|
---|
Category:Inspection Report
MONTHYEARIR 05000413/20230042024-02-0202 February 2024 Integrated Inspection Report 05000413-2023004 and 05000414-2023004 RA-23-0288, End of Cycle 27 (C1 R27) Steam Generator Tube Inspection Report2023-11-16016 November 2023 End of Cycle 27 (C1 R27) Steam Generator Tube Inspection Report IR 05000413/20230102023-10-11011 October 2023 NRC Inspection Report 05000413/2023010 and 05000414/2023010 IR 05000413/20230052023-08-25025 August 2023 Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2023005 and 05000414/2023005) IR 05000413/20230022023-07-25025 July 2023 Integrated Inspection Report 05000413/2023002 and 05000414/2023002 IR 05000413/20230012023-05-0505 May 2023 Integrated Inspection Report 05000413/2023001 and 05000414/2023001 IR 05000413/20230112023-04-25025 April 2023 Focused Engineering Inspection Report 05000413/2023011 and 05000414/2023011 IR 05000413/20220062023-03-0101 March 2023 Annual Assessment Letter for Catawba Nuclear Station, Units 1 and 2 (NRC Inspection Report 05000413/2022006 and 05000414/2022006) IR 05000413/20234012023-03-0101 March 2023 Security Baseline Inspection Report 05000413 2023401 and 05000414 2023401 IR 05000413/20233012023-02-17017 February 2023 Operator Licensing Examination Approval 05000413/2023301 and 05000414/2023301 IR 05000413/20220042023-01-31031 January 2023 Integrated Inspection Report 05000413/2022004 and 05000414/2022004 IR 05000413/20220112022-12-15015 December 2022 Biennial Problem Identification and Resolution Inspection Report 05000413/2022011 and 05000414/2022011 IR 05000413/20224032022-11-17017 November 2022 Cyber Security Inspection Report 05000413/2022403 and 05000414/2022403 (Public) IR 05000414/20220032022-10-31031 October 2022 Integrated Inspection Report 05000414/2022003 and 05000414/2022003 IR 05000413/20224022022-10-28028 October 2022 Security Baseline Inspection Report 05000413 2022402 and 05000414 2022402 IR 05000413/20220052022-08-26026 August 2022 Updated Inspection Plan for Catawba Nuclear Station, Units 1 and 2 - NRC Inspection Report 05000413/2022005 and 05000414/2022005 IR 05000413/20220022022-07-29029 July 2022 Integrated Inspection Report 05000413/2022002 and 05000414/2022002 IR 07200045/20220012022-07-26026 July 2022 Operation of an Independent Spent Fuel Storage Installation Report 07200045/2022001 IR 05000413/20220102022-07-21021 July 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000413/2022010 and 05000414/2022010 IR 05000414/20220012022-04-28028 April 2022 Integrated Inspection Report 05000413/ 2022001 and 05000414/2022001 IR 05000413/20224202022-04-0707 April 2022 Security Inspection Report 05000413/2022420 and 05000414/2022420 RA-22-0080, Independent Spent Fuel Storage Installation, McGuire, Units 1 & 2, Independent Spent Fuel Storage Installation, Request for an Exemption to the Requirements of Certificate of Compliance No. 1031 for the NAC Magnastor Storage System2022-04-0707 April 2022 Independent Spent Fuel Storage Installation, McGuire, Units 1 & 2, Independent Spent Fuel Storage Installation, Request for an Exemption to the Requirements of Certificate of Compliance No. 1031 for the NAC Magnastor Storage System IR 05000413/20210062022-03-0202 March 2022 Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2021006 and 05000414/2021006) IR 05000413/20224012022-02-18018 February 2022 Security Baseline Inspection Report 05000413/2022401 and 05000414/2022401 IR 05000413/20210042022-01-26026 January 2022 Integrated Inspection Report 05000413/2021004 and 05000414/2021004 ML22011A1802022-01-18018 January 2022 Review of the Spring 2021 Steam Generator Tube Inspection Report IR 05000413/20213012021-11-0808 November 2021 Operator Licensing Examination Report 05000413/2021301 