

Specification Y-2725.

The procedure was approved by Sargent

and Lundy and it did not conform to the requirements of the

specification.

This is an item of noncompliance with 10 CFR 50, Appendix B,

Criterion III.

(546/79-03-02; 547/79-03-02)

,

- 8-

34/

076

Section II

Prepared by F. C. Hawkins

,

Reviewed by D. W. Hayes, Chief _

Engineering Support

Section 1

1.

Observation of Safety Related Concrete Work Activities and

Related Quality Records

The inspector observed in process pre-placement and post-placement

concrete work activities and the related quality records for

several Category I concrete placements.

Specific observations

were as follows:

a.

Pre-Placement Inspection - On April 5, 1979, the inspector

performed a pre-placement inspection of placement No.

1S-377-1.

15-377-1 is a 96 cubic yard slab located in

Steam Tunnel No. 1.

At the time of the inspection

(approximately 5:00 p.m.) the following observations were

made:

(1)

Five reinforcing bars were not secured against displace-

ment during concrete placement

required by WCJV

am

WCQAP-9, Rev.

1, Attachment A, Item 8.

(2) Reinforcing steel was not free from containments as

required by WCJV WCQAP-9, Rev.

1, Attachment A,

Item 2.

(3) Adjacent concrete surfaces, forework, waterstops, and

joint filler material were not adequately cleaned for

concrete placement as required by Newberg QAPN-10,

Rev. 3, Section 4.4.

Subsequent review of the ISS-377-1 Newberg Placement Check

Sheet revealed that it had been signed-off by the responsible

WCJV and Newberg QC inspectors to accept Items 1 through 3

above prior to their completion, without noting any work -

to be completed after concrete placement had begun.

In

addition, the Newberg QC Engineer had also signed off the

Placement Check Sheet prior to completion of Items 1 through

3 above.

This sign-off gives him the authority to sign the

PSI Placement Check Sheet for release of the area for place-

ment of concrete as stated in Newberg QAPN-10, Rev. 3,

Section 4.6.

_9_

347

077

The accompanying PSI QC Civil Inspector concurred with the

inspector that Items 1 through 3, noted above, were not

acceptable and that more work would be required prior to

concrete placement.

Furthermore, he stated that he would

not release the area for placement until the required work

.

was complete.

_

Licensee personnel stated that the WCJV and Newberg QC

inspectors are charged with the responsibility of 1007 first

line inspection of concrete placements to verify quality

cf the work in their respective disciplines.

The PSI QC

Civil Inspector performs only surveillance inspection of the

placement area and must base his release for concrete place-

ment on that inspection.

It is the inspector's concern that

the first line inspection is adequate to verify quality of

all completed work prior to concrete placement.

The licensee was advised that this failure to execute the

program for inspection of activities affecting quality

to verify conformance with documented instruction, proc ec'ur es

and drawings is considered an item of noncompliance with

10 CFR 50, Appendix B, Criterion X.

(546/79-03-03;

547/79-03-03)

b.

Concrete Testing - Compressive strength cylinder Nos. 1847,

1849, 1854, 1857 and grout cube No. 1846 representing

placement No. ICW-Ext-4, 4a, 4b were observed to be initially

cured in accordance with ASTM C31. The inspector also

verified the cylinders and cubes were transported from the

field within the time limit specified by ASTM C31, stripped

and placed in the required curing at 73.4 + 3F at the

U. S. Testing Laboratory.

c.

Post-Placement Inspection

(1) Curing of In-Place Concrete - Proper curing techniques

in accordance with the job specification were observed

for placement Nos. ICS-390-1 and ICW-Ext-4, 4a , 4b.

Review of the Newberg Curing Card verified that both

placements were inspected at least once daily by the

Newberg QC inspector to assure proper curing methods

and duration.

-

(2) Form Removal Inspection - During a tour of the Auxi'iary

Building, the inspector observed numerous areas of

defective concrete (i.e., honeycomb).

Further inspection

revealed the following:

_

- 10 -

34/

C78

~

(a) One area of hrneycomb located at U and 16-17

lines, Elevation 383' slab, which had not been

identified by Newberg QC.

Newberg QAPN-10, Rev.

3,

dated May 1, 1978, Section 4.7.3 states that,

"At completion of form removal, the QC inspector

shall inspect and attach Temporary Hold Tags

(Att. G) to all defective areas."

