ML19065A323
| ML19065A323 | |
| Person / Time | |
|---|---|
| Site: | Dresden, Peach Bottom, Limerick, Clinton, Quad Cities, FitzPatrick, LaSalle |
| Issue date: | 03/06/2019 |
| From: | Blake Purnell Plant Licensing Branch III |
| To: | Tom Loomis Exelon Generation Co |
| References | |
| JAFP-19-0025, L-2019-LLR-0012, RS-19-032 | |
| Download: ML19065A323 (3) | |
Text
1 NRR-DMPSPEm Resource From:
Purnell, Blake Sent:
Wednesday, March 6, 2019 4:09 PM To:
Loomis, Thomas R:(GenCo-Nuc) (thomas.loomis@exeloncorp.com)
Cc:
Barstow, James:(GenCo-Nuc); Wrona, David
Subject:
Exelon Fleet - Alternative Request to Use Updated BWRVIP Guidelines (EPID L-2019-LLR-0012)
Mr. Loomis:
By application dated February 19, 2019 (ADAMS Accession No. ML19050A363), Exelon Generation Company, LLC (the licensee) submitted a request in accordance with Paragraph 50.55a(z)(1) of Title 10 of the Code of Federal Regulations (10 CFR) for a proposed alternative to the requirements of 10 CFR 50.55a and the American Society of Mechanical Engineers Code at Clinton Power Station, Unit No. 1; Dresden Nuclear Power Station, Units 2 and 3; James A. FitzPatrick Nuclear Power Plant; LaSalle County Station, Units 1 and 2; Limerick Generating Station, Units 1 and 2; Peach Bottom Atomic Power Station, Units 2 and 3; and Quad Cities Nuclear Power Station, Units 1 and 2. The proposed alternative would allow the licensee to use more recent versions of certain Boiling Water Reactor Vessel and Internals Project guidelines for each of these facilities.
The purpose of this email is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this proposed alternative. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it provides technical information in sufficient detail to enable the staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed alternative in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review, as compared to the detailed technical review, there may be instances in which issues that impact the staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the staffs detailed technical review by separate correspondence.
Based on the information provided in your submittal, the NRC staff estimates that review of this request will take approximately 75 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br /> to complete. The staff expects to complete its review by March 31, 2020. These estimates are based on the staffs initial review of the application and they could change due to several factors, including requests for additional information. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes to the forecasted hours, I will inform you of the reason for the change and provide the new estimates.
Sincerely, Blake Purnell, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission
2 Docket Nos. 50-461, 50-237, 50-249, 50-333 50-373, 50-374, 50-352, 50-353, 50-277, 50-278, 50-254, and 50-265
Hearing Identifier:
NRR_DMPS Email Number:
848 Mail Envelope Properties (DM6PR09MB305039922D526A91460EAFC4E6730)
Subject:
Exelon Fleet - Alternative Request to Use Updated BWRVIP Guidelines (EPID L-2019-LLR-0012)
Sent Date:
3/6/2019 4:08:37 PM Received Date:
3/6/2019 4:08:37 PM From:
Purnell, Blake Created By:
Blake.Purnell@nrc.gov Recipients:
"Barstow, James:(GenCo-Nuc)" <James.Barstow@exeloncorp.com>
Tracking Status: None "Wrona, David" <David.Wrona@nrc.gov>
Tracking Status: None "Loomis, Thomas R:(GenCo-Nuc) (thomas.loomis@exeloncorp.com)" <thomas.loomis@exeloncorp.com>
Tracking Status: None Post Office:
DM6PR09MB3050.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3176 3/6/2019 4:08:37 PM Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received: