Forwards IE Insp Rept 50-333/79-09 on 790625-29 & Notice of Violation
ML19210E190
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 09/20/1979
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Leonard J
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
Shared Package
ML19210E183 List:
References
NUDOCS 7911300675
Download: ML19210E190 (2)


See also: IR 05000333/1979009

Text

.

.

UNITED STATES

p,

o

NUCLEAR REGULATORY CoMMisslON

o

REGION l

$

$

631 PARK AVENUE

f

KING OF PRUSSI A. PENNSYLVANIA 19406

\\

/

SEP 2 01979

Docket No. 50-333

Power Authority of the State of New York

James A. FitzPatrick Nuclear Power Plant

ATTN: Mr. J. D. Leonard

Resident Manager

P. O. Box 41

Lycoming, New York 13093

Gentlemen:

Subject:

Inspection No. 79-09

This refe'4 to the inspection conducted by Mr. T. Stetka of this office on

June 25-29, 1979 of activities authorized by NRC License No. DPR-59 and to the

discussions ci our findings held by Mr. Stetka with Mr. R. Pasternack and other

members of your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter.

Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations by the

inspector.

Based on the results of this inspection, it appears that certain of your activ-

ities were not conducted in full compliance with NRC requirements, as set forth

in the Notice of Violation, enclosed herewith as Appendix A.

These items of

noncompliance have been categorized into the levels as described in our corre-

spondence to you dated December 31, 1974.

This notice is sent to you pursuant

to the provisions of Section 2.201 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations.

Section 2.201 requires you to submit to

this office, within twenty (20) days of your receipt of this notice, a written

statement or explanation in reply including:

(1) corrective steps which have

been taken by you and the results achieved; (2) corrective steps which will be

taken to avoid further items of noncompliance; and (3) the date when full com-

pliance will be achieved.

Item B, shown in the Notice of Violation enclosed with this letter, is a recur-

rent or uncorrected item.

In your response please give this matter your parti-

cular attention.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosures will

be placed in the NRC's Public Document Room.

If this report contains any in-

formation that you (or your contractor) believe to be proprietary, it is neces-

sary that you make a written application within 20 days to this office to withhold

}439

  • 1300 ,Q5

.

.

SEP 2 01979

Pow r Authority of the

2

State of New York

such information from public disclosure. Any such application must be accompanied

by an affidavit executed by the owner of the infonnation, which identifies the

document or part sought to be withheld, and which contains a statement of reasons

which addresses with specificity the items which will be considered by the

Commission as listed in subparagraph (b) (4) of Section 2.790.

The information

sought to be withheld shall be incorporated as far as possible into a separate

part of the affidavit.

If we do not hear from you in this regard within the

specified period, the report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be pleased to

discuss them with you.

Sincerely,

=_ m

-

c.1dofJ.Brunner, Chief

Read, tar Operations and Nuclear

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Office of Inspection and Enforcement

Inspection Report No. 50-333/79-09

cc w/ encl:

George T. Berry, Executive Director

P. W. Lyon, Manager - Nuclear Operations

A. Klausmann, Director, Quality Assurance

M. C. Cosgrove, Quality Assurance Supervisor

J. F. Davis, Chairman, Safety Review Ccmittee

V. J. Cassan, Assistant General Counsel

G. M. Wilverding, Licensing Supervisor