MONTHYEARML24127A0362024-04-23023 April 2024 News Release-II-24-011: NRC Schedules Virtual Public Meeting to Discuss Virginia Nuclear Power Plants Performance ML24052A2692023-10-24024 October 2023 News Release-II-23-031: NRC Names New Resident Inspector at Surry Power Station ML24047A0842023-05-0303 May 2023 News Release-II-23-012: NRC Schedules Virtual Meeting to Discuss North Anna and Surry Nuclear Power Plant Performance Press Release-II-22-017, NRC Names New Senior Resident Inspector at Surry Nuclear Power Plant2022-06-23023 June 2022 Press Release-II-22-017: NRC Names New Senior Resident Inspector at Surry Nuclear Power Plant Press Release-II-22-010, NRC Schedules Virtual Meeting to Discuss Safety Performance of North Anna and Surry Nuclear Power Plants2022-04-13013 April 2022 Press Release-II-22-010: NRC Schedules Virtual Meeting to Discuss Safety Performance of North Anna and Surry Nuclear Power Plants ML21209A5092021-05-0404 May 2021 News Release-21-019: NRC Issues Subsequent Renewed Licenses for Surry Reactors Press Release-II-21-007, NRC Hosts Virtual Meeting to Discuss 2020 Safety Performance of V.C. Summer, North Anna and Surry Nuclear Power Plants2021-04-19019 April 2021 Press Release-II-21-007: NRC Hosts Virtual Meeting to Discuss 2020 Safety Performance of V.C. Summer, North Anna and Surry Nuclear Power Plants Press Release-I-20-008, NRC Schedules Webinar to Discuss 2019 Safety Performance at Pennsylvania and Maryland Nuclear Power Plants2020-05-27027 May 2020 Press Release-I-20-008: NRC Schedules Webinar to Discuss 2019 Safety Performance at Pennsylvania and Maryland Nuclear Power Plants Press Release-II-20-009, NRC Schedules Virtual Meeting to Discuss 2019 Safety Performance of North Anna and Surry Nuclear Power Plants2020-04-15015 April 2020 Press Release-II-20-009: NRC Schedules Virtual Meeting to Discuss 2019 Safety Performance of North Anna and Surry Nuclear Power Plants Press Release-20-022, NRC Issues Final Environmental Impact Statement for Surry Subsequent License Renewal2020-04-10010 April 2020 Press Release-20-022: NRC Issues Final Environmental Impact Statement for Surry Subsequent License Renewal Press Release-II-19-031, NRC Names New Senior Resident Inspector at Surry Nuclear Power Station2019-07-11011 July 2019 Press Release-II-19-031: NRC Names New Senior Resident Inspector at Surry Nuclear Power Station Press Release-II-19-021, NRC Schedules Open House to Discuss Surry Nuclear Power Plant Performance2019-04-18018 April 2019 Press Release-II-19-021: NRC Schedules Open House to Discuss Surry Nuclear Power Plant Performance Press Release-18-064, NRC to Hold Public Meeting Seeking Comment on Environmental Review for Surry Subsequent License Renewal2018-12-21021 December 2018 Press Release-18-064: NRC to Hold Public Meeting Seeking Comment on Environmental Review for Surry Subsequent License Renewal Press Release-18-062, Revised with New Filing Deadline: NRC Accepts Application for Subsequent License Renewal of Surry Power Station Reactors2018-12-19019 December 2018 Press Release-18-062: Revised with New Filing Deadline: NRC Accepts Application for Subsequent License Renewal of Surry Power Station Reactors Press Release-18-062, NRC Accepts Application for Subsequent License Renewal of Surry Power Station Reactors2018-12-10010 December 2018 Press Release-18-062: NRC Accepts Application for Subsequent License Renewal of Surry Power Station Reactors ML18344A4882018-12-10010 December 2018 Press Release-18-062: NRC Accepts Application for Subsequent License Renewal of Surry Power Station Reactors Press Release-18-054, NRC Makes Surry'S Subsequent License Renewal Application Publicly Available2018-10-26026 October 2018 Press Release-18-054: NRC Makes Surry'S Subsequent License Renewal Application Publicly Available Press Release-II-18-028, NRC Names New Resident Inspector at Surry Nuclear Power Plant2018-06-11011 June 2018 Press Release-II-18-028: NRC Names New Resident Inspector at Surry Nuclear Power Plant Press Release-II-18-022, NRC to Hold Open House to Discuss 2017 Performance of Surry Nuclear Power Plant2018-05-0808 May 2018 Press Release-II-18-022: NRC to Hold Open House to Discuss 2017 Performance of Surry Nuclear Power Plant Press Release-II-17-022, NRC Schedules Open House to Discuss 2016 Performance of