ML19029B333
ML19029B333 | |
Person / Time | |
---|---|
Site: | Oyster Creek |
Issue date: | 01/29/2019 |
From: | Raymond Mckinley Plant Support Branch 1 |
To: | Dostal J Exelon Generation Co |
McKinley R | |
References | |
Download: ML19029B333 (3) | |
Similar Documents at Oyster Creek | |
---|---|
Category:Letter
MONTHYEARML23342A1162024-01-0909 January 2024
[Table view]Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 IR 05000219/20230022023-11-0909 November 2023 EA-23-076 Oyster Creek Nuclear Generating Station - Notice of Violation and Proposed Imposition of Civil Penalty - $43,750 - NRC Inspection Report No. 05000219/2023002 ML23286A1552023-10-13013 October 2023 Defueled Safety Analysis Report (DSAR) ML23249A1212023-09-0606 September 2023 NRC Inspection Report 05000219/2023002, Apparent Violation (EA-23-076) ML23242A1162023-08-30030 August 2023 Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Report January 1, 2021 Through December 31, 2022 ML23214A2472023-08-22022 August 2023 NRC Inspection Report 05000219/2023002 IR 05000219/20230012023-05-31031 May 2023 NRC Inspection Report No. 05000219/2023001 IR 07200015/20234012023-05-16016 May 2023 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2023401 ML23114A0912023-04-24024 April 2023 Annual Radioactive Effluent Release Report for 2022 ML23114A0872023-04-24024 April 2023 Annual Radioactive Environmental Operating Report for 2022 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000219/20220022023-02-0909 February 2023 NRC Inspection Report No. 05000219/2022002 ML23031A3012023-02-0808 February 2023 Discontinuation of Radiological Effluent Monitoring Location in the Sewerage System ML23033A5052023-02-0202 February 2023 First Use Notification of NRC Approved Cask RT-100 ML23025A0112023-01-24024 January 2023 LLRW Late Shipment Investigation Report Per 10 CFR 20, Appendix G ML22347A2732022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 ML22297A1432022-12-15015 December 2022 Part 20 App G Exemption Letter L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 IR 07200015/20224012022-12-0606 December 2022 NRC Independent Spent Fuel Storage Installation Security Inspection Report 07200015/2022401 (Letter & Enclosure 1) ML22280A0762022-11-0202 November 2022 Us NRC Analysis of Holtec Decommissioning Internationals Funding Status Report for Oyster Creek, Indian Point and Pilgrim Nuclear Power Station ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22286A1402022-10-13013 October 2022 NRC Confirmatory Order EA-21-041 IR 05000219/20220012022-08-11011 August 2022 NRC Inspection Report 05000219/2022001 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22214A1732022-08-0202 August 2022 Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E ML22207B8382022-07-26026 July 2022 NRC Confirmatory Order EA-21-041 ML22130A6882022-05-10010 May 2022 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G L-22-026, Occupational Radiation Exposure Data Report - 20212022-04-29029 April 2022 Occupational Radiation Exposure Data Report - 2021 ML22118A6122022-04-28028 April 2022 Annual Radioactive Environmental Operating Report for 2021 ML22118A5822022-04-28028 April 2022 Annual Radioactive Effluent Release Report for 2021 ML22091A1062022-04-0101 April 2022 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) L-22-022, and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations - Holtec.2022-03-25025 March 2022 and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations - Holtec. ML22069A3762022-03-10010 March 2022 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML22032A0582022-03-0808 March 2022 EA-21-139; EA-150: Oyster Creek Nuclear Generating Station - NRC Investigation Report Nos.. 1-2021-002 & 1-2021-014 ML22060A2202022-03-0202 March 2022 NRC Office of Investigations Case No. 1-2021-009 ML22049B2452022-02-19019 February 2022 Late Low Level Radwaste Shipment Report Pursuant to 10 CFR 20 Appendix G IR 05000219/20214022022-01-26026 January 2022 EA-21-041: Confirmatory Order Related to Oyster Greek Nuclear Generating Station - NRC Investigation Report I-2020-007; NRC