and 05000414/2021301 IR 05000413/20214022021-11-0303 November 2021 Security Baseline Inspection Report 05000413/2021402 and 05000414/2021402 IR 05000413/20210032021-10-28028 October 2021 Integrated Inspection Report 05000413/2021003 and 05000414/2021003 IR 05000413/20210102021-09-27027 September 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000413/2021010 and 05000414/2021010 IR 05000413/20214042021-08-26026 August 2021 Material Control and Accounting Program Inspection Report 05000413/2021404 and 05000414/2021404 (OUO Removed) IR 05000413/20210022021-08-0505 August 2021 Integrated Inspection Report 05000413/2021002 and 05000414/2021002 IR 05000413/20210012021-04-29029 April 2021 Integrated Inspection Report 05000413/2021001 and 05000414/2021001 IR 05000413/20210112021-04-23023 April 2021 NRC Fire Protection Team Inspection Report 05000413/2021011 and 05000414/2021011 IR 05000413/20200062021-03-0303 March 2021 Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 - NRC Inspection Report 05000413/2020006 and 05000414/2020006 IR 05000413/20214012021-02-26026 February 2021 Security Baseline Inspection Report 05000413/2021401 and 05000414/2021401 IR 05000413/20200042021-01-28028 January 2021 Integrated Inspection Report 05000413/2020004 and 05000414/2020004 IR 05000413/20200112020-12-18018 December 2020 Biennial Problem Identification and Resolution Inspection Report 05000413/2020011 and 05000414/2020011 Dated December 18, 2020 IR 05000413/20204012020-11-23023 November 2020 Security Aseline Inspection Report 05000413/2020401 and 05000414/2020401 IR 05000413/20200032020-10-30030 October 2020 Integrated Inspection Report 05000413/2020003, 05000414/2020003 and 07200045/2020002 IR 05000413/20200052020-08-17017 August 2020 Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (NRC Inspection Report 05000413/2020005 and 05000414/2020005) IR 05000413/20200022020-08-0303 August 2020 Integrated Inspection Report 05000413/2020002, 05000414/2020002 and 07200045/2020001 IR 05000413/20200012020-04-28028 April 2020 Integrated Inspection Report 05000413/2020001 and 05000414/2020001 IR 05000413/20200102020-03-10010 March 2020 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000413/2020010 and 05000414/2020010 IR 05000413/20190062020-03-0303 March 2020 Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 - NRC Inspection Report 05000413/2019006 and 05000414/2019006 IR 05000413/20190042020-01-27027 January 2020 Integrated Report 05000413/2019004 and 05000414/2019004 IR 05000413/20190102020-01-0909 January 2020 Reissue Catawba - Design Basis Assurance Inspection (Programs) Inspection Report 05000413/2019010 and 05000414/2019010 ML19354A8562019-12-20020 December 2019 Design Basis Assurance Inspection (Programs) Inspection Report 0500413/2019010 and 05000414/2019010 IR 05000413/20194112019-11-26026 November 2019 U.S. Nuclear Regulatory Commission Security Inspection Report 05000413/2019411 and 05000414/2019411 IR 05000413/20190032019-11-0707 November 2019 Integrated Inspection Report 05000413/2019003 and 05000414/2019003 2024-02-02
[Table view] Category:Letter
MONTHYEARIR 05000413/20230042024-02-0202 February 2024 Integrated Inspection Report 05000413-2023004 and 05000414-2023004 ML24005A2512024-01-26026 January 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230102023-10-11011 October 2023 NRC Inspection Report 05000413/2023010 and 05000414/2023010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230052023-08-25025 August 2023 Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2023005 and 05000414/2023005) ML23233A1692023-08-17017 August 2023 EN 56683 - Curtiss Wright, Interim Notification Report for PotentialPurt2l IR 05000413/20230022023-07-25025 July 2023 Integrated Inspection Report 