ML19209C999

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-321/79-26 & 50-366/79-30 on 790704-0803.No Noncompliance Noted.Major Areas Inspected:Refueling Outage Tech Spec Compliance,Response to IE Bulletins & Circulars, Ros,Housekeeping,Operator Performance & QA Practices
ML19209C999
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 08/30/1979
From: Dance H, Rogers R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19209C997 List:
References
50-321-79-26, 50-366-79-30, NUDOCS 7910180567
Download: ML19209C999 (4)


See also: IR 05000321/1979026

Text

'

9 ate

uq%

9

UNITED STATES

!

i

NUCLEAR REGULATORY COMMISSION

5

.E

REGION il

'

101 MARIETTA ST., N.W., SulTE 3100

[

ATLANTA GEORGIA 3o303

<

.....

.

.

Report Nos. 50-321/79-26 and 50-366/79-30

Licensee: Georgia Power Company

270 Peachtree Street, N. W.

Atlanta, Georgia 30303

Facility Name: Hatch I and 2

Docket Nos. 50-321 and 50-366

',

License Nos. DPR-57 and NPF-5

Inspection at Hatch Site near Baxley, Georgia

Inspector:

(

O-c u h

f 1

?7

R/F.

ogerg

[

pate Signed

Approved by:

[N_

f 3c /7 5

H. C. Dance, Section Chief, RONS Branch

Dste S'igne'd

SUMMARY

Inspection on July 4-August 3, 1979

Areas Inspected

This inspection involved 110 inspector-hours onsite of the Unit I refueling

outage, Unit 2 startup testing, technical specification compliance, IE Bulletins

and Circulars, reportable occurrences, housekeeping, operator perforuiance,

overall plant operations, quality assurance practices, station and corporate

management practices, corrective and preventative maintenance activities, site

security procedures and radiation control activities.

Results

Of the thirteen areas inspected, no apparent items of noncompliance or devia-

tions were identified.

1177 ]85

~

'

79101806Q

.

.

DETAILS

,

.

.

.

1.

Persons contacted

Licensee Employees

  • H. Manry, Plant Manager
  • T. Moore, Assistant Plant Manager
  • T. Greene, Assistant Plant Manager

S. Baxley, Superintendent of Operations

R. Nix, Superintendent of Maintenance

C. Coggins, Superintendent of Engineering Services

' ,

'

W. Rogers, Health Physicist / Radiochemist

C. Bellflower, QA Site Supervisor

Other licensee employees contacted included technicians, operators, mechan-

ics, security force members, and office personnel.

  • Attended exit interview.

2.

Exit Interview

The inspection scope and findings were summarized on July 13, 20, 27 and

August 3, 1979 with those persons indicated in paragraph I above.

3.

Licensee Action on Previous Inspection Findings

Not inspected.

4.

Unresolved Items

Unresolved items were not identified during this inspection.

5.

Tours of the Plant (Units 1 and 2)

The inspector conducted plant tours periodically during the inspection

interval to verify that monitoring equipment was recording as required,

equipment was properly tagged, operations personnel were aware of plant

conditions and were alert, and plant housekeeping efforts were adequate.

Some tours were conducted on backshifts and on weekdends.

6.

Review of Nonroutine Events Reported by the Licensee (Units I and 2)

The following licensee event reports (LERs) were reviewed for potential

generic problems, to detect possible trends, and to determine whether

corrective actions appeared sppropriate. Events which were reported

immediately were also reviewed as they occurred to determine that technical

specifications were being met and that the public health and safety was of

utmost consideration.

'

il77

286

-

.

.

.