Inspection Report Nos. 05000219/2021402 & 07200015/2021401 ML22025A3422022-01-25025 January 2022 and Big Rock Point - Changes to Site Organization ML22025A2182022-01-25025 January 2022 Late LLRW Shipments Investigation Report Pursuant to 10 CFR 20, Appendix G ML22021B5512022-01-21021 January 2022 Compensatory Measures Not Implemented Per Site'S Physical Security Plan Due to Multiplexer (Mux) Power Supply Failure L-21-134, and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Independent Spent Fuel Storage Installations2021-12-17017 December 2021 and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Independent Spent Fuel Storage Installations ML21349A5192021-12-15015 December 2021 Commitment Change Summary Report ML21285A1912021-11-30030 November 2021 Nrc'S Analysis of Holtec Decommissioning International'S Decommissioning Funding Status Report for Oyster Creek Nuclear Generating Station and Pilgrim Nuclear Power Station, Docket Nos 50-219 and 50-293 IR 05000219/20210032021-11-16016 November 2021 NRC Inspection Report No. 05000219/2021003 L-21-118, Changes to Signature Authority & Addressee for Holtec Decommissioning International, LLC Correspondence Re to Oyster Creek Nuclear Generating Station, Pilgrim Nuclear Power Station, Indian Point Nuclear Generating Units 1, 2, 3, & Palisades2021-11-0909 November 2021 Changes to Signature Authority & Addressee for Holtec Decommissioning International, LLC Correspondence Re to Oyster Creek Nuclear Generating Station, Pilgrim Nuclear Power Station, Indian Point Nuclear Generating Units 1, 2, 3, & Palisades IR 05000219/20214042021-08-26026 August 2021 NRC Independent Spent Fuel Storage Security Inspection Report No. 07200015/2021402 and Security Decommissioning Inspection Report 05000219/2021404 - (Public) 2024-01-09 Category:Report MONTHYEARML23286A1552023-10-13013 October 2023
[Table view]Defueled Safety Analysis Report (DSAR) ML23025A0112023-01-24024 January 2023 LLRW Late Shipment Investigation Report Per 10 CFR 20, Appendix G ML22130A6882022-05-10010 May 2022 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML21036A1692021-01-29029 January 2021 ISFSI Only Security Plan, Training Qualification Plan, Safeguards Contingency Plan Supplemental Information ML20153A2282020-05-29029 May 2020 Biological Opinion for Oyster Creek Shutdown and Decommissioning ML19214A0452019-08-0202 August 2019 NRC to NMFS, Revised Proposed Action for Oyster Creek Endangered Species Act Section 7 Consultation ML19029B3332019-01-29029 January 2019 Security Inspection Plan for Oyster Creek Station - 2019 RA-18-084, Secondary Containment Capability Test2018-09-14014 September 2018 Secondary Containment Capability Test ML18033B7442018-02-21021 February 2018 Staff Assessment of the Response to 10 CFR 50.54(F) Information Request Flood-Causing Mechanism Reevaluation RA-17-032, Submittal of Biennial 10 CFR 50.59 and 1 O CFR 72.48 Change Summary Reports - January 1, 2015 Through December 31, 20162017-05-16016 May 2017 Submittal of Biennial 10 CFR 50.59 and 1 O CFR 72.48 Change Summary Reports - January 1, 2015 Through December 31, 2016 ML15350A3532016-02-17017 February 2016 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) Seismic Hazard Reevaluations for Recommendation 2.1 of the Near Term Task Force... RA-15-042, Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Reports - January 1, 2013 Through December 31, 20142015-05-26026 May 2015 Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Reports - January 1, 2013 Through December 31, 2014 ML15093A2842015-02-23023 February 2015 Enclosure 2: Flood Hazard Reevaluation Report for Oyster Creek Nuclear Generating Station, Rev. 1 RA-14-078, Secondary Containment Capability Test2014-10-24024 October 2014 Secondary Containment Capability Test RS-14-277, Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 12014-09-24024 September 2014 Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 1 RA-14-068, Sea Turtle Incidental Take Report 2014-32014-08-0101 August 2014 Sea Turtle Incidental Take Report 2014-3 ML14176A9612014-06-24024 June 2014 Submittal of Non-Proprietary