REVIEWER WORK REQUEST OFFICE OF NUCLEAR MATERIAL SAFETY AND SAFEGUARDS October 16, 2018 FROM:
Jacob Zimmerman, Chief, Fuel Facility Licensing Branch (FFLB)
Division of Fuel Cycle Safety, Safeguards, and Environmental Review (FCSE)
NMSS TO:
Chris McKenney, Risk and Technical Analysis Branch (RTAB)
Decommissioning, Uranium Recovery, and Waste Programs (DUWP)/NMSS PROJECT:
Massachusetts Institute of Technology Financial Assurance Update, Self-Guarantee DOCKET NO:
0700-0938 LICENSE NO: SNM-986 DOCUMENT DATE: Sept 27, 2018 (Docketed October 11, 2018)
ADAMS ACCESSION NO.: ML18284A321 CAC/DOCKET/EPID NO: A38003/L-2018-DFA-0009 REQUESTED ACTION: Review the Instrument for an Update to Financial Assurance (Self Guarantee) submitted by the Massachusetts Institute of Technology material licensees identified on the docketed correspondence. Determine if there are major deficiencies that make the submittal unacceptable for detailed review and prepare a recommendation to accept or deny (if required).
Prepare requests for additional information, if needed. Evaluate any additional information submitted. Participate in meetings, conference calls, and site visits, if necessary. Provide input for a Final Report.
RECEIVING BRANCH CHIEF - PLEASE COMPLETE AND RETURN IN 5 BUSINESS DAYS:
Technical Reviewer: ______Reginald Augustus______
Estimated Staff Hours: 30 BC Concurrence: ____cam____
Requested Acceptance Review Date: 11/16/2017 Proposed Target Date: _11/16/2018_
Requested RAI Input Date: 12/18/2017 Proposed Target Date: _12/18/2018_
Requested SER Input Date: 1/25/2019 Proposed Target Date: _1/25/2019__
BC Concurrence: ___CAM________