05000413/2023002 and 05000414/2023002 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined IR 05000413/20230012023-05-0505 May 2023 Integrated Inspection Report 05000413/2023001 and 05000414/2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000413/20230112023-04-25025 April 2023 Focused Engineering Inspection Report 05000413/2023011 and 05000414/2023011 ML23107A2542023-04-14014 April 2023 301 Examination Report Letter and Report (Merged) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000413/20220062023-03-0101 March 2023 Annual Assessment Letter for Catawba Nuclear Station, Units 1 and 2 (NRC Inspection Report 05000413/2022006 and 05000414/2022006) IR 05000413/20234012023-03-0101 March 2023 Security Baseline Inspection Report 05000413 2023401 and 05000414 2023401 IR 05000413/20233012023-02-17017 February 2023 Operator Licensing Examination Approval 05000413/2023301 and 05000414/2023301 IR 05000413/20220042023-01-31031 January 2023 Integrated Inspection Report 05000413/2022004 and 05000414/2022004 IR 05000413/20220112022-12-15015 December 2022 Biennial Problem Identification and Resolution Inspection Report 05000413/2022011 and 05000414/2022011 ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations IR 05000413/20224032022-11-17017 November 2022 Cyber Security Inspection Report 05000413/2022403 and 05000414/2022403 (Public) ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 ML22319A0942022-11-10010 November 2022 EN 56219 - Flowserve. 10 CFR Part 21 Report 38878-8 Solenoid Valve at Duke, Catawba Flowserve Evaluation 105 IR 05000414/20220032022-10-31031 October 2022 Integrated Inspection Report 05000414/2022003 and 05000414/2022003 IR 05000413/20224022022-10-28028 October 2022 Security Baseline Inspection Report 05000413 2022402 and 05000414 2022402 ML22297A2642022-10-25025 October 2022 Project Manager Assignment ML22276A2492022-10-25025 October 2022 Completion of License Renewal Commitment No. 10, Aging Management of Environmentally Assisted Fatigue ML22303A0052022-10-24024 October 2022 EN 56178 - Tioga Final. LTR-TP-22-29 2021 10CFR Part 21 Improper Notification of NRC ML22258A0302022-09-15015 September 2022 Evacuation Time Estimate Reports ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition ML22231B1362022-09-0101 September 2022 Review of the Draft Environmental Assessment and Findings of No Significant Impact for Catawba Nuclear Station, H.B. Robinson Steam Electric Plant, and Oconee Nuclear Station Independent Spent Fuel Storage Installation Decommissioning Fundi ML22303A0042022-08-31031 August 2022 Final Report Notification Pursuant to 10 CFR Part 21.21, Regarding Supply of 6 NPS Sch. 40 Seamless Stainless-Steel Pipe; Manufacturer: Maxim Tubes Company Pvt. Ltd.; Heat No: N200309AW01, SR No: 7; 9 Pcs; 180 Feet Total Procured as Unquali IR 05000413/20220052022-08-26026 August 2022 Updated Inspection Plan for Catawba Nuclear Station, Units 1 and 2 - NRC Inspection Report 05000413/2022005 and 05000414/2022005 ML22217A0792022-08-0303 August 2022 301, Corporate Notification Letter (210-day Ltr) IR 05000413/20220022022-07-29029 July 2022 Integrated Inspection Report 05000413/2022002 and 05000414/2022002 IR 07200045/20220012022-07-26026 July 2022 Operation of an Independent Spent Fuel Storage Installation Report 07200045/2022001 ML22215A2502022-07-25025 July 2022 EN 55960 - Update - Curtiss Wright IR 05000413/20220102022-07-21021 July 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000413/2022010 and 05000414/2022010 ML22195A2432022-07-19019 July 2022 Request for Withholding Information from Public Disclosure Regarding Reactor Vessel Closure Head Repair Alternative ML22164A0362022-07-19019 July 2022 Mcguire Nuclear Station, Units 1 and 2; Issuance of Amendments