Forwards IE Bulletin 79-14,Suppl 1, Seismic Analysis for As-Built Safety-Related Piping Sys. Action Required
ML19207B513
Person / Time
Site: Pilgrim
Issue date: 08/15/1979
From: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Andognini G
BOSTON EDISON CO.
References
NUDOCS 7908300094
Download: ML19207B513 (1)


Text

Ib 4

(o, UNITED STATES E ' ) P ( [

,'d NUCLEAR REGULATORY COMMISSION REGION I O,','

/c [c 3

631 PARK AVENUE V

KING OF PRUS$1A, PENNSYLVANIA 19406

,o AllG 151m Docket No. 50-293 Boston Edison Company M/C Nuclear ATTN: Mr. G. Carl Andognini, Manager Nuclear Operationc Department 800 Boylston Street Boston, Massachusetts 02199 Gentlemen:

The enclosed supplement to Bulletin 79-14 is forwarded to you to provide added guidance on the intent of the Bulletin.

If you desire additional information regarding this matter, please contact this office.

Sincerely, k N'f j

oyce H. Grier Director

Enclosures:

1.

Supplement IE Bulletin 79-14 2.

Listing of IE Bulletins Issued in the Last 6 Months cc w/encls:

P. J. McGuire, Pilgrim Station Manager A. Z. Roisman, Natural Resources Defense Council 852 110 790830009% f

ENCLOSURE 1 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.

20555 Supplement IE Bulletin No. 79-14 Date:

August 15, 1979 P.ge 1 of 2 SEISMIC ANALYSIS FOR AS-BUILT SAFETY-RELATED PIPING SYSTEMS Discription of Circumstances:

IE Bulletin No. 79-14 was issued on July 2,1979 and revised on July 18, 1979.

The bulletin requested licensees to take certain actions to verify that seismic analyses are applicable to as-built plants.

This supplement to the bulletin provides additional guidance and definition of Action Items 2, 3, and 4.

To comply with the requests in IE Bulletin 79-14, it will be necessary for licensees to do the following:

2.

Inspect Part of the Accessible Piping For each system selected by the licensee in accordance with Item 2 of the Bulletin, the licensee is expected to verify by physical inspection, to the extent practicable, that the inspection elements meet the acceptance criteria.

In performing these inspectons, the licensee is expected to use measuring techniques of sufficient accuracy to demonstrate that acceptance criteria are met.

Where inspection elements important to the seismic analysis cannot be viewed because of thermal insulation or location of the piping, the licensee is expected to remove thermal insulation or provide access.

Where physical inspection is not practicable, e.g., for valve weights and materials of construction, the license is expected to verify conformance by inspection of quality assurance records.

If a nonconformance is found, the licensee is expected in accordance with Item 4 of the Bulletin to perform an evaluation of the significance of the nonconformance as rapidly as possible to determine whether or not the operability of the system might be jeopardized during a safe shutdown earthquake as defined in the Regulations.

This evaluation is expected to be done in two phases involving an initial engineering judgement (within

2. days), followed by an analytical engineering evaluation (within 30 days).

Where either phase of the evaluation shows that system operability is in jeopardy, the licensee is expected to meet the applicable technical specification action statement and complete the inspections required by Item 2 and 3 of the Bulletin as soon as possible.

The licensee must report the results of these ir in accordance with the require-

~

ments for content and schedule