U.S. NUCLEAR REGULATORY COMMISSION
.
OFFICE OF INSPECTION AND ENFORCEMENT
REGION III
Report Nos. 454/79-16; 455/79-16
Docket Nos. 50-454; 50-455
Iicense Nos. CPPR-130; CPPR-131
Licensee: Commonwealth Edison Company
P.O. Box 767
Chicago, IL 60690
Facility Name: Byron Station, Units 1 and 2
Inspection At: Byron Site, Byron, Illinois
Inspection Conducted: October 23-25, 1979
/}.I h
"/'NY
Inspector: E. W. K. Lee
Approved by: D. H. Danielson, Chief
[77b <""> ' o T'
'"
'
'
-
Engineering Support Section 2
Inspection Summary: Inspection on October 23-25, 1979 (Reports Nos.
50-454/79-16; 50-455/79-16)
Areas Inspected: Reactor Coolant Pressure Boundary and Safety Related
Piping work activity and welding; quality records and procedures. The
inspection involved a total of 20 inspector hours on site by one NRC
inspector.
Results: Of the six areas inspected, no apparent items of noncompliance
or deviation were identified in five areas, one apparent item of noncom-
pliance was identified in one area (infraction - inadequate procedure,
paragraph 3a).
.
1630
22
7 E12200 5 [f
.
.
DETAILS
.
Persons Contacted
Principal Licensee Employees
- S. T. Forsha, Structure QA Coordinator
- T. McIntire, QA Supervisor
- J. Porter, Mechanical QA Coordinator
- G. Sorenson, Project Superintendent
- M. Stanish, QA Engineer
- R. Tuetkin, Lead Mechanical Engineer
Hunter Corporation
- J. H. Robertson, Welding Engineer
- M. Somsag, QA Supervisor
The inspector also contacted and interviewed other licensee and contractor
personnel, including area superintendents and craftsmen.
- Denotes those present at the exit interview.
Licensee Action on Previous Inspection Findings
,
(Closed) Noncompliance Item (454/79-02-02; 455/79-02-01) - Control of
welding material: The inspector reviewed the randomly selected weld
material issuance slips and determined that returned unused materials
wer' marked on the slips.
(Closed) Unresolved Item (454/79-12-01; 455/79-12-01) - Pipe storage: The
inspector reviewed the pipe storage surveillance report which indicated
that the storage conditions were corrected.
(Closed) Noncompliance Item (454/79-12-01) - Weld data sheet hold point:
The inspector reviewed the nonconformance report and determined it was
properly closed.
(Closed) Noncompliance Item (454/79-12-03; 455/79-12-02) - Control of
Document: The inspector verified that the procedure supplements have
been redistributed. The revised procedure was also reviewed.
Functional or Program Areas Inspected
1.
Peactor Coolant Pressure Boundary Piping - Observation of
Work and Work Activities (Unit 1)
The inspector observed weld end preparation of Safety Injection
System weld No. 122 on Isometric Drawing No. SI-6 and Spool No. SI-1
1630
23
-2-
.
on Isometric Drawing No. SI-1-4. It was determined that work activities
were performed in accordance with the applicable procedures and good
a
construction practices were adhered to.
No items of noncompliance or deviations were identified.
2.
Reactor Coolant Pressure Boundary Piping - Review of Quality Records
The inspector reviewed the Westinghouse Corporation Quality
a.
Release, ASME data Report and Receiving Inspection Report for
the following piping spools:
(1) QR No. 35627 for spool No. CBE-Loop-1-6
(2) QR No. 35628 for spool No. CBE-Loop-2-1
(3) QR No. 35630 for spool No. CBE-Loop-2-6
(4) QR No. 31246 for spool No. CAE-Loop-2-1
(5) QR No. 31244 for spool No. CAE-Loop-3 f
(6) QR No. 35633 for spool No. CBE-Loop-3-6
(7) QR No. 35634 for spool No. CBE-Loop-4-1
(8) QR No. 35635 for spool No. CBE-Loop-4-6
-
It was determined that the documents are legible and acceptable.
b.
The inspector reviewed the pipe storage inspection records for
the period between February 1978, and August 1979. It was
determined that (1) the records are difficult to retrieve; (2)
inspection was performed at the required frequency and (3)
storage requirements were met.
The inspector reviewed the following CECO audit reports:
c.
(1) CECO Audit Reports No. 6-79-201, No. 6-79-215, No. 6-79-180
and No. 6-78-160.
(2) CECO reports of audit performed at Westinghouse Corporation,
Monroeville for years 1977, 1978.
It was determined that the records are acceptable and findings
were closed out in a timely manner. However, the audits at
Westinghouse were performed by CECO home office personnel hence
not all the supporting documents, such as follow-up actions,
checklists used during the audits, were available on site. The
licensee stated those documents can be made available, including
the 1979 audit report, on site. This matter is considered unre-
1630
324
-3-
.
solved pending a review during a subsequent inspection.
(454/79-16-01)
>
No items of noncompliance or deviations were identified.
3.
Reactor Coolant Pressure Boundary Piping - Observation of
Welding Activities (Unit 1)
The inspector observed the followlag welding activities:
a.
(1) Reactor Coolant System, Weld No. 219 on isometric drawing
No. RC-1-1, Welds No. 82 and 83 on isometric drawing
No. RC-1
(2) Safety Injection System, Weld No. 109 on isometric drawing
No.
SI-1.
It was determined that (1) work was conducted in accordince
with traveler; (2) proper welding materials were used; (3)
welding procedure requirements were met; (4) work area was free
of welding rod-stubs; (5) physical appearance was acceptable
and (6) weld end detail for weld No. 219 on isometric drawing
No. RC-1-1 was not specified and accepted by QC inspector based
on no acceptance criteria. This condition is an item of noncom-
pliance identified in Appendix A. (454/79-16-02)
b.
The inspector observed liquid penetrant examination of Safety
.
Injection System, Weld No. 141 on isometric drawing No. SI-5
and weld No. 111 on isometric drawing No. SI-1. It was determined
that: (1) surface condition was acceptable; (2) procedure
requirements were met and (3) personnel were properly qualified.
Except as noted, no items of noncompliance or deviations were identified.
4.
Reactor Coolant Pressure Boundary and Safety Related Piping -
Welding Material Control (Units 1 and 2)
a.
Review of Documents
(1) The inspector established that Hunter Corporation procedure
for welding material control has not been revised since
the last review (IE inspection Reports No. 50-454/79-12
and No. 50-455/79-12, paragraph 3a) except procedure
No. 5.101. The current revision of this procedure is
revision 6. The revision was reviewed.
(2) Receiving Inspection Report, Material Certification and
Purchase Order for ER 308L welding rod with heats No. 741403
and No. 741573 and ERNicr-3 welding rod with heats No. 762453
and No. 760460.
1630 325
-4-
.
It was determined that the above documents met the PSAR, 10 CFR
,
50, Appendix B and the applicable code requirements.
b.
Control of Materials
The inspector toured welding material issuing stations No. 3
and No. 5. It was determined that (1) the welding materials are
properly identified and segregated; (2) the temperature of the
rod oven is maintained; (3) records are properly kept; and (4)
issuance and return of welding materials are controlled in
accordance with approved procedures.
No items of noncompliance or deviations were identified.
5.
Reactor Coolant Pressure Boundary and Safety Related Piping -
Welder Qualification (Unit 1)
The inspector reviewed the following documents:
Ilunter Corporation Site Implementing Procedure No. 5-301,
a.
Revision 6, " Welder Qualification."
b.
Qualification records of welders who performed welding of welds
identified in paragraphs 3a and 7 of this report).
The inspector determined that the above documents met the requirements of
,
No items of noncompliance or deviations were identified.
6.
Safety Related Piping - Observation of Work and Work Activities
(Unit 1)
The inspector observed weld end preparation of Safety Injection System,
Spool No. SI-13-10 on isometric drawing No. SI-13. It was determined
that work activities were performed in accordance with the applicable
procedures and good construction practices were adhered to.
No items of noncompliance or deviations were identified.
7.
Safety Related Piping - Observation of Welding' Activities
(Unit 1)
The inspector observed the following welding activities:
Component Cooling Water System, Weld No. 689 on isometric drawing
a.
No. CC-48, Weld No. 28B on isometric drawing No. CC-1 and Weld
No. 93 on isometric drawing No. CC-5.
b.
Containment Spray System, weld No. 282 on isometric drawing
No. CS-23.
1630 326
-5-
.
c.
Residual Heat Removal System, weld No. 181 on isometric No. RH-7.
,
d.
Safety Injection System, Weld No. 342 on isometric drawing
No. SI-13-13
It was determined that (1) work was conducted in accordance with
traveler; (2) proper welding materials were used; (3) welding proce-
dure requirements were met; (4) work area was free of weld rod-stubs;
(5) physical appearance was aedeptable and (6) weld No. 28B on
isometric drawing No. CC-1 was rejected by the QC inspector because
of bad fit-up.
Unresolved Items
Unresolved items are matters about which more information is required in
order to ascertain whether they are acceptable items, items of noncompliance,
or deviations. Unresolved items disclosed during the inspection are discussed
in paragraph 2c.
Exit Interview
The inspector met with licensee representatives (denoted under Persons
Contacted) at the conclusion of the inspection on October 25, 1979. The
inspector summarized the purpose and findings of the inspection. The
licensee acknowledged the findings reported herein.
.
1630
a27
.
-6-