Summary of Owners Groups Meetings on the New Standard Technical Specifications: March 18 & 19, 1992
ML18157A019
Person / Time
Issue date: 04/06/1992
From: Charemagne Grimes
Office of Nuclear Reactor Regulation
To: Rossi C
Office of Nuclear Reactor Regulation
References
Download: ML18157A019 (13)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20!ll55 April 6, 1992 MEMORANDUM FOR:

Charles E. Rossi, Director FROM:

Division of Operational Events Assessment, NRR Christopher I. Grimes, Chief Technical Specifications Branch Division of Operational Events Assessment, NRR RECEIVED APR 1 3 t!

SUBJECT:

SUMMARY

OF OWNERS GROUPS MEETINGS ON THE NEW STANDARD TECHNICAL SPECIFICATIONS:

MARCH 18 & 19, 1992 On March 18, 1992, the Technical Specifications Branch met with the Owners Groups, and on.March 19, 1992, the owners Groups Executives met with NRR senior management to discuss the status of.activities for resolving comments on the draft standard technical specifications (STS) and related matters. The meeting attendees are liste_d in Enclosures 1 and 2, respectively.

There was no formal agenda for the staff's meeting with the Owners Groups on March 18, 1992; the purpose of the meeting was to discuss the status of the schedule, action assignments, and the Executive agenda. The Owners presented an updated activity schedule (Enclosure 3.).

Bob Tjader indicated that the staff had proposed a note to be added for the control rod movability surveillance requirement to clarify operability considerations (movabfl ity as an indicator of "trippabil ity") for the surveiltance and the application of SR 3.0.1 to trippability, as described in the condition for the control rod LCO.

NRR management previously concluded during the meeting on February 5, 1992, that trippab1l ity is the attribute of importance for the control rod safety function. However, the application of this concept appeared to conflict with SR 3~0.1, which states:

11Fa1lure to meet a Surveillance, whether such failure is experienced during performance of the Surveillance or between performances of the Surveillance, shall be -failure to meet the LCo.*

The owners Groups concluded that there was no need for any. clarification. The Owners contend that the relationship between operability and trippability will be adequately explained in the Bases for Section 3.1 of the STS, to the extent that there 1s no need to change OPERABLE in the body of the limiting condition to read "trippable." Further, the owners indicated that, in the event that a control rod is immovable at the time the surveillance is due, the failure would have to be corrected so that the surveillance (movement) could be performed within the 25% allowance for the surveillance interval.

The Owners Groups' explanation of operability considerations for control rods caused a tumultuous response from the staff. Particularly, the staff expressed concern that the control rods are not particularly different than other safety systems that may have non-safety functions or capabilities that also must be considered relative to "operability" of particular systems. The

- 2

  • April 6, 1992 staff also expressed concern that the Owners Groups'.rationalization of the need to restore the "non-safety" function 1n order to perform the surveillance fundamentally violates long-standing principles and interpretations applied to operability and surveillances for technical specifications. The staff also expressed concern over the precedent that this particular position would have*

on the recently issued guidance on degraded conditions and operability, and potential future ramifications. for more extensive divisions between safety and non-safety functions.

During the discussion that. ensued, the staff and Owners discussed a variety of implications. and analogies to characterize the relationships between operability and safety function, and between surveillance results and.

operability determinations to grapple with this issue. These protracted discussions primarily involved different views regarding language meaning*and consistency and did. not appear to disclose any new insights into the safety fun~tions of control rods. Consequently, I concluded that the staff's concerns involved language preferences, irrespective of the potential for misuse or abuse of this position as a demonstration of the relationship between operability and safety function with respect to broader technical specification policies. On this basis, I concluded that OTSB will defer to*

the Owners Groups choice of language for control rod operability and Bases, provided that their proposed language is technically accurate.

(

The B&W Owners indicated that, although the generic concerns regarding pressure isolation valves (PIVs) had been addressed during the meeting on March 16, 1992, there are unique design. considerations for B&W plants which make the resolution of the PIV issues untenable for them. I requested that the B&W Owners submit. a written appeal to ensure that staff can focus its limited resources* in this area to the B&W-spec1.f1c concerns.