to Revise the Conditional Exemption of the End-Of-Cycle Moderator Temperature Coefficient Measurement Methodology (EPID L-2021-LLA-0198) Public ML22199A2552022-07-0606 July 2022 Ds Catawba 2022 RQ Inspection Notification Letter ML22222A0092022-07-0101 July 2022 EN 55974 - Flowserve, Part 21 Report Re Solenoid Coil Failure of Model 38878-8 Solenoid Valve at Catawba Nuclear Station for Use on FWIV Actuator ML22175A0342022-06-28028 June 2022 Information Request for the Cyber-Security Baseline Inspection Notification to Perform Inspection 05000413/2022403 and 05000414/2022403 ML22046A0222022-06-14014 June 2022 Issuance of Amendments to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML22111A3572022-05-16016 May 2022 Letter Issuing Exemption to Catawba IR 05000414/20220012022-04-28028 April 2022 Integrated Inspection Report 05000413/ 2022001 and 05000414/2022001 2024-02-02
[Table view] |
Inspection Report - Catawba - 2019011 |
---|
|
|
Text
uly 24, 2019
SUBJECT:
CATAWBA NUCLEAR STATION - TEMPORARY INSTRUCTION 2515/194 OPEN PHASE CONDITION REPORT 05000413/2019011 AND 05000414/2019011
Dear Mr. Simril:
On June 12, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Catawba Nuclear Station Units 1 and 2 and discussed the results of this inspection with Mr.
Clark Curry and other members of your staff. The results of this inspection are documented in the enclosed report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Christopher J. Even, Chief (Acting)
Construction Inspection Branch 2 Division of Construction Oversight Docket Nos.: 05000413 and 05000414 License Nos.: NPF-35 and NPF-52
Enclosure:
As stated
Inspection Report
Docket Numbers: 05000413 and 05000414 License Numbers: NPF-35 and NPF-52 Report Numbers: 05000413/2019011 and 05000414/2019011 Enterprise Identifier: I-2019-011-0039 Licensee: Duke Energy Carolinas, LLC Facility: Catawba Nuclear Station Location: York, SC 29745 Inspection Dates: June 10, 2019 to June 12, 2019 Inspectors: J. Kent, Construction Inspector Approved By: Christopher J. Even, Chief (Acting)
Construction Inspection Branch 2 Division of Construction Oversight Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Temporary Instruction 2515/194 Open Phase Condition inspection at Catawba Nuclear Station in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations No findings or violations of more than minor significance were identified.
INSPECTION SCOPE
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
OTHER ACTIVITIES
- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL 2515/194 - Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)
This inspection was conducted using Temporary Instruction (TI) 2515/194 (ADAMS Accession No. ML17137A416), dated October 31, 2017. The inspectors reviewed the licensees implementation of Nuclear Energy Institute voluntary industry initiative (VII) in compliance with Commission guidance. The inspectors discussed the licensees open phase condition (OPC)system design and ongoing implementation plans with plant staff. The inspectors reviewed licensee documentation, vendor documentation, and performed system walkdowns to determine if the installed equipment was supported by the design documentation. These reviews were also made to determine if the licensee had completed the installation and testing of equipment, installed and tested alarming circuits both locally and in the control room, and analyzed potential impacts associated with the design implementation on the current licensing basis.
The objective of TI 2515/194 was to verify that licensees had appropriately implemented the NEI VII (ADAMS Accession No. ML15075A454), dated March 16, 2015, including updating their licensing basis to reflect the need to protect against OPCs.
Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01) (1 Sample)
Temporary Instruction 2515/194-03.01 - VII (Part 1)
Catawba Nuclear Station selected the open phase detection system designed and manufactured by Power System Sentinel Technologies, LLC. At the end of this inspection the system remained in the monitoring mode of operation to facilitate continued data gathering of the system for evaluation of alarm and trip setpoints. The equipment was installed on the main step-up transformers (MSU) 1A, 1B, 2A, and 2B. Catawba Nuclear Station currently has no set scheduled date to transition the open phase detection system to full implementation (tripping functions enabled).
INSPECTION RESULTS
Assessment 2515/194 Detection, Alarms, and General Criteria - TI 2515/194-03.01 - VII (Part 1)
Based on discussions with the licensee staff, review of available design, testing, grid data trending results documentation, and walkdowns of installed equipment, the inspectors had reasonable assurance the licensee appropriately implemented the VII.
The inspectors determined that:
- (1) OPCs will be detected and alarmed in the control room on the common annunciator panel.
- (2) Detection circuits will be sensitive enough to identify an OPC for all credited loading conditions for installed equipment.
- (3) No Class-1E circuits were being replaced with non-Class 1E circuits in the design.
- (4) The Updated Final Safety Analysis Report (UFSAR) has been updated to discuss the design features and analyses related to the effects of, and protection for, any OPC design vulnerability.
Assessment 2515/194 Protective Actions Criteria - TI 2515/194-03.01 - VII (Part 1)
- (1) Four transformers were susceptible to an OPC as identified in this VII when the main generator was offline. The licensee installed detection and mitigating equipment for these affected transformers.
- (2) With an OPC present and with or without an accident condition signal, the open phase design would not adversely affect the function of important-to-safety systems, structures, or components. The licensees OPC design solution added Power System Sentinel Technologies, LLC systems on the main step-up transformers MSU 1A, 1B, 2A, and 2B. The tripping function, when enabled, will provide an additional input to the associated transformer lockout relays. The credited plant response is not negatively affected and will be the same regardless of the conditions that generated the lockout of the transformer.
Assessment 2515/194 Detection, Alarms, and General Criteria Exceptions - TI 2515/194-03.01 - VII (Part 1)
The inspectors identified the following minor exceptions to the Temporary Instruction criteria resulting from the operating status of the design modifications.
- (1) The licensees design was operating in the monitoring mode with already established setpoints and gathering data to verify the OPC design and protective schemes would minimize mis-operation, or spurious actions in the range of voltage unbalance normally experienced in the transmission system. The licensee developed engineering calculations to demonstrate coordination of the OPC detection and tripping setpoints for the actuation circuit that does not result in lower overall plant operation reliability. This calculation was presented in CNC-1381.06-00-0080, Rev. 0 and CNC-1381.06-00-0081, Rev. 0, for Units 1 and 2, respectively.
- (2) A draft of the UFSAR was available for the inspectors review that included information related to OPCs. The licensee provided the inspectors with proposed changes to the licensing basis that discussed the system requirements related to the effects of, and protection for, any OPC design vulnerability. The inspectors verified the proposed change process was being tracked under initiating document EC 0000401499, OPEN PHASE DETECTION U1, Rev. 000 & EC 0000402827, OPEN PHASE DETECTION U2, Rev. 000.
The inspectors also determined that the Technical Specification Bases was not affected by this VII as evaluated under AR 02170349 and AR 02114867 for Units 1 and 2, respectively.
Assessment 2515/194 Protective Actions Criteria Exceptions - TI 2515/194-03.01 - VII (Part 1)
The inspectors identified the following minor exceptions to the Temporary Instruction criteria resulting from the operating status of the design modifications.
The licensees OPC design solution uses Power System Sentinel Technologies, LLC to detect, alarm, and provide an input to the associated MSU zone lockout relays. Upon an initiation of the zone lockout relays, the zone that is affected by a power loss is tripped and isolated.
The tripping function input to the transformer lockout relays remained deactivated during the onsite system implementation inspection and was not able to be demonstrated to perform the designed function. This action was being tracked in the design change package EC 0000401499 & EC 0000402827. Once enabled, the Open Phase Protection system will have the ability to isolate an affected MSU with an OPC detected on the high voltage side of the MSUs when either the Generator Power Circuit Breakers (GPCB) or at least one of the two no-load motor operated disconnects for physical break isolation of the GPCB are opened.