Surry Nuclear Station2017-04-12012 April 2017 Press Release-II-17-022: NRC Schedules Open House to Discuss 2016 Performance of Surry Nuclear Station Press Release-II-16-015, NRC Schedules Open House to Discuss Agency'S 2015 Assessment of Surry Nuclear Station2016-04-0505 April 2016 Press Release-II-16-015: NRC Schedules Open House to Discuss Agency'S 2015 Assessment of Surry Nuclear Station Press Release-II-15-030, NRC Schedules Open House April 28 to Discuss Agency'S 2014 Assessment of Surry Nuclear Station2015-04-20020 April 2015 Press Release-II-15-030: NRC Schedules Open House April 28 to Discuss Agency'S 2014 Assessment of Surry Nuclear Station Press Release-II-14-033, NRC Assigns New Resident Inspector to Surry Nuclear Power Plant2014-06-16016 June 2014 Press Release-II-14-033: NRC Assigns New Resident Inspector to Surry Nuclear Power Plant Press Release-II-14-007, NRC Schedules Open House for March 18 to Discuss Surry Nuclear Plant Safety Performance2014-03-0707 March 2014 Press Release-II-14-007: NRC Schedules Open House for March 18 to Discuss Surry Nuclear Plant Safety Performance Press Release-II-13-052, NRC Assigns New Senior Resident Inspector to Surry Nuclear Power Plant2013-08-22022 August 2013 Press Release-II-13-052: NRC Assigns New Senior Resident Inspector to Surry Nuclear Power Plant Press Release-II-13-036, NRC Schedules Open House to Discuss Annual Assessment of Surry Nuclear Power Station2013-05-13013 May 2013 Press Release-II-13-036: NRC Schedules Open House to Discuss Annual Assessment of Surry Nuclear Power Station ML12110A3222012-04-17017 April 2012 Press Release-II-12-023: NRC Schedules Open House to Discuss Annual Assessment of Surry Nuclear Power Plant Press Release-II-12-023, NRC Schedules Open House to Discuss Annual Assessment of Surry Nuclear Power Plant2012-04-17017 April 2012 Press Release-II-12-023: NRC Schedules Open House to Discuss Annual Assessment of Surry Nuclear Power Plant Press Release-II-12-017, NRC Schedules Regulatory Conference to Discuss Apparent Violation at Surry Nuclear Station2012-04-11011 April 2012 Press Release-II-12-017: NRC Schedules Regulatory Conference to Discuss Apparent Violation at Surry Nuclear Station Press Release-12-011, NRC Seeks Comment on Reactor Accident Consequence Research; Public Meetings Feb. 21, 22 in Virginia, Pennsylvania2012-02-0101 February 2012 Press Release-12-011: NRC Seeks Comment on Reactor Accident Consequence Research; Public Meetings Feb. 21, 22 in Virginia, Pennsylvania Press Release-11-159, NRC Makes Preparations for Approach of Hurricane Irene; Dispatches Additional Inspectors to Nuclear Plants2011-08-26026 August 2011 Press Release-11-159: NRC Makes Preparations for Approach of Hurricane Irene; Dispatches Additional Inspectors to Nuclear Plants Press Release-II-11-021, NRC Monitors Events at Surry Nuclear Power Plant After Loss of Offsite Power and Unusual Event Declaration2011-04-17017 April 2011 Press Release-II-11-021: NRC Monitors Events at Surry Nuclear Power Plant After Loss of Offsite Power and Unusual Event Declaration Press Release-II-11-013, NRC Schedules Meeting to Discuss 2010 Performance of Surry Nuclear Power Plant2011-03-30030 March 2011 Press Release-II-11-013: NRC Schedules Meeting to Discuss 2010 Performance of Surry Nuclear Power Plant Press Release-10-168, NRC Approves Power Uprate for Surry Nuclear Power Plant2010-09-27027 September 2010 Press Release-10-168: NRC Approves Power Uprate for Surry Nuclear Power Plant Press Release-II-10-046, NRC Begins Special Inspection at Surry Nuclear Plant2010-06-11011 June 2010 Press Release-II-10-046: NRC Begins Special Inspection at Surry Nuclear Plant Press Release-II-10-015, NRC Schedules Open House to Discuss 2009 Performance of Surry Nuclear Power Plant2010-04-0707 April 2010 Press Release-II-10-015: NRC Schedules Open House to Discuss 2009 Performance of Surry Nuclear Power Plant Press Release-II-09-015, NRC Schedules Open House to Answer Questions on 2008 Performance of Surry Nuclear Power Plant2009-03-25025 March 2009 Press Release-II-09-015: NRC Schedules Open House to Answer Questions on 2008 Performance of Surry Nuclear Power Plant Press Release-II-08-019, NRC to Discuss 2007 Performance of Surry Nuclear Power Plant2008-04-0909 April 2008 Press Release-II-08-019: NRC to