Chris Hoxie indicated that an action item for Section 1.0 concerning the definition of pressure boundary LEAKAGE had been overlooked. The Owners had agreed to develop a clarification for. the Bases to resolve the issue rais~d in Section 1.0. While the clarification effects several sections, the Owners had proposed to incorporate the additional Bases material in Section 3.4 for the Reactor Coolant System. Mr. Hoxie will coordinate with Ms. Weston to incorporate an appropriate clarif;cation.

Carl. Schulten similarly indicated that a new issue evolved from the resolution of issues for Section 3.3; the issue involves consistency in the manner by which the potential.for positive reactivity changes are treated in the Applicability provisions for Sections 3.3, 3.4 and 3.7. The Owners agreed to evaluate the concern and develop a means to achieve consistency between the

  • three sections that would allow appropriate latitude for normal maneuvers, with appropriate c~nstraints for Applicability considerations.

Mag Weston indicated that the BWR Owners had submitted proposed changes for Section 3.9.6 (Enclosure 4) which had been previously rejected because of a lack of technical basis to incorporate the changes. The BWR OWners indicated that they believe that the proposed changes, which would distinguish the limitations on handling irradiated fuel from those for new fuel or control rods. I indicated that (1) the proof and review version of Section 3.9 had April 6, 1992 just.been issued, and I did not believe that this issue warranted pulling the.

sect1on back for such a change, and (2) I had previously concluded that additional technical support would be necessary to clarify the appropriate constraints. Consequently, I concluded that, if technical resources are available, OTSB would arrange for a technical clarification of this issue and incorporate any acceptable changes into the June issuance of the completed STS*

for proof and review.

I also noted that, in a meeting on February 24, 1992, the SICB staff had informed the Owners Groups that all of the open issues related to B&W's topical report on "indefinite channel bypassa had been resolved; however, before OTSB could incorporate conforming changes to Section 3.3, we needed to have the staff's safety evaluation report (SER) to clearly understand the extent of the changes and provide the techn1ca1 justification for the changes.

However, because of resource constraints, OTSB*had committed to assist SICB in the preparation of the SER, which would detract from the time available for us to resolve all of the*other changes to the STS. Accordingly, I concluded that the changes to incorporate u1ndef1nite ch~nnel bypass" for both CE and B&W plants would have to be deferred to preclude broader impacts on the comment resolution schedule..

OTSB will incorporate these changes at the earliest possible time after the SER has been approved, hopefully before June l992.

The resulting updated list of STS action items is included as Enclosure 5.

The Executive meeting was held on March 19, 1992; the meeting agenda is presented in Enclosure 6. I described the status of the schedule

  • (Enclosure 7) and the Executive's priority issues (Enclosure 8). I indicated that Section 3.9 had been issued on March 16, 1992, and there continues to be agonizing but steady progress. I also indicated that the staff has only had limited experience with the complete edit cycle, but I believed.that process improvements would continue as they had with the editorial panel reviews.

All of the Executive Priority Issues have been resolved, except for the four items that are outside the scope of the comment resolution process (Enclosure 8). I described the resource/priority issu~ assDciated with the topical report review. described above, and committed to address the issue at the earliest possible time our resources permit; nevertheless, this issue can still be resolved during implementation, as well. I noted that a similar resource/priority constraint has delayed the preparation of a line-item improvement for diesel testing requirements.

OTSB needs to resolve the testing issues in Section 3.8 to provide the model specifications that would accompany the generic action. Subsequently, we would present the proposed action to the CRGR, and their schedules have been delayed by the President's request for a regulatory review.

The appeal on the staff's position for alternate/dedicated and remote shutdown equipment was presented to NRR. management and the Executives, as sunvnarized in. The staff's and Owners Groups' written positions on this issue had previously been distributed, and are included as Enclosure 10 for completeness. I summarized the staff's position along the following points:

  • It was the staff's intent in Generic Letter BB-12, to implement the April.6, 1992 Commissions' interim policy on technical specification improvements in such a way as to retain the equipment relied*upon for post-fire safe plant shutdown ;n the limiting conditions for operation (as defined by Generic Letter 81-12), even though these generic requirements have not been implemented consistently.
  • The inclusion of this equipment in the technical specifications is consistent with ncriterion 4" of the policy (rislt significance), because fires inside or outside the control room can be a significant contributor to core*damage frequency, and this equipment is necessary to ensure safe shutdown capability.