BWROG Technical Product, BWROGTP-11-006 - ECCS Containment Walkdown Procedure, Rev 1 (January 2011), as Formally Requested During the Public Meeting Held on April 30, 2014 ML14065A2322014-06-16016 June 2014 Staff Assessment of Response to Enclosure 4 of the March 12, 2012, 10 CFR 50.54(F) Information Request - Flooding Walkdowns ML14030A5132014-02-19019 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) ML14038A1112014-02-11011 February 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Oyster Creek Nuclear Generating Station, TAC No.: MF0824 NEI 99-04, Oyster Creek Nuclear Generating Station, Commitment Change Summary Report - 20122013-12-23023 December 2013 Oyster Creek Nuclear Generating Station, Commitment Change Summary Report - 2012 RA-13-127, Commitment Change Summary Report - 20122013-12-23023 December 2013 Commitment Change Summary Report - 2012 RA-13-088, Sea Turtle Incidental Take Report 2013-52013-09-0909 September 2013 Sea Turtle Incidental Take Report 2013-5 RA-13-074, Sea Turtle Incidental Take Reports 2013-1 and 2013-22013-08-0909 August 2013 Sea Turtle Incidental Take Reports 2013-1 and 2013-2 ML15093A2832013-07-0303 July 2013 Enclosure 1: Local Intense Precipitation Evaluation Report for Oyster Creek, Rev. 6 RS-12-177, E Plan for Future Seismic Walkdown of Inaccessible Equipment2013-04-26026 April 2013 E Plan for Future Seismic Walkdown of Inaccessible Equipment ML13120A1862013-04-0909 April 2013 Enclosure 1, Seismic Walkdown Report in Response to the 50.54(f) Information Request Regarding Fukushima Near-Term Task Force Recommendation 2.3: Seismic Updated Transmittal # 1 for the Oyster Creek Generating Station Correspondence No. RS- ML13098A2092013-04-0505 April 2013 2.206 Petition by New Jersey Environmental Federation (Et.Al.) for Oyster Creek Nuclear Generating Station Exelon Generation Company, LLC IR 05000272/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000456/20132022013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee ML13008A2192013-01-31031 January 2013 U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000454/20132022013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000461/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000237/20132022013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000373/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000289/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000254/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000277/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000219/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000352/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee ML12355A1422012-12-31031 December 2012 2012 Oyster Creek Nuclear Generating Station Emergency Planning Zone Evacuation Time Estimates Analysis. Part 1 of 2 RS-12-217, 2012 Oyster Creek Nuclear Generating Station Emergency Planning Zone Evacuation Time Estimates Analysis. Part 2 of 22012-12-31031 December 2012 2012 Oyster Creek Nuclear Generating Station Emergency Planning Zone Evacuation Time Estimates Analysis. Part 2 of 2 RS-12-217, 2012 Oyster Creek Nuclear Generating Station Emergency Planning Zone Evacuation Time Estimates Analysis. Part 1 of 22012-12-31031 December 2012 2012 Oyster Creek Nuclear Generating Station Emergency Planning Zone Evacuation Time Estimates Analysis. Part 1 of 2 RA-12-117, Company, Llc'S 180-Day Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2012-11-19019 November 2012 Company, Llc'S 180-Day Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident ML12359A0082012-11-0606 November 2012 Rev. 1 to Report 12Q0108.80-R-001,Seismic Walkdown Report in Response to the 50.54(f) Information Request Re Fukushima Near-Term Task Force Recommendation 2.3: Seismic for the Oyster Creek Generating Station Unit 1. Part 1 of 4 ML12359A0062012-11-0606 November 2012 Rev. 1 to Report 12Q0108.80-R-001,Seismic Walkdown Report in Response to the 50.54(f) Information Request Re Fukushima Near-Term Task Force Recommendation 2.3: Seismic for the Oyster Creek Generating Station Unit 1. Part 3 of 4 ML12359A0052012-11-0606 November 2012 Rev. 1 to Report 12Q0108.80-R-001,Seismic Walkdown Report in Response to the 50.54(f) Information Request Re Fukushima Near-Term Task Force Recommendation 2.3: Seismic for the Oyster Creek Generating Station Unit 1. Part 2 of 4 RS-13-065, Core Spray/Auto Depress'N System Relay Logic Panel2012-10-10010 October 2012 Core Spray/Auto Depress'N System Relay Logic Panel RA-13-022, D Area Walk-By Checklists (Awcs)2012-10-10010 October 2012 D Area Walk-By Checklists (Awcs) ML12178A2152012-08-0202 August 2012 Closeout of Bulletin 2011-01 Migrating Strategies. 