Repair work

had commenced in this one defective area without

the responsible Newberg QC inspector's knowledge

of it. In addition, at least three honeycomb

areas in each the Auxiliary Building, Elevation

383' slab and the Reactor Building Unit I exterior

wall, Az. 300 , were not properly tagged for

status and repair in accordance with Newberg QAPN-10.

(b) Two repaired areas, one located at P between 17 and

18 lines, Elevation 383' slab and another located

at U and 19 lines, Elevation 364', which were not

cured in accordance with ACI 301-72, Chapter 9 and

Newberg WPN-25, Rev. O.

ACI 301-72 states in

part, that, "The patched area shall be kept damp

for 7 days."

WPN-25 states in part, that, "If

forms are removed prior to completion of the

seven-day core period, the surface will be sprayed

with an approved curing compound .

." Licensee

. .

personnel concurred with the inspector that

neither area was being cured properly at the

time of this inspection.

Items (a) and (b) are further examples of noncompliance

as cited previously in Section 1.a of this report.

(546/79-03-03; 347/79-03-03)

2.

Containment Post-Tensioning - Observation of Work Activities and

Related Quality Records

The inspector toured the Units 1 and 2 Reactor Buildings and

observed that post-tensioning work at this time consists of the

installation of trumplates, funnels, conduits, and couplers.

Newberg Construction Company subcontractor, Whalen-Chilstrom

Joint Venture (WCJV) is performing the installation and QC

-

inspe_ tion of this hardware.

a.

Maintenance of Installed Post-Tensioning Items

(1) Trumplates (Units 1 and 2) - The installed trumplates

in Unit I tendon gallery were inspected by licensee

personnel and the inspector for maintenance of corrosion

- 11 -

7 !7

nTO

Jk/

h//

protective paint.

Some slight corrosion around the

edge of all ten trumplates inspected was noted.

To

preclude detrimental corrosion of the trumplates, the

licensee stated that he would institute periodic

inspection of them as part of a scheduled surveillance

plan.

The inspector has no further questions about

this matter at this time.

(2) Conduit (Unit 1) - During the course of the inspection,

it was noted to licensee personnel that the temporary

plastic conduit covers were not installed in the Unit I

horizontal tendon conduits as suggested by the manu-

facturer.

The licensee stated that it was his intention

to do so, and immediately initiated installation of

the plastic covers.

The inspector has no further

questions about this matter at this time.

b.

Certification of Post-Tensioning Personnel

A review of the indoctrination and training records for

WCJV post-tensioning QC personnel revealed the certification

records failed to meet the requirements of ANSI N45.2.6-73,

in that they included ne Certificate of Qualification as

specified in ANSI N45.2.6-73, Section 2.2.4.

In addition,

WCJV WCQAP-7, Rev. 2, Section 4.1.2 and Attachment A does

not provide for the indoctrination and training of post-

tensioning QC personnel.

This failure to provide for the indoctrination and training

of personnel performing activities affecting quality as

necessary to assure that suitable proficiency is achieved

and maintained is considered an item of noncompliance with

10 CFR 50, Appendix B, Criterion II.

(546/79-03-04;

547/79-03-04)

.

.

- 12 -

347

030

Section III

Prepared by J. F.

Suermann

_

Reviewed by D. W. Hayes, Chief

_

Engineering Support

Section 1

Quality Records - Unit II Basemat

1.

Geneqal

Public Service of Indiana (PSI) performs site surveillcnce of its

contractors for the installation of reinforcing steel (rebar) and

the use of mechanical splices (cadwelds) associated with rebar

installation. PSI's site contractor for basemat work is

G. K. Newberg Company and the sub-contractor for rebar work and

cadweld work is Whalen-Chilstrom Joint Venture (Whalen-Chilstrom).

The quality records on a portion of the basemat rebar and cadwelds

were reviewed against the requirements of Sargent and Lundy

Specification Y-2850, dated February ll, 1977, " Inspection and

Testing Services," and Sargent and Lundy Specification BY/ER/MCS,

Rev. 7, July 5, 1978, "Specificaticn for Making and Inspecting

Mechanical (Cadweld) Splices."

The inspector noted that Paragraph

1.3.3 of Specification BY/BR/MCS incorrectly made re2erence to ANSI

Standard N45.2.5-1975.

Discussion between the licensee and Sargent

and Lundy ascertained that the standard should have read N45.2.5-

Draft 1975 (which subsequently became N45. 2. 5-1978) .

The licensee

obtained a commitment from Sargent and Lundy that the specification

would be corrected. A representative of ERICO Products,

Incorporated (the cadweld supplier) observed the first twenty-five

production cadweld splices on January 11-12, 1978, as required by

Paragraph 5.2 of Specification BY/BR/MCS.