The owners Groups position was su1M1arized as follows:

  • Although the need for these safe shutdown capabilities in the plant design is clear, these features are an integral part of a larger program for fire protection, and are not otherwise required to be in technical specifications according to the applicable regulations (GDC 19 or Appendix R).
  • Some of these safe shutdown capabilities~ be important to risk, but that depends on widely varying plant-specific vulnerabilities. Not all of the safe shutdown capabilities are primary success paths to mitigate dominant accident sequences. The extent of importance to risk will be established as part of lPEEE.
  • Only four plants have technical specifications for the full complement of post-fire safe shutdown equipment. All of the other plants have maintained the safe shutdown equipment (except for the Remote Shutdown.

Panel) as part of their Fire Protection Program; the NRC has inspected these progra~s and found them acceptable.

  • The full complement of post-fire safe shutdown equipment is extensive; listings of the equipment can range from 30 to 50 pages. Such a scope of equipment would be cumbersome in the t,chnical specifications.

The Owners Executives indicated that the administrative controls for the Fire Protection Program in Section 5.0 of the new STS could be expanded to more clearly address the equipment for the post-fire dedicated, alternate, and remote shutdown capabilities. Further, the Owners Executives indicated that it was not their intention to remove the limiting conditions for the remote shutdown panel. However, all of the other post-fire safe shutdown equipment has been adequately maintained under these programs and, therefore, the Owners Groups do not believe that broader Technical Specification controls are necessary.

Mr R11s~eJJ coocJuded that, if on]y four plants have the full complement of post-fire safe shutdown equipment in the technical Specifications. then it would be inappropriate to attempt to incorporate broader requirements into the new sis.. beyond the remote shutdown capabjli.ty, However, Mr. Russell also indicated that the staff should pursue this matter as a potential backfit, if necessary, to resolve the consistency of control for post-fire safe shutdown April 6, 1992 equipment.

He noted that additional requirements for hot shutdown capability will likely evolve from the Shutdown Risk Study because of the particular significance of fire as dominant contributors to shutdown risks.

Consequently, in the long term, additional limiting conditions may ~ave to be imposed for all plants to ensure adequate safe shutdown capability for fire events.

The Executives indicated that the next meeting should address measures of effectiveness and implementation issues, because those issues were raised by the Conunission. In particular, the Executives requested that we resolve the need for renotici~g of the license amendments for STS conversions. Dr. Murley indicated that whether or not hearings will be required,. before or after conversion to.the new STS, will depend on the quality of the significant hazards considerations, and the extent to which the utilities application tries ta accumulate changes beyond the scope of the STS conversion.

  • I suggested that founding the STS thrDugh rulemaking be considered as one of the alternative approaches. Dr. Murley and Mr. Russell encouraged the sta.ff. and Owners Groups to be open-minded* and innovative, and requested that the staff and owners Groups develop a generic-conversion process that could serve as a framework for the evolution of more detailed practices.

The ne~t Executive meeting 1s scheduled for April 23, 1992.

Enclosures:

As stated cc:. T. Murley

w. Russell L. Bush, OG

~w. Hall, NUMARC R. Tworek, MEREX

/'.-;-QJ.

\\.......J.-

M L WA.

Christop er I. Grimes; Chief Technical Specifications Branch

.. Division of Operational Events Assessment, NRR

SUMMARY

Staff Position:

The NRC Staff has concluded that the Standard Technical Specifications (STS) should include alternate/dedicated shutdown equipment provided for the design to comply with the requirements of Appendix R and remote shutdown capability of GDC 19. "... fires (either inside or outside the control room) can be a significant contributor to the core melt frequency... the [remote shutdown] instrumentation meets the Policy Statement Criteria, based on risk."

