Forwards IE Insp Repts 50-440/79-07 & 50-441/79-07 on 790910-12 & Notice of Violation
ML19210E408
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 10/04/1979
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Davidson D
CLEVELAND ELECTRIC ILLUMINATING CO.
Shared Package
ML19210E409 List:
References
NUDOCS 7912050006
Download: ML19210E408 (2)


See also: IR 05000440/1979007

Text

b

-

.

-

'o

UNITED STATES

l'

NUCLEAR REGULATORY COMMISSION

,

g

g

.-r

REGION lil

"

O[

799 ROOSEVELT ROAD

o,

% **

GLEN ELLYN. ILLINOIS So137

o

    • .*

OCT

.s79

Docket No. 50-440

Docket No. 50-441

The Cleveland Electric Illuminating

Company

ATTN: Dalwyn R. Davidson

Vice President - Engineering

Post Office Box 5000

Cleveland, OH 44101

Gentlemen:

This refers to the inspection conducted by Mr. C. M. Erb of this office

on September 10-12, 1979, of activities at Perry Nuclear Power Plant,

Units 1 and 2, authorized by NRC Construction Permits No. CPPR-148 and

No. CPPR-149 and to the discussion of our findings with Mr. Kacer and

others at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted of

a selective examination of procedures and representative records, obser-

vations, and interviews with personnel.

During this inspection, certain of your activities appeared to be in

noncompliance with NRC requirements, as described in the enclosed

Appendix A.

This notice is sent to you pursuant to the provisions of Section 2.201 of

the NRC's " Rules of Practice," Fart 2, Title 10, Code of Federal Regulations.

Section 2.201 requires you to submit to this office within thirty days of

your receipt of this notice a writteu statement or explanation in reply,

including for each item of noncompliance: (1) corrective action taken and

the results achieved; (2) corrective action to be taken to avoid further

noncompliance; and (3) the date when full compliance will be achieved.

!

f

.

-

.

.

1500

191

7 91205 0 M

.

.

OCi

3 79

The Cleveland Electric

-2-

._

Illuminating Company

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter, the enclosures,

and your response to this letter will be placed in the NRC's Public

Dc :ument Room, except as follows.

If the enclosures contain information

that you or your contractors believe to be proprietary, you must apply in

writing to this office, within twenty days of your receipt of this letter,

to withhold such information from public disclosure. The applicacion

must include a full statament of the reasons for which the information is

considered proprietary, anc should be prepared so that proprietary infor-

mation identified in the application is contained in an enclosure to the

application.

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

e

s'

'

Gaston Fiorelli, Chief

Reactor Construction and

Engineering Support Branch

Enclosures:

1.

Appendix A, Notice

of Violation

2.

IE Inspection Reports

No. 50-440/79-07 and

No. 50-441/79-07

cc w/encls:

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

Harold W. Kohn, Power

Siting Commission

Mr. Daniel D. Wilt,

Atto rney

.

-

6

-

.

0

4