2023-10-13 Category:Miscellaneous MONTHYEARML23025A0112023-01-24024 January 2023
[Table view]LLRW Late Shipment Investigation Report Per 10 CFR 20, Appendix G ML19029B3332019-01-29029 January 2019 Security Inspection Plan for Oyster Creek Station - 2019 ML18033B7442018-02-21021 February 2018 Staff Assessment of the Response to 10 CFR 50.54(F) Information Request Flood-Causing Mechanism Reevaluation RA-17-032, Submittal of Biennial 10 CFR 50.59 and 1 O CFR 72.48 Change Summary Reports - January 1, 2015 Through December 31, 20162017-05-16016 May 2017 Submittal of Biennial 10 CFR 50.59 and 1 O CFR 72.48 Change Summary Reports - January 1, 2015 Through December 31, 2016 ML15350A3532016-02-17017 February 2016 Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) Seismic Hazard Reevaluations for Recommendation 2.1 of the Near Term Task Force... RA-15-042, Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Reports - January 1, 2013 Through December 31, 20142015-05-26026 May 2015 Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Reports - January 1, 2013 Through December 31, 2014 RA-14-068, Sea Turtle Incidental Take Report 2014-32014-08-0101 August 2014 Sea Turtle Incidental Take Report 2014-3 ML14065A2322014-06-16016 June 2014 Staff Assessment of Response to Enclosure 4 of the March 12, 2012, 10 CFR 50.54(F) Information Request - Flooding Walkdowns NEI 99-04, Oyster Creek Nuclear Generating Station, Commitment Change Summary Report - 20122013-12-23023 December 2013 Oyster Creek Nuclear Generating Station, Commitment Change Summary Report - 2012 RA-13-127, Commitment Change Summary Report - 20122013-12-23023 December 2013 Commitment Change Summary Report - 2012 RA-13-088, Sea Turtle Incidental Take Report 2013-52013-09-0909 September 2013 Sea Turtle Incidental Take Report 2013-5 RA-13-074, Sea Turtle Incidental Take Reports 2013-1 and 2013-22013-08-0909 August 2013 Sea Turtle Incidental Take Reports 2013-1 and 2013-2 ML13098A2092013-04-0505 April 2013 2.206 Petition by New Jersey Environmental Federation (Et.Al.) for Oyster Creek Nuclear Generating Station Exelon Generation Company, LLC IR 05000454/20132022013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000456/20132022013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee ML13008A2192013-01-31031 January 2013 U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000461/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000289/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000272/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000254/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000277/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000219/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000352/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000373/20132012013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee IR 05000237/20132022013-01-31031 January 2013 Exelon Generation Co., LLC, U.S. Nuclear Regulatory Commission (NRC) Office of Investigations (01) Investigation; Summary of 01 Report No. 3-2010-034; NRC Inspection Report Conference Letter - Licensee ML12178A2152012-08-0202 August 2012 Closeout of Bulletin 2011-01 Migrating Strategies. ML12166A5042012-07-0505 July 2012 Operating Station Review of Committment Submittal for License Renewal Regarding Thermal Aging Irradiation Embrittlement of Cast Austenitic Stainless Steel ML1127000692011-09-26026 September 2011 Enclosure 2, Mfn 10-245 R4, Description of the Evaluation and Surveillance Recommendations for BWR/2-5 Plants