Industry Position:

The ~C Stqff's position that the Standard Tecl,nical Spectfications (STSJ should include alternate/dedicated and remote shutdown equipment provided to comply with the requirements of Appendix R appears to consider post-fire sqfe shutdown equipment as a stand-alone component of the plant's fire protection program. While it is acknowledged that fires are a significant contributor In probabilistic risk assessmenis, these risk assessments are not generally driven by fires in the control room because the control room is continuously. manned. The-Stqffs position fails to recognize the Integral role of the post-fire safe shutdown equipment within the fire protection program and the limited role of the alternate/dedicated.

and remote shutdown panels.

Both the Branch Technical Position CMEB 9.5-1, "Guidelines for Fire Protection for Nuclear Power Plants" and Appendix R to 10 CFR. 50, "Fire Protection for Nuclear Power Facilit_ies Operating.prior to January*

1, 1979," describe the means for ensuring a sqfe shutdown capability.

Bastcaily, four means are provided for ensuring a post-jlre sqfe shutdown capability: 1) Separatio71 by a fire barrier. having a 3-hour rating: 2)

Separation by a horizontal distance of more than 20 feet with protection fromjire detectors and an automatic fire suppression system: JJ Enclosure

. In afire barrier having a 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> rating wlthprotectionfrom.fire detectors and an automaticfire suppression system,* and 4) Providing an altemative or dedicated shutdown capability with p,:otection from fire detector and a fixed fire suppression system (Appendix R only). The cold shutdown portion of the sqfe shutdown capability also has the option of allowing post-fire repairs to ensure the Sf!./e shutdown capabiUty. Each of the means for ensuring a post-fire safe*shutdown capability are integrated with various fire protection features

  • Including barriers, detectors and suppression.

The Industry believes the alternate/dedicated* and remote sh~

equipment is an integral part of the overall fire protection program and that the overall fire protection program is adequately addressed by licensee fire protection programs.

S~ff Position:

It is the *staff position that the criteria governing the design of plant safe shutdown capability from outside the control* ro~m are 10 c~ 50 Appendix A, GDC 19 and 10 CFR 50 Appendix R. The Staff position for technical specifications to meet the post-fire safe shutdown capability of Appendix R was provided through a series of.Generic Letters. (GL) beginning with GL 81-12, "Fire Protection Rule" (February *20, 1981).

This was further supported by the issuance-of Generic Letters 86-10 and 88-12.

Industry Position:

While the Industry agrees that criteria governing the design of plant sqfe shutdown capability from outside the control room are 10 CFR 50 Appendix A, GDG 19 and 10 GFR 50 Appendix R, the Industry does not agree that these requirements have to be in the Technical Specifications to ensure that they* are met. Neither GDC 19 or Appendix R directly require Technical Specifications. GDC 19 does not require redundant.

equipment to perform this junction and Appendix R does not require redundant or safety relat_ed equipment and states, '!The shutdown capability for specific fire areas may be unique for each such area, or it may be one unique combination of systems for all such areas". Both GDG

  • 19 and Appendix R recognize _ihe need for procedure"S to implement the capability for shutdown outside* the control room. And w,iile the Stqff points to their issuance of GL
  • 81-12, GL 86-10 and GL 88-12 to demonstrate their requirement for Technical Specifications, the reality is that the Industry has not been required to include Technical Specifications and has demonstrated t~ ability to adequately address these requirements :

through licensee controlled programs. The history and some backgrowul around the Stqffs actions are as follows:

  • The Standard Technical Specificadons (STS) prior to and qfter GL 81-12 did not include TS required as designated in GI.t. 81-12 The technical Staff (then the Chemical Engineering Branch) had attempted to convince NRG management that the* S1'S and plants in the NTOL process shoukl.

include TS as required in GL 81-12 and that NRC management stated this position was inappropriate at that time due to the following:

1.

Not all plants were Appendix R plants and the reviews were d{fferem in

~cope.

2.

The NRG was still a/tempting to resolve the Appendix R issue and the NRC regr1latory position.

3.

. The STS and NTOL plants include Remote Shutdown System TS to cover

  • the GDG 19 habitability c,oncerns.

i

1.

I The NRC changed its philosophy and require'!'ents in late 1982, that fire protection related systems should !1!11 require plant shu~own - the STS was changed accordingly.

The issuance of GL 86-lO*and the NRC philosophy that fire protection related systems should and cou'/tl be adequately controlled procedurally and under a 50.59 review

  • process.

