Forwards IE Insp Rept 50-364/79-16 on 791023-26.No Noncompliance Noted
ML19211A081
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 11/15/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Clayton F
ALABAMA POWER CO.
Shared Package
ML19211A076 List:
References
NUDOCS 7912170010
Download: ML19211A081 (2)


See also: IR 05000364/1979016

Text

,'

f nou

'o,,

'

UNITED STATES

8

NUCLEAR REGULATORY COMMISSION

o

g

ae

REGION 11

O

101 MARIETTA ST., N.W., SUITE 3100

o

ATLANTA, CEORGIA 303o3

NOV 151979

In Reply Refer To:

RII:MDH

50-364/79-16

Alabama Power Company

. Attn:

F. L. Clayton, Jr.

Senior Vice President

Post Office Box 2641

Birmingham, Alabama 35291

Gentlemen:

This refers to the inspection conducted by M. D. Hunt of this office on

October 23-26, 1979 of activities authorized by NRC Construction Permit No.

CPPR-86 for the Farley Nuclear facility, and to the discussion of our findings

held with J. A. Mooney at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were disclosed.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application within 20 days

to this office to withhold such information from public disclosure. Any such

application must include a full statement of the reasons on the basis of which

it is claimed that the information is proprietary, and should be prepared so

that proprietary information identified in the application is contained in a

separate part of the document.

If we do not hear from you in this regard within

the specified period, the report will be placed in the Public Document Room.

1594

118

7 91217o O\\ O

.

-

,

)

Alabama Power Company

-2-

NOV 151979

,

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

M

,

C. E. Murphy, Chief

Reactor Construction and

Engineering Support Brasch

' Enclosure:

Inspection Report No. 50-364/79-16

cc w/ enclosure:

A. R. Barton

Executive Vice President

Post Office Box 2641

Birmingham, Alabama 35291

H. O. Thrash

Manager, Nuclear Generation

Post Office Box 2641

Birmingham, Alabama 35291

C. Biddinger, Jr.

Manager-Corporate Quality Assurance

Post Office Box 2641

Birmingham, Alabama 35291

W. G. Hairston, III

Plant Manager

Drawer 470

Ashford, Alabama 36312

l}Qf

ll}

R. E. Hollands, Jr.

QA Supervisor

Post Office Box U

Ashford, Alabama 36312

.