-2-

,

50-321/79-27

5/7/79

Valve Seat Leakage Excessive

50-321/79-28

5/17/79

Valve Seat Leakage Excessive

50-321/79-32

5/30/79

Cable Spreading Room Sprinkler

not Seismic

50-321/79-33

5/24/79

RHR Valve Leakage Excessive

50-321/79-36

5/30/79

Reactor Sample Valve Solenoid

not Environmentally Qualified

50-321/79-42

7/10/79

SBLC Inboard Isolation Valve

Leakage

50-321/79-43

7/3/79

Radwaste Sump Discharge Line not

Seismic

l: j

50-321/79-45

7/12/79

SBLC Relief Valve Lifted Low

50-321/79-47

7/27/79

RCIC Torus Suction Line not Seismic

50-321/79-48

7/30/79

MCC Breakers Undersized

50-366/79-36

5/30/79

Cable Spreading Room Sprinklers

not Seismic

50-366/79-56

7/10/79

Torus Level High

50-366/79-57

7/10/79

Loss of Service Water to Drywell

Cooling

50-366/79-61

7/13/79

RCIC Condensate Pump Trip

50-366/79-64

7/13/79

RCIC Inadvertent Isolation

50-366/79-65

7/18/79

RBM "A" Downscale Setpoint High

50-366/79-69

7/30/79

RCIC Inbosrd Isolation Valve Galled

50-366/79-70

8/1/79

Drywell Pressure Switch Set High

50-366/79-71

8/1/79

Drywell Airlock Handwheel Leak

50-366/79-22

8/1/79

Controller For RHRSW Pump

Inoperative

7.

liigh Pressure Coolant Injection and Reactor Core Isolation Cooling Malfunc-

tions and Test Programs (Units 1 and 2)

As a result of the simultaneous failures of the High Pressure Coolant

Injection system (HPCI) and the Reactor Core Isolation Cooling system

(RCIC) in June, the licensee completed an extensive test program on Unit 2.

This program was described in detail in IE report 50-321/79-24 and

50-366/79-28. The test program commenced on July 6, 1979 and was completed

on August 3, 1979. The test series consisted of approximately twenty five

automatic starts of HPCI and RCIC turbines under various plant operating

conditions. All starts were successful and four were observed by the

inspector.

Special instrumentation indicated that both systems sensed an

elevated steam flow D/P spike on system startup which approached the high

steam flow D/P isolation setpoint. The occurrence of this spike would

normally be expected under system initiation conditions. The licensee has

installed 3 second time delay relays in the isolation initiation logic

circuits for both HPCI and RCIC to further enhance system reliability. NRC

is evaluating this modification. Unit I will conduct a similar but abbre-

visted test program on HPCI and RCIC during post refueling testing to

assure that Unit I systems are operable and if circuitry modifications are

warranted.

-

1177 ]87

.

.

-3-

-

The Resident Inspector will continue to follow this item.

>

8.

Technical Specification Compliance (Units 1 and 2)

During this reporting interval, the inspector verified compliance with

selected limiting conditions for operation (LCO's) and results of selected

surveillance tests. These verifications were accomplished by direct observa-

tion of monitoring instrumentaiton, valve positions, switch positions, and

review of completed logs and records. The licensee's compliance with

selected LCO action statements were reviewed on selected occurrences as

they happened.

9.

Voltage Regulator Problems (Unit 2)

'i

On August 3, 1979, Unit 2 tripped from full power due to rapid change in

load on the transmission grid.

It appeared that the excitation portion of

the voltage regulation circuit for the generator field had failed to re-

spond properly to the grid disturbance. The licensee has initiated an

investigation with General Electric, the generator manufacturer, to deter-

mine the cause.

10.

Followup on IE Bulletins

For the following Bulletins, the inspector verified that the response was

timely, included the required information, contained adequate commitments,

and that corrective action as described in the written responses was complet-

ed.

IEB 78-10, Bergen-Patterson Hydraulic Shuck Suppressor Accumulator

a.

Springs

The inspector verified that this concern had been addressed by the

licensee for Unit I during the current outage. Affected snubbers have

been repaired. This item is closed.

b.

IEB 79-11, Faulty Overcurrent Trip Devices in ECCS Circuit Breakers

The inspector reviewed the licensee's response dated June 19, 1979

which indicated that these circuit breakers are not in use in either

unit at Hatch. This item is closed for both units.

11. Followup on IE Circulars

For the following circulars, the inspector verified that the circular was

received, reviewed, and corrective actions taken or planned if appropriate.

IEC 78-14, HPCI Turbine Reversing Chambcr Hold Down Bolting

IEC 78-19, Manual Overide of Safety Systems

1177 ]88

-

'