RA-11-031, Oyster Creek - Submittal of Commitment Change Summary Report - 20102011-08-12012 August 2011 Oyster Creek - Submittal of Commitment Change Summary Report - 2010 NEI 99-04, Oyster Creek - Submittal of Commitment Change Summary Report - 20102011-08-12012 August 2011 Oyster Creek - Submittal of Commitment Change Summary Report - 2010 RA-11-005, Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Reports - January 1, 2009 Though December 31, 20102011-06-24024 June 2011 Biennial 10 CFR 50.59 and 10 CFR 72.48 Change Summary Reports - January 1, 2009 Though December 31, 2010 RA-10-023, Submittal of Commitment Change Summary Report - 20092010-08-0606 August 2010 Submittal of Commitment Change Summary Report - 2009 NEI 99-04, Oyster Creek, Submittal of Commitment Change Summary Report - 20092010-08-0606 August 2010 Oyster Creek, Submittal of Commitment Change Summary Report - 2009 ML1012704392010-05-0505 May 2010 Y020100187 - List of Historical Leaks and Spills at U.S. Commercial Nuclear Power Plants ML1007402512009-08-0707 August 2009 AR 00916938 Report ML0934208122009-06-29029 June 2009 Root Cause Evaluation Report: Tritium Identified in Emergency Service Water (ESW) Vault ML1020203712009-06-25025 June 2009 Assignment Report #00907846 ML1007402602009-06-24024 June 2009 Issue - Statement of Confirmation ML1007402612009-06-24024 June 2009 AR 00934636 Report ML1020203682009-06-23023 June 2009 Assignment Report #009128267 ML1007402592009-06-21021 June 2009 Stable Standard-Fixed Target Hot Lab ML1007402192009-06-14014 June 2009 AR 00931098 Report ML1007402562009-06-0505 June 2009 AR 00928211 Report ML1020203672009-06-0404 June 2009 Assignment Report #00928211 ML1020203662009-06-0303 June 2009 Assignment Report #00927310 ML1007402572009-06-0101 June 2009 AR 00926251 Report ML1020203652009-05-26026 May 2009 Assignment Report #00907846 ML1007402162009-05-22022 May 2009 AR 00922841 Report ML1007402552009-05-22022 May 2009 AR 00922841 Report ML1020203302009-05-14014 May 2009 Assignment Report #00919392 2023-01-24 |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 January 29, 2019 Mr. Jeffery Dostal Decommissioning Plant Manager Oyster Creek Nuclear Generation Stn Exelon Generation Company LLC 741 Route 9 South Forked River, NJ 08731
SUBJECT:
SECURITY INSPECTION PLAN FOR OYSTER CREEK GENERATING STATION
Dear Mr. Dostal:
The enclosed inspection plan lists the security inspections scheduled through December 31, 2020. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well before our inspectors arrive on site.
In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRCs Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (610) 337-5150 with any questions you may have regarding the inspection plan.
Sincerely,
/RA/
Raymond R. McKinley, Chief Plant Support Branch 1 Division of Reactor Safety Docket No. 50-219 License No. DPR-16
Enclosure:
Oyster Creek Nuclear Generating Station Inspection Plan cc w/encl; J. Dwyer, Manager, Nuclear Security
IP 24 Security Activity Plan Report Oyster Creek 01/01/2019 - 12/31/2020 Unit Start End Activity CAC Title Staff Count ACCESS CONTROL & EQUIP PERF 2 1 03/11/2019 03/15/2019 IP 81200.02 000025 Access Control for Decommissioning Nuclear Power Reactors 1 03/11/2019 03/15/2019 IP 81200.04 000026 Equipment Performance, Testing, and Maintenance for Decommissioning Nuclear Power Reactors Access Control, Sec Training, Protective Strategy, TSR 3 1 03/16/2020 03/20/2020 IP 81200.02 000025 Access Control for Decommissioning Nuclear Power Reactors 1 03/16/2020 03/20/2020 IP 81200.05 000027 Protective Strategy Evaluation and Performance Evaluation Program for Decommissioning Nuclear Power 1 03/16/2020 03/20/2020 IP 81200.07 000029 Security Training for Decommissioning Nuclear Power Reactors 1 03/16/2020 03/20/2020 IP 81200.14 000030 Review of Decommissioning Reactor Target Sets Page 1 of 1 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures. 12/10/2018 11:27:22 AM
ML19029B333 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRS RI/DNMS RI/DRS NAME JRey/JR RPowell/RP RMcKinley/RRM DATE 12/17/18 12/17/18 01/29/19