Summary of the Category 1 Public Teleconference with NuScale Power, LLC - Meeting to Discuss the NuScale Power Initial Test Program Review
ML18157A255
Person / Time
Site: NuScale
Issue date: 06/14/2018
From: Gregory Cranston
NRC/NRO/DNRL/LB1
To: Samson Lee
NRC/NRO/DNRL/LB1
Cranston G / 415-0546
References
Download: ML18157A255 (5)


Text

June 14, 2018 MEMORANDUM TO: Samuel S. Lee, Chief Licensing Branch 1 Division of Licensing, Siting, and Environment Analysis Office of New Reactors FROM: Gregory Cranston, Senior Project Manager /RA/

Licensing Branch 1 Division of Licensing, Siting, and Environment Analysis Office of New Reactors

SUBJECT:

SUMMARY

OF THE MAY 23, 2018, CATEGORY 1 PUBLIC TELECONFERENCE WITH NUSCALE POWER, LLC - MEETING TO DISCUSS THE NUSCALE POWER INITIAL TEST PROGRAM REVIEW The U.S. Nuclear Regulatory Commission (NRC) staff held a Category 1, public teleconference with NuScale Power, LLC (NuScale) on May 23, 2018, to clarify the review approach to the NuScale Final Safety Analysis Report Section 14.2, Initial Plant Test Program, that incorporates a risk-informed approach to the NuScale design.

The public meeting notice can be found in the Agencywide Documents Access and Management Systems under Accession No. ML18141A656. This meeting notice was also posted on the NRC public Website.

The meeting summary, agenda and list of participants can be found in Enclosures 1, 2, and 3, respectively.

No comments from members of the public were received.

Docket No.52-048

Enclosures:

1. Meeting Summary
2. Agenda
3. Attendees CONTACT: Gregory Cranston, NRO/DLSE 301-415-0546

SUBJECT:

SUMMARY

OF THE MAY 23, 2018, CATEGORY 1 PUBLIC TELECONFERENCE WITH NUSCALE POWER, LLC - MEETING TO DISCUSS THE NUSCALE POWER, LLC, INITIAL TEST PROGRAM REVIEW DATED: June 14, 2018 DISTRIBUTION:

PUBLIC SLee, NRO GCranston, NRO PChowdhury, NRO ABradford, NRO ACampbell, NRO RTaylor, NRO TMcGinty, NRO PKrohn, NRO RidsNroDnrlLb1 RidsNroDnrl RidsAcrsAcnwMailCenter RidsOgcMailCenter NuScale DC Listserv ADAMS Accession No.: ML18157A255 *via email NRC-001 OFFICE NRO/DLSE/LB1: PM NRO/DLSE/LB1: LA* NRO/DCIP/QVIB3: BC*

NAME GCranston MMoore KKavanagh DATE 6/14/18 6/13/18 6/13/18

U.S. NUCLEAR REGULATORY COMMISSION

SUMMARY

OF THE MAY 23, 2018, PUBLIC TELECONFERENCE MEETING WITH NUSCALE POWER, LLC, REGARDING THE NUSCALE INITIAL TEST PROGRAM The purpose of the teleconference was to introduce the U.S. Nuclear Regulatory Commissions (NRC) proposed initial test program review.

The NRC staff started the call with a brief discussion of the memo dated March 27, 2018, entiled Review Approach and Expectations for the NuScale Power, LLC (NuScale), Initial Test Program (Agencywide Documents Access and Management Systems (ADAMS) Accession No. ML18074A124) from Tim McGinty, Director Division of Construction Inspection and Operational Programs, Office of New Reactors (NRO) , to the NRC technical staff and provided a status of branch responses as required by the May 15, 2018, due date. This review approach is also discussed in the memo dated March 7, 2018, entitled Proposed Pilot Approach for the NuScale Power, LLC, Initial Test Program Review, (ADAMS Accession No. ML18060A298) from Tim McGinty to Frank Akstulewicz, NRO, Director of New Reactor Licensing.

NuScale had no questions on the approach that the NRC staff was taking as described in the memo. The NRC staff discussed some additional issues with NuScale so that they had an idea of where additional or new testing may be needed. These areas included the Low Temperature Overpressure Protection (LTOP) system, Title 10 of Code of Federal Regulations (CFR), Part 50, Appendix J, Integrated Leakage Rate Testing, and the reactor coolant system.

NuScale requested information regarding which test abstracts the NRC staff would be reviewing as part of the design certification (DC) application. The NRC staff informed NuScale that identification of the specific test abstracts is part of the second review scope described in the March 27, 2018, memo and that NRC should have that information for NuScale no later than June 29, 2018. The NRC staff plans to have another public meeting with NuScale in July 2018 to discuss any remaining outstanding issues with the test abstracts that were reviewed by the staff.

The next topic of the meeting was a high level discussion of NuScales options as it pertains to the test abstracts that will not be reviewed by the NRC staff during the DC application review, i.e., information can be removed from the final safety analysis report (FSAR) or as the NRC staff writes the final safety evaluation report (FSER) and rule limiting the finality to only the test abstracts reviewed. Since NuScale did not have their General Counsel present for the call, they requested another public meeting to discuss this topic.

NuScale also wanted to know what was driving the change to the review. The NRC staff stated that the review of FSAR Chapter 14.2 Initial Plant Test Program, requires the services of the same technical staff that review the technical chapters and that they need to complete the technical chapters prior to focusing on initial test program (ITP). The NRC staff reminded NuScale that the regulations for a DC do not require an ITP, whereas the regulations for a combined license (COL) require an ITP. The NRC staff stated that it looked like the information provided in the FSAR would require significant requests for additional information to resolve the missing information consistent with standard review plan (SRP) Section 14.2 and that the revised approach would maintain the current review schedule.

1 Enclosure 1

There were no questions or comments from the members of the public.

U.S. NUCLEAR REGULATORY COMMISSION

SUMMARY

OF THE MAY 23, 2018, TELECONFERENCE WITH NUSCALE POWER, LLC MEETING AGENDA Meeting Introductions NRC/NuScale 11:00 - 11:10 General Discussions Regarding the NuScale NRC/NuScale 11:10 - 11:55 Initial Test Program Questions and Comments NRC/NuScale/Public 11:55 - 12:00 1

Enclosure 2

U.S. NUCLEAR REGULATORY COMMISSION

SUMMARY

OF THE MAY 23, 2018, TELECONFERENCE WITH NUSCALE POWER, LLC LIST OF ATTENDEES NuScale Power, LLC Spain Abney Carl Dumsday Edan Engstrom Chris Maxwell Steve Mirsky Steve Pope U.S. Nuclear Regulatory Commission Staff Kerri Kavanagh Paul Prescott Clinton Ashley Aaron Armstrong Olivia Mikula, Office of the General Counsel Members of the Public Adrian Fletcher, Westinghouse Bob Fuld, Westinghouse Enclosure 3