Discuss 2007 Performance of Surry Nuclear Power Plant Press Release-II-07-048, - NRC Assigns New Senior Resident Inspector to Surry Nuclear Power Plant2007-10-0202 October 2007 Press Release-II-07-048 - NRC Assigns New Senior Resident Inspector to Surry Nuclear Power Plant Press Release-II-07-019, NRC to Discuss 2006 Performance at Surry Nuclear Plant2007-04-13013 April 2007 Press Release-II-07-019: NRC to Discuss 2006 Performance at Surry Nuclear Plant Press Release-II-06-043, NRC to Send Special Inspection Team to Surry Nuclear Plant to Review Offsite Power Loss and Shutdown2006-10-13013 October 2006 Press Release-II-06-043: NRC to Send Special Inspection Team to Surry Nuclear Plant to Review Offsite Power Loss and Shutdown Press Release-II-06-021, NRC to Discuss 2005 Performance at Surry Nuclear Plant2006-04-11011 April 2006 Press Release-II-06-021: NRC to Discuss 2005 Performance at Surry Nuclear Plant Press Release-II-05-012, NRC to Discuss 2004 Performance at Surry Nuclear Power Plant2005-03-23023 March 2005 Press Release-II-05-012: NRC to Discuss 2004 Performance at Surry Nuclear Power Plant Press Release-05-038, NRC Renews License for Dry-Cask Spent Fuel Installation at Dominion'S Surry Nuclear Power Plant2005-03-0101 March 2005 Press Release-05-038: NRC Renews License for Dry-Cask Spent Fuel Installation at Dominion'S Surry Nuclear Power Plant Press Release-II-04-048, NRC Cites Surry Nuclear Power Plant for Inspection Findings of Low to Moderate Safety Significance2004-09-17017 September 2004 Press Release-II-04-048: NRC Cites Surry Nuclear Power Plant for Inspection Findings of Low to Moderate Safety Significance Press Release-II-04-042, Garrett Named NRC Senior Resident Inspector at Surry Nuclear Station2004-08-0606 August 2004 Press Release-II-04-042: Garrett Named NRC Senior Resident Inspector at Surry Nuclear Station Press Release-II-04-021, NRC to Hold Open Regulatory Conference to Discuss Surry Nuclear Plant Operations2004-03-31031 March 2004 Press Release-II-04-021: NRC to Hold Open Regulatory Conference to Discuss Surry Nuclear Plant Operations Press Release-II-04-016, NRC to Meet with Dominion Energy Officials to Discuss Safety Performance at Surry Nuclear Power Plant2004-03-22022 March 2004 Press Release-II-04-016: NRC to Meet with Dominion Energy Officials to Discuss Safety Performance at Surry Nuclear Power Plant Press Release-II-03-045, NRC Region II Office in Atlanta Implements Hurricane Response Procedure2003-09-17017 September 2003 Press Release-II-03-045: NRC Region II Office in Atlanta Implements Hurricane Response Procedure Press Release-II-03-037, Mccoy Named NRC Senior Resident Inspector at Surry Nuclear Plant2003-07-18018 July 2003 Press Release-II-03-037: Mccoy Named NRC Senior Resident Inspector at Surry Nuclear Plant 2024-04-23
[Table view] |
See also: see also:Press Release-18-062
Text
No: 18-062 December 10, 2018
CONTACT: Scott Burnell, 301-415-8200
NRC Accepts Application for Subsequent License Renewal
of Surry Power Station Reactors
The Nuclear Regulatory Commission has accepted for review an application from Virginia
Electric and Power Company (Dominion Energy Virginia) to extend for an additional 20 years the
renewed operating licenses of Surry Units 1 and 2, located near Surry, Va. Dominion submitted its
subsequent license renewal application on Oct. 15.
The application, less proprietary details, is available on the NRC website. Dominion is seeking a
subsequent renewal for the Surry units, approximately 17 miles northwest of Newport News, Va. The
NRC approved the initial license renewal in March 2003, with Unit 1 currently licensed to operate
through May 25, 2032, and Unit 2 through Jan. 29, 2033.
Accepting the application for review, or docketing the application, does not indicate whether
the Commission will approve or reject the request. More information about subsequent license renewal
is available on the NRC website.
The NRC has published in the Federal Register a notice of opportunity to intervene in an
adjudicatory hearing. Petitions to intervene in a hearing must be filed by Feb. 5, 2019, by anyone whose
interest may be affected by the proposed license renewal and who wishes to participate as a party in the
proceeding. More information on the hearing process is available on the NRC website.