The cadwelds were

found to be acceptable.

2.

Cadweld Inspection Records

The inspector reviewed Whalen-Chilstrom drawing CMS C17B dated

May 21, 1978, which plotted and identified a total of 62 cadweid

splices in layer 12 of the basemat for the Unit II containment.,

All splices were made on grade 60 steel No. 18 rebar and were

installed in the horizontal position.

All 62 splices were made

.

e

- 13 -

jy/

b

using kit No. RBT-1891-H, sleeve No. S-1298, and powde" batch No.

P20884 or No. P20348. The installation records revie-ed by the

inspector were as follows:

a.

Whalen-Chilstrom Request for Cadweld Material, dated September 1,

1978, and the associated U. S. Testing Company-Field Cadweld

Visual Inspection Report.

The report was properly approved

and stated the following splices met the specificaticn.

P-561-1

P-561-6

P-561-2

P-561-7

P-561-3

P-561-8

P-561-4

P-561-9

P-561-5

P-561-10

b.

Whalen-Chilstrom Request for Cadweld Material, dated September 1,

1978, and the assoicated U.

S. Testing Company Field Cadweld

Visual Inspection Report. The report was properly approved

and stated the following splices met the specification.

P-562-2

P -5 62-5

P-562-3

T-562-6

P-562-4

One splice, P-562-1, wa s rej ec ted due to a damaged sleeve and

replaced by P-569-1 (which was accepted).

c.

Whalen-Chilstron Request for Cadweld Material, dated September 1,

1978, and the associated U.

S. Testing Company Field

Cadweld Visual Inspection Report.

The report was properly

approved and stated the 'ollowing splices met the specification.

P-563-1

P- 56 3- 5

P-563-2

P-563-6

P-563-3

P-563-7

P-563-4

P-563-8

d.

Whalen-Chilstrom Request for Cadweld Material, dated September 1,

1978, and the associated U. S. Testing Company Field Cadweld

Visual Inspection Report.

The report was properly approved

and stated the following splices met the specification.

'

.

P-564-1

P-564-7

P-564-2

P-564-8

P-564-3

P-564-9

P-564-4

P-564-10

F-564-5

P-564-11

P-564-6

_

- 14 -

347

082

e.

Whalen-Chilstrom Request for Cadweld Material, dated September 1,

1978, a..o the associated U. S. Testing Company Field Cadweld

Visual Inspection Report.

The report was properly approved

and stated the following splices met the specification.

P-567-1

P-567-6

P-567-11

P-567-2

P-567-7

P-567-3

P-567-8

P-567-13

P-567-4

P- 567- 9

P-567-14

P-567-5

P-567-10

P-567-15

A " sister" splice, S-567-12, was made relative to production

splice No. P-567-11 and was subsequently tested to 96,250 psi

which exceeded requirements.

f.

Whalen-Chilstrom Request for Cadweld Material, dated September 1,

1978, and Daily Inspection Checklist for Cadweld Inspections

f or splices P-568-2 and P-568-5 dated September 1, 1978, which

indicated pre-placement checkpoints were acceptable for both

splices. The associated U. S. Testing Company Field Cadweld

Visual Inspection Report was also reviewed and stated that the

following splices met the specifications.

P-568-1

P-568-6

P-568-11

P-568-2

P-568-7

P-568-12

P-568-3

P-56 8- 8

P-568-13

P-568-4

P-568-9

P-558-14

P-568-5

A " sister" splice, S-568-10, was made relative to production

splice No. P-568-9 and was subsequently tensile tested to

105,750 psi which exceeded requirements.

g.

Whalen-Chilstrom Request for Cadweld Material, dated September 2,

1978, and the associated U.

S. Testing Company Field Cadweld

Visual Inspection Report.

The report was properly approved

and stated splice P-569-1 met the specification.

3.

Cadweld Tensile Testing

The inspector reviewed U. S. Testing Company Incorporated Prccedure

QCP-ll, Rev. 1, dated November 7, 1978, " Inspection and Testing of

Reinforcing Steel and Cadweld Splices." Cadweld Splice Test Report

No. 78- 160, dated Septceber 5,1978, was checked by a Level II

inspect or and reviewed by a Level III inspector.

The test report

appeared to meet the requirements of the testing procedure and

indicated the following:

_

- 15 -

347

083

Splice

Ult. Load

Failura Mode

Iensile Strength

S-568-10

423,000 lbs.

