MONTHYEARML17200D1622017-07-19019 July 2017 License Amendment Request to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors Project stage: Request ML17240A0072017-08-25025 August 2017 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of 10 CFR 50.69 LAR, Risk-Informed Categorization and Treatment of SSCs Project stage: Acceptance Review ML17249A0722017-09-0505 September 2017 NRR E-mail Capture - Slides for Sept 6, 2017, Public Meeting to Discuss Nei'S Model 10 CFR 50.69 License Amendment Request Project stage: Meeting ML18099A0072018-04-0606 April 2018 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for 10 CFR 50.69 LAR (CAC Nos. MF9971, MF9972, and MF9973; EPID L-2017-LLA-0276) Project stage: RAI ML18129A4482018-05-0909 May 2018 APS Response to Request for Additional Information for License Amendment Request to Adopt 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems, and Components Project stage: Response to RAI ML18194A9142018-07-13013 July 2018 Supplemental Response to Request for Additional Information 3.a for License Amendment Request to Adopt 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems, and Components Project stage: Supplement ML18223A0052018-08-10010 August 2018 Updated Proposed License Condition Regarding License Amendment Request to Adopt 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems, and Components Project stage: Request ML18243A2802018-10-10010 October 2018 Issuance of Amendment Nos. 207, 207, and 207 to Adopt 10 CFR 50.69 (CAC Nos. MF9971, MF9972, and MF9973; EPID L-2017-LLA-0276) Project stage: Approval 2018-10-10
[Table View] |
|
---|
Category:Letter
MONTHYEARML24295A0362024-10-23023 October 2024 Regulatory Audit Plan in Support of Relief Request No. 71; Resubmittal of Relief Request-30 IR 05000528/20244022024-10-22022 October 2024 Security Baseline Inspection Report 05000528/2024402 and 05000529/2024402 and 05000530/2024402 ML24296B2142024-10-22022 October 2024 Transmittal of Valve Relief Request (VRR) - 02: Alternative Request Allowing Normally Closed Valves with a Safety Function to Close to Be Exercise Tested Once Per Refueling Cycle ML24296B2152024-10-22022 October 2024 Transmittal of Valve Relief Request (VRR) - 03: Alternative Request Allowing Removal of the Lower Acceptance Criteria Threshold from Solenoid-Operated Valves ML24296B2172024-10-18018 October 2024 Submittal of Unit 1 Core Operating Limits Report, Revision 34, Unit 2 Core Operating Limits Report, Revision 26, and Unit 3 Core Operating Limits Report, Revision 3 ML24292A2192024-10-18018 October 2024 Core Operating Limits Report Revision 34, 26 and 33 ML24292A0322024-10-17017 October 2024 Th Refueling Outage Steam Generator Tube Inspection Report ML24285A2562024-10-11011 October 2024 License Renewal - Alloy 600 Management Program Plan Response to Request for Additional Information IR 07200044/20244012024-10-0808 October 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07200044/2024401 ML24269A1542024-09-27027 September 2024 Summary of Presubmittal Meeting with Arizona Public Service Company to Discuss Proposed Life-of-Plant Alternatives for a Pressurizer Thermowell Nozzle Repair at Palo Verde Nuclear Generating Station, Unit 1 ML24262A0972024-09-23023 September 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000529/2024011) ML24241A2542024-08-28028 August 2024 Inservice Inspection Request for Information ML24241A2782024-08-28028 August 2024 License Amendment Request to Revise the Technical Specifications 3.5.1 and 3.5.2 Safety Injection Tank Pressure Bands, and to Use GOTHIC Code ML24240A2682024-08-27027 August 2024 Transmittal of Technical Specification Bases Revision 79 IR 05000528/20240052024-08-22022 August 2024 Updated Inspection Plan for Palo Verde Nuclear Generating Station - Units 1, 2, and 3 (Report 05000528/2024005, 05000529/2024005, 05000530/2024005) 05000530/LER-2024-001-01, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation2024-08-21021 August 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24208A0612024-08-20020 August 2024 Issuance of Amendment Nos. 224, 224, and 224 Regarding Revision to Technical Specifications 3.5.1, 3.5.2 and 3.6.5 IR 05000528/20244042024-08-0808 August 2024 Cybersecurity Inspection Report 