Due to the configuration of Catawba Nuclear Station electrical distribution system, a loss of phase on one transformer would only affect one train of equipment, and loads required to mitigate postulated accidents would be available on the non-affected train, ensuring that safety functions are preserved as required by the current licensing bases.
Periodic tests, calibrations, setpoint verifications or inspections (as applicable) have been established for any new protective features. The surveillance requirements have been maintained for the plant Technical Specifications in compliance with the provisions of 10 CFR 50.36. Existing plant equipment will continue to be maintained according to the licensees current preventative maintenance program.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
2515/194 Calculations CNC-1381.06-00-0032 023
CNC-1381.06-00-0080 000
CNC-1381.06-00-0081 000
Drawings CN-1700-02.01 VTO ONE LINE DIAGRAM 22 KV RELAYS & 009B
METERS TRANSFORMERS N
- O. 1A, 1T1A, 1T2A &
1ATE
CN-1700-03.01 VTO ONE LINE DIAGRAM 22 KV RELAYS & 010A
METERS TRANSFORMERS N
- O. 1B, 1T1B & 1T2B
CN-1701-04 LOGIC DIAGRAM UNIT MAIN PWR SYS 007
PROTECTIVE RELAYING ZONE 1B PRIMARY &
BACKUP
CN-2700-02.01 VTO ONE LINE DIAGRAM 22KV RELAYS & 008A
METERS TRANSFORMER N
- O. 2A, 2T1A 2T2A &
2ATE
CNEE-0186-01.01 ELEMENTARY DIAGRAM UNIT MAIN POWER 008B
SYS RELAYING NEUTRAL OVERCURRENT
RELAYS ZONE 1A
CNEE-0198-01 ELEMENTARY DIAGRAM TRANSFORMER 1A 005A
MONITORING
CNM 1330.05-0101 PSSTech Open Phase Protection (OPP) System- 000
MSU 1A Ch 1 Electrical Drawings
CNM 1330.05-0103 PSSTech Open Phase Protection (OPP) System- 000
MSU 1A Elementary Drawings
CNM 1330.05-0110 PSSTech Open Phase Protection (OPP) System- 000
MSU 1B Ch 1 Electrical Drawings
SK-EC410663-1000 Sheet Open Phase Protection System Main Step Up A
Transformer 1A Conduit Route Plan
SK-EC410663-3000 Sheet Open Phase Protection System Main Step Up A
Transformer 1A Power & Control Block Diagram
Engineering 0000401499 OPEN PHASE DETECTION U1 00
Changes 0000402827 OPEN PHASE DETECTION U2 00
Engineering AR 02114867 Open Phase Detection U2 00
Inspection Type Designation Description or Title Revision or
Procedure Date
Evaluations AR 02170349 Open Phase Detection U1 00
Miscellaneous IEGR-MN-2007 Open Phase Protection (OPP) System Preventative 11/12/2018
Maintenance Guide
PSSTech/OPPsys/Analysis- Open Phase Protection (OPP) System: Analysis of 2015
-2015/0225-200 Open Phase Protection (OPP) System Impact on
Existing Power System
UFSAR Chapter 8 20
UFSAR Changes UFSAR Change for EC 402827 00
Procedures OP/0/A/6350/010 Operation of Station Breakers and Disconnects 101
OP/1/A/6350/001 Normal Power Checklist 085
OP/1/B/6100/010 L Annunciator Response for Panel 1AD-11 063
OP/1/B/6300/001 Turbine Generator 109
OP/2/A/6350/001 Normal Power Checklist 083
OP/2/B/6100/010 L Annunciator Response for Panel 2AD-11 062
OP/2/B/6300/001 Turbine Generator 092
7