Bar Failure

105,750 psi

S-567-12

385,000 lbs.

Bar Failure

96,250 psi

-

The report stated both splices met the required criteria.

4.

Material Certification - Cadwelds

Whalen-Chilstrom audits ERICO Products, Incorporated, on an annual

basis with audits having been done March 22, 1978 and, most recently,

March 26, 1979. The March 26, 1979, audit done by the Whalen-

Chilstrom QA Supervisor found ERICO's QA program to be acceptable.

The site contractor, G. K. Newberg, in turn reviews and audits

Whalen-Chilstrom's QA program approxirctely every 90 days.

The

inspector reviewed the following documents for compliance with the

requirements of ANSI standard N45.2.13-1976 and they appeared te be

in order:

a.

Material Certification, dated June 30, 1978, on sleeve type

S-1298 was signed by the ERICO QA manager. Certification indi-

cated a yield strength of 90,500 psi and a tensile strength of

104,100 psi.

b.

Final Inspection Report, dated August 29, 1978, signed by r.i

ERICO QA representative indicated splice kit T-1891-H was

acceptable.

c.

Certificate of Conformance, No. 10340, (ated August 29, 1978,

was signed by an ERICO QA representative and indicated confor-

mance to recognized standards for powder batch P-20884,

sleeve S-1298 and kit T-1891-H.

5.

Storage Inspection and Surveillance - Cadweld and Rebar

G. K. Newberg Company has neasures to accomplish storage inspection

and surveillance o; cadweld material incorpormted in their quality

control procedures. The inspector reviewed quality records as

fellows and they appeared to be in order:

a.

Site Surveillance Report No. 1103785038, dated November 1,

1978, was signed by a PSI 0C en;4naar and indicated proper-

tagging, logging and storing of rebar ano proper issuiog

and storing of cadweld materials.

b.

Site Surveillance Report No. 0215795024, dated February 13,

1979, was signed by a PSI QC ergineer and indicated cadweld

materials were stored properly. Additionally,_the report

- 16 -

34/

084

indicated crucibles used for the cadwelds were preheated,

splice sleeves were cleaned and preheated as were the rebar

ends, and finally the cadwelds were identified and inspected

according to procedures with no apparent discrepancies.

c.

Site Surveillance Report No. 0309795028, dated March 6, 1979.

-

was signed by a PSI QC engineer and indicated rebar was stored

in designated areas and tagged and logged in upon receipt

at the storage area; cadwelds were stored in dry areas,

issued by requisition and logged in the QA field office.

6.

Nonconformances - Corrective Action

The inspector reviewed approximately ten of the change requests

and nonconformances written on the Unit II basemat.

The following

documents, typical of all those reviewed, indicated that corrective

action was applied to a field change or nonconforming situation,

that the required engineering review vas accomplished, and that

final approval by the QA department was obtained:

a.

Newberg Contractor Change Request (CCR) No. 037, dated

August 17, 1978.

b.

Newberg Contractor Change Request (CCR) No. 073, dated

September 14, 1978.

c.

Whalen-Chilstror Nonconformance Report (NCR) No. 32, dated

February 8, 1979.

d.

Newberg Nonconf ormance Report (NCR) No. 083, dated

May 4,

1978.

7.

Cadweld Operator Qualification

Regulatory Guide 1.10, Rev.

1, datee sanuary 2,

1973, and Specification

BY/BR/MCS require that each operator perform two qualification

splices on the largest size rebar used in a given position.

The

inspector reviewed the quality records of Whalen-Chilstrom and

U. S. Testing Company and determined for the six operators who

installed the 62 splices in layer 12 of the Unit II basemat that

(a) they had all performed the two qualifications splices in the

horizontal position, (b) the qualification splices were all

accep!9hle based on tensile testing, and (c) all six operators l

were qualified at the time the layer 12 splices were made.

No items of noncompliance were identified in the above areas.

.

- 17 -

347

085

.

.

Exit Meeting

The inspectors met with the site staff representatives (denoted in

the Persons Contacted paragraph) at thc conclusion of the inspection

on April 6, 1979. The inspectors sum =arized the scope and findings

of the inspection including the three apparent items of noncocpliance

identified in Section I, Paragraph 2.b,Section II, Paragraphs 1.a

and 1.c.(2), and Section II, Paragraph 2.b, and the one apparent

deviation identified in Section I, Paragraph 2.a of the Details section

of this report. The licensee acknowledged the findings.

.

- 18 -

347

086