05000528/2024404, 05000529/2024404 and 05000530/2024404 ML24213A3232024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 71: Re-Submittal of RR-30 ML24213A3292024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 72: Re-Submittal of RR-39 IR 05000528/20240022024-07-29029 July 2024 Integrated Inspection Report 05000528/2024002 and 05000529/2024002 and 05000530/2024002 ML24173A3302024-07-24024 July 2024 Pressurizer Surge Line Inspection Program ML24159A4702024-07-17017 July 2024 Issuance of Amendment Nos. 223, 223, and 223 Revision to Technical Specifications 3.5.1 and 3.5.2 Using Risk Informed Process for Evaluations ML24198A0662024-07-16016 July 2024 Program Review - Simulator Testing Methodology ML24193A3442024-07-11011 July 2024 Fourth 10-Year Interval, Second Period Owner’S Activity Report Number 3R24 ML24129A0522024-07-0303 July 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report IR 05000528/20240042024-06-25025 June 2024 Notification of Inspection (NRC Inspection Report 05000528/2024004, 05000529/2024004, 05000530/2024004) 05000530/LER-2024-002, Invalid Specified System Actuation of Train B Emergency Diesel Generator2024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator ML24177A3212024-06-25025 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canisters Identification Numbers AMZDFX180, AMZDFX181, AMZDFX182 Vertical Concrete Cask Identification Nu ML24177A3222024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator ML24170A9962024-06-18018 June 2024 Response to Second Request for Additional Information to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) – Operating, TS 3.5.2, Safety Injection Tanks (Sits) – Shutdown a ML24129A2062024-06-14014 June 2024 Issuance of Amendment Nos. 222, 222, and 222 Revision to Technical Specifications to Adopt TSTF-266-A 05000530/LER-2024-001, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation2024-06-0505 June 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24159A0262024-06-0303 June 2024 Annual Report of Guarantee of Payment of Deferred Premium 05000529/LER-2024-001, Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater2024-05-23023 May 2024 Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater ML24135A2482024-05-14014 May 2024 Response to Second Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24164A2582024-05-0909 May 2024 10-PV-2024-04 Post-Exam Comments ML24129A1482024-05-0707 May 2024 And Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Casks with Applied Changes ML24128A2702024-05-0707 May 2024 Docket Nos. Stn 50-528/529/530 - Response to NRC Regulatory Issue Summary (RIS) 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000528/20240012024-05-0202 May 2024 Independent Spent Fuel Storage Installation, Integrated Inspection Report 05000528/2024001, 05000529/2024001, 05000530/2024001, 07200044/2024001, and Exercise of Enforcement Discretion ML24119A0022024-04-26026 April 2024 2023 Annual Environmental Operating Report ML24116A2082024-04-24024 April 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2023 ML24109A0712024-04-22022 April 2024 NRC Initial Operator Licensing Examination Approval 05000528/2024301, 05000529/2024301, and 05000530/2024301 IR 05000528/20244012024-04-22022 April 2024 Security Baseline Inspection Report 05000528/2024401 and 05000529/2024401 and 05000530/2024401 (Cover Letter) ML24112A0012024-04-19019 April 2024 Core Operating Limits Report, Revision 32 ML24108A1982024-04-16016 April 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Casks with Applied Changes Authorized by an Amended Certificate of Compliance ML24103A2482024-04-12012 April 2024 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2023 ML24131A0972024-04-10010 April 2024 Annual Radiological Environmental Operating Report 2023 ML24096A2202024-04-0505 April 2024 Transmittal of Technical Specification Bases Revision 78 ML24032A1542024-04-0303 April 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) 2024-09-27
[Table view] |
Text
10 CFR 50.69 10 CFR 50.90 MARIA L. LACAL Senior Vice President Nuclear Regulatory and Oversight Palo Verde Nuclear Generating Station P.O. Box 52034 102-07765-MLL/MDD Phoenix, AZ 85072 August 10, 2018 Mail Station 7605 Tel 623.393.6491 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Reference:
