Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Rept 50-333/79-09
ML19210E182
Person / Time
Site: FitzPatrick 
Issue date: 10/30/1979
From: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Leonard J
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
Shared Package
ML19210E183 List:
References
NUDOCS 7911300667
Download: ML19210E182 (1)


See also: IR 05000333/1979009

Text

Q,

-

,;a m

+

'

UNITED STATES

E 7 ) .- cg( j'

NUCLEAR REGULATORY COMMISSION

?\\

iv/

E

REGION I

S,

'[

631 PARK AVENUE

% ' .\\ J

,&,

KING OF PRUSSI A, PENNSYLVANIA 19406

+ ...

OCT 3 c 1979

Docket No. 50-333

Power Authority of the State of New York

James A. FitzPatrick Nuclear Power Plant

ATTN:

Mr. J. D. Leonard

Resident Manager

P.O. Box 41

'

Lycoming, New York 13093

Gentlemen:

Subject:

Inspection No. 79-09

This refers to your letter dated October 10, 1979, in response to our letter

dated September 20, 1979.

Based on a telephone conversation between Mr. T. Stetka of this office, your-

self and Mr. R. Pasternack on October 18, 1979, it is our understanding that

the RES Technician inspections discussed in your response to Item B will be

implemented in accordance with a Radiological and Environment Services Depart-

ment Standing Order.

This Standing Order will specify the type and frequency

of these inspection patrols.

In addition, a Security and Safety Department

Standing Order will be issued that will direct the in plant security guard to

conducts checks of radiological control doors during each watch standing shi't.

This procedure will be implemented by November 30, 1979.

Thank you for informing us of the corrective and preventive actions documenced

in your letter.

These actions will be examined during a subsequent inspection

of your licensed program.

Your cooperation with us is appreciated.

Sincerely,

s

1

g

M *)6 4'

'

.

'

Boyce H. Grier

Director

cc:

George T. Berry, Executive Director

P. W. Lyon, Manager - Nuclear Operations

A. Klausmann, Director, Quality Assurance

M. C. Cosgrove, Quality Assurance Supervisor

J. F. Davis, Chairman, Safety Review Committee

V. J. Cassan, Assistant General Counscl

G. M. Wilverding, Licensing Supervisor

v439