MONTHYEARML18047A7252018-02-16016 February 2018 Holtec International - Safety Analysis Report Project stage: Other ML18047A7242018-02-16016 February 2018 Holtec International - Certificate of Compliance for Radioactive Material Packages Project stage: Other ML18047A7232018-02-16016 February 2018 Application Request for a Certificate of Compliance (CoC) for Holtec'S Model No. HI-STAR 100MB Type B(U)F-96 Transportation Package Project stage: Request ML18134A2062018-05-11011 May 2018 Letter to R. Ngwayah Request for Supplemental Information for the Review of the Model No. HI-STAR 100MB Package Project stage: Approval ML18134A2042018-05-11011 May 2018 Package: Request for Supplemental Information for the Review of the Model No. HI-STAR 100MB Package Project stage: Request ML18134A2052018-05-11011 May 2018 Enclosurequest for Supplemental Information (Letter to R. Ngwayah Request for Supplemental Information for the Review of the Model No. HI-STAR 100MB Package) Project stage: Approval ML18192B7612018-07-11011 July 2018 Holtec International - Responses to Rsi 3-2 and Observation 6-1 Project stage: Other ML18192B7582018-07-11011 July 2018 Holtec International - HI-STAR 1OOMB Resubmittal of Responses to NRC Rsi 3-2 and Observation 6-1 Project stage: Other ML19035A1162019-02-0404 February 2019 Letter to R. Ngwayah Request for Additional Information for the Review of the Model No. HI-STAR 100MB Package (W/Enclosure) Project stage: RAI ML19179A0212019-06-28028 June 2019 Letter to B. Seawright Application for the Review of the Model No. HI-STAR 100MB Package - Updated CoC Issuance Schedule Project stage: Approval ML19221B6572019-08-0909 August 2019 Enclosure 2: Safety Evaluation Report (Letter to B. Seawright Certificate of Compliance No. 9378, Revision No. 0, for the Model No. HI-STAR 100MB Package) Project stage: Approval ML19221B6542019-08-0909 August 2019 Package: Certificate of Compliance No. 9378, Revision No. 0, for the Model No. HI-STAR 100MB Package Project stage: Request ML19221B6562019-08-0909 August 2019 Letter to B. Seawright Certificate of Compliance No. 9378, Revision No. 0, for the Model No. HI-STAR 100MB Package Project stage: Other ML19221B6552019-08-0909 August 2019 Enclosure 1: Certificate of Compliance No. 9378, Rev. No. 0 (Letter to B. Seawright Certificate of Compliance No. 9378, Revision No. 0, for the Model No. HI-STAR 100MB Package) Project stage: Other 2018-07-11
[Table View] |
|
---|
Category:Letter
MONTHYEARML24263A0612024-09-19019 September 2024 International, Upcoming Amendment for 10 CFR 71 Certificate of Compliance No. 9378 ML24199A1722024-08-0202 August 2024 Letter and Safety Evaluation Report for Revision No. 2 of the Certificate of Compliance No. 9378 ML24162A0872024-06-10010 June 2024 International, Request for Renewal of 10 CFR 71 Certificate of Compliance No. 9378 ML21133A2702021-05-27027 May 2021 Cover Letter - Certificate of Compliance No. 9378, Revision No. 1, for the Model No. Hi-Star 100mb Package ML21120A1322021-04-30030 April 2021 International Submittal of the Second RAI Reponses for the Review of the Model No. HI-STAR 100MB Package License Amendment Request ML21014A5032021-01-14014 January 2021 International, Submittal Date for Responses to Nrc'S Second Request for Additional Information (RAI) for HI-STAR 100MB Transport Package License Amendment Request 9378-1 ML20258A0542020-09-11011 September 2020 International - Submittal of RAI Reponses for the Review of the Model No. HI-STAR 100MB Package License Amendment Request ML20205L5472020-07-23023 July 2020 Revised Submittal Date for Responses to Nrc'S Request for Additional Information (RAI) for HI-STAR 100MB Transport Package License Amendment Request 9378-1 ML20136A4442020-05-14014 May 2020 Submittal Date for Responses to Nrc'S Request for Additional Information (RAI) for HI-STAR 100MB Transport Package License Amendment Request 9378-1 ML20097E1902020-04-14014 April 2020 Request for Additional Information for the Review of the Model No. HI-STAR 100MB Package ML19221B6562019-08-0909 August 2019 Letter to B. Seawright Certificate of Compliance No. 9378, Revision No. 0, for the Model No. HI-STAR 100MB Package ML19179A0212019-06-28028 June 2019 Letter to B. Seawright Application for the Review of the Model No. HI-STAR 100MB Package - Updated CoC Issuance Schedule ML19035A1162019-02-0404 February 2019 Letter to R. Ngwayah Request for Additional Information for the Review of the Model No. HI-STAR 100MB Package (W/Enclosure) ML18192B7582018-07-11011 July 2018 Holtec International - HI-STAR 1OOMB Resubmittal of Responses to NRC Rsi 3-2 and Observation 6-1 ML18134A2062018-05-11011 May 2018 Letter to R. Ngwayah Request for Supplemental Information for the Review of the Model No. HI-STAR 100MB Package ML18047A7232018-02-16016 February 2018 Application Request for a Certificate of Compliance (CoC) for Holtec'S Model No. HI-STAR 100MB Type B(U)F-96 Transportation Package 2024-09-19
[Table view] |
Text
T. Tate UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 28, 2019 Mr. Brian Seawright Holtec International 1 Holtec Blvd Camden, NJ 08104
SUBJECT:
APPLICATION FOR THE REVIEW OF THE MODEL NO. HI-STAR 100MB PACKAGE - UPDATED COC ISSUANCE SCHEDULE
Dear Mr. Seawright:
By letter dated February 16, 2018 (Agencywide Document Access and Management System Accession No. ML18047A723), you submitted an application for the Certificate of Compliance No. 9378 for the Model No. HI-STAR 100 MB. Your application was accepted for review on June 1, 2018, when staff received your responses to our request for supplemental information dated May 11, 2018. You responded successively on February 13 and March 14, 2019, to our request for additional information letter dated February 4, 2019.
On May 29, 2019, you submitted Revision No. 2 of your application (ML19151A490) and the staff was anticipating a CoC issuance in June 2019. However, unforeseen scheduling conflicts and resource limitations force us to delay the issuance of your certificate until August 2019.
Please reference Docket No. 71-9378 and EPID No. L-2018-NEW-0000 in future correspondence related to this licensing action. If you have any questions regarding this matter, please contact me at 301-415-7505.
Sincerely,
/RA John McKirgan Acting for/
Pierre Saverot, Project Manager Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 71-9378 EPID: L-2018-NEW-0000
ML19179A021 OFFICE: NMSS/DSFM NMSS/DSFM NMSS/DSFM NAME: PSaverot MSeyoum-Seifu JMcKirgan for SFigueroa DATE: 06/10/2019 6/28/2019 6/28/2019