Arizona Public Service Company (APS) Letter 102-07690, APS Response to Request for Additional Information for License Amendment Request to Adopt 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems, and Components, dated May 9, 2018, ADAMS No. ML18129A448
Dear Sirs:
Subject:
Palo Verde Nuclear Generating Station Units 1, 2, and 3 Docket Nos. STN 50-528, 50-529, and 50-530 Updated Proposed License Condition Regarding License Amendment Request to Adopt 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems, and Components On July 19, 2017, APS submitted a license amendment request (LAR) to adopt Title 10 of the Code of Federal Regulations (10 CFR) Section 50.69, Risk-Informed Categorization and Treatment Of Structures, Systems, and Components for Nuclear Power Reactors. During the week of February 20, 2018, the NRC staff conducted an audit at the Palo Verde Nuclear Generating Station (PVNGS) to gain an understanding of the risk-informed categorization process and to review the probabilistic risk assessment models that will be used by APS for this risk-informed LAR. The NRC staff determined that additional information was required to complete their review. The APS response to the Request for Additional Information (RAI) was provided by the referenced letter.
Subsequently, the NRC staff requested a clarification call with APS that was held on August 8, 2018. During the call, the NRC noted that it would be appropriate for APS to provide an update to the proposed license condition. Specifically, the license condition should itemize, in greater detail, the probabilistic risk assessment models used to perform 10 CFR 50.69 evaluations. The enclosure to this letter includes the entire license condition that supports the license amendment request.
APS has reviewed the information supporting a finding of no significant hazards consideration that was provided to the NRC. The information provided in this letter does not affect the basis for concluding that the proposed license amendment does not involve a significant hazards consideration under the standards set forth in 10 CFR 50.92.
A member of the STARS Alliance Callaway Diablo Canyon Palo Verde Wolf Creek
Enclosure Updated Proposed License Condition
Enclosure Additional Condition Operating License No. NPF-41, NPF-51, and NPF-74 APS proposes the following license condition be added to Appendix D of the PVNGS Units 1, 2, & 3 Renewed Operating Licenses:
Amendment Additional Condition Implementation Number Date APS is approved to implement 10 CFR 50.69 using the processes for categorization of Risk-Informed Safety Class (RISC)-1, RISC-2, RISC-3, and RISC-4 structures, systems, and components (SSCs) using: Probabilistic Risk Assessment (PRA) models to evaluate risk associated with internal events, internal flooding, internal fire, and seismic; the shutdown safety assessment process to assess shutdown risk; the Arkansas Nuclear One, Unit 2 (ANO-2) passive categorization method to assess passive component risk for Class 2 and Class 3 SSCs and their associated supports; and the results of non-PRA evaluations that are based on a screening of other external hazards using the external hazard screening significance process identified in ASME/ANS PRA Standard RA-Sa-2009; as specified in license amendment [NUMBER] dated
[DATE].
Prior NRC approval, under 10 CFR 50.90, is required for a change to the categorization process specified above (e.g.,
change from a seismic margins approach to a seismic probabilistic risk assessment approach).
[NUMBER] APS will complete the implementation items listed in the Prior to implementation of Enclosure of APS letter 102-07546, dated July 19, 2017, to 10 CFR 50.69.
the NRC and in Attachment 1, Table 1-1 of APS letter 102-07690, dated May 8, 2018, prior to implementation of 10 CFR 50.69. All issues identified in the enclosure will be addressed and any associated changes will be made, focused scope peer reviews will be performed on changes that are PRA upgrades as defined in the PRA standard (ASME/ANS RA-Sa-2009, as endorsed by RG 1.200, Revision 2), and any findings will be resolved and reflected in the PRA of record prior to implementation of the 10 CFR 50.69 categorization process.