Acceptance for Review of Global Nuclear Fuel Proposed Amendment 47 to NEDE-24011-P-A-27, General Electric Standard Application for Reactor Fuel (Gestar II) Supporting Implementation of TSTF-564 (EPID: L-2018-Top-0038)
ML18313A052
Person / Time
Site: 99901376
Issue date: 11/15/2018
From: Dennis Morey
NRC/NRR/DLP/PLPB
To: Michelle Catts
GE-Hitachi Nuclear Energy Americas
Golla J, NRR/DLP, 415-1002
References
EPID L-2018-TOP-0038, NEDE-24011-P-A-27, TSTF-564
Download: ML18313A052 (4)


Text

November 15, 2018 Ms. Michelle Catts Senior Vice President, Regulatory Affairs GE-Hitachi Nuclear Energy Americas, LLC P.O. Box 780, M/C A-10 Wilmington, NC 28401-0780

SUBJECT:

ACCEPTANCE FOR REVIEW OF GLOBAL NUCLEAR FUEL PROPOSED AMENDMENT 47 TO NEDE-24011-P-A-27, GENERAL ELECTRIC STANDARD APPLICATION FOR REACTOR FUEL (GESTAR II) SUPPORTING IMPLEMENTATION OF TSTF-564 (EPID: L-2018-TOP-0038)

Dear Ms. Catts:

By letter dated September 12, 2018 (Agencywide Documents Access and Management System Accession No. ML18256A013), Global Nuclear Fuel - Americas (GNF), submitted for U.S. Nuclear Regulatory Commission (NRC) staff review Proposed Amendment 47 to NEDE-24011-P-A-27, General Electric Standard Application for Reactor Fuel (GESTAR II)

Supporting Implementation of TSTF-564. The NRC staff has performed an acceptance review of this topical report (TR). We have found that the material presented is sufficient to begin our review. We expect to issue our request for additional information by January 9, 2019, and issue our draft safety evaluation (SE) by March 26, 2019.

This schedule information takes into consideration the NRCs current review priorities and available technical resources and may be subject to change. If modifications to these dates are deemed necessary, we will provide appropriate updates to this information. The NRC staff estimates that the review will require approximately 160 staff hours including project management. The review schedule milestones and estimated review costs were discussed and agreed upon in an email exchange between Ms. Lisa Schichlein and the NRC staff on November 9, 2018.

Section 170.21 of Title 10 of the Code of Federal Regulations requires that TRs are subject to fees based on the full cost of the review. You did not request a fee waiver; therefore, NRC staff hours will be billed accordingly.

J. Head Please contact Joseph A. Golla at (301) 415-1002, if you have any questions on this subject.

Sincerely,

/RA/

Dennis C. Morey, Chief Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation Docket No. 99901376 cc: See next page

ML18313A052 *concurrence via e-mail NRR-106 OFFICE NRR/DLP/PLPB NRR/DLP/PLPB/ LA* NRR/DSS/SNPB NRR/DLP/PLPB/BC NAME JGolla DHarrison RLukes DMorey DATE 11/13/2018 11/13/2018 11/14/2018 11/15/2018 GE-Hitachi Nuclear Energy Americas Docket No. 99901376 Project No. 712 cc:

Ms. Michelle P. Catts Senior Vice President, Regulatory Affairs GE-Hitachi Nuclear Energy Americas, LLC P.O. Box 780 M/C A-10 Wilmington, NC 28401 Michelle.Catts@ge.com Mr. Kent E. Halac Senior Project Manager, Regulatory Affairs GE-Hitachi Nuclear Energy Americas, LLC P.O. Box 780, M/C A-70 Wilmington, NC 28401-0780 Kent.Halac@ge.com Dr. Brian R. Moore General Manager, Core & Fuel Engineering Global Nuclear Fuel-Americas, LLC P.O. Box 780, M/C A-75 Wilmington, NC 28401-0780 Brian.Moore@ge.com Ms. Lisa K. Schichlein Senior Project Manager, Regulatory Affairs GE-Hitachi Nuclear Energy Americas, LLC P.O. Box 780, M/C A-70 Wilmington, NC 28401-0780 Lisa.Schichlein@ge.com