The. issuance of GL 88-12 which was a clarification. of GL 86-10 and additional information.gainedfrom those plants Implementing the requii'emenJs of GL 86-10 and GL 88-12 stated that the NRC approved Fire Protection Program must.be incorporated in the FSAR and defined the NRC approved Fir~ Protection Program as :.... includes theflre protection and post-jire sqfe shutdown systems necessary to satiefy NRC guidelines and requirements **** "

The Technical Specf/lcation Improvement Program (J'SIP), which ~luded the..

Commission Interim Policy Statement (JPS, February, 1987) criteria, established those items that slwuld be included in the Technical Specifications and tlwse items which could '

be relocated and controlled by the licensee. This criteria did not idenlffJ fire protection or Appendtx R Safe Shutdown related TS as being those.meeting the criteria for Inclusion*

in the Technical Specifications.

Very few STS plants presently have TS on Appendix R Sqfe Shutdown Equipment (most STS plants have Remote Shutdown GDC 19 requirements) and the vast majority of custom TS nlants have neither - only a han4ful of custom TS plants. have Appendix R Sqfe Shutdown Equipment TS, such as Montic_ello and DC Cook, and these plants were individually. required to Include these TS.

Browns Ferry was able to demonstrate to the Stqff the acceptabl,lty of controlling Appendix R Sqfe Shutdown Eq1fipment programmatically outside of the Technical Specijic~ons in 1989.

Staff Position:

The list of instrumentation and equipment not already addressed in the Technical Specifications which would be included to meet the alternate/dedicated shutdown equipm.ent is small. *

. Industry Position:

The Appendix R alternat~ and dedicated shutdown capability section states "The shutdown capability for specific fire areas may be unique for each such area, or it may be one unique combination of systems for all such areas. Procedures shall be in effect to implement this capability". There are a multitude of varied scenario~ which could present themselves where an.y number of.alternate capabilities could be used to satiefy the sqfe

.shu(downfunction~ A representative list of equipp,entfrom San Onofre is attached. This list is sqfficientlj large to demonstrate that if these systems were In the Technical Specifications, there would be a severe limit placed

on the licensee as to which subset of systems could be used in different scenarios. And with an LCO and a co"esponding Completion Time, the licensee would be required to seek fomral relief from the NRC for

  • continired operation where the level of degradation does not impair at all the capability for alternate sqfe shUldown In the event of a fire.

The Industry shares the NRC's concern for ensuring that alternative and dedicated shutdown capability in the event of a fire inside or outside the control room be maintained. The Industry believes that it has demonstrated the capability over the past 12 years to ensure this capability is maintained through programs and procedures which address the e~tire fire protection *measures

  • spectrum. These programs provide requirements for periodic testing and actions for impairment

. of these equipment. These programs have and continue tq* be the subject of NRC review and audit.

The Industry does not believe that the NRC or the Industry. stand to gain any improvement in safety by requiring these systems in the Improved Technical Specificati.ons after there has been 12 years of experience which. indicates that this equipment can be adequately controlled through license programs and procedures.

RESPONSE TO NRR STAFF POSXTION ON TECHNICAL SPECIFlCA TIONS FOR ALTERNATE/DEDICATED AND REMOTE SHUTDOWN' EQUIPi\\-lE:.°'i""l' TO COMPLY WITH THE REQUmEMENTS OF APPENDIX R SUi\\,[l\\,fARY The NRC Stafrs position that the S~andard Technical Specifications (STS)

  • should include alternate/dedicated and remote shutdown equipment provided to comply with.the. requirements of Appendi.'t R appears to consider post-fire safe shutdown equipment as a stand-alone component of the plant's fire protection program *. The Starrs position fails to ~ognize the integral role of the post-tire safe shutdown equipment within the fire protettion program and the

'limited role of *the alternate/dedicated and remote shutdown panels. In addition, the Stafrs

  • ,position on alternate/dedicated and remote shutdown equipment is ipi:onsi.stent with* the guidance provided by Generic* Letter 88-12 regarding removal of the fire protection requirements from the Technical Specifications.
  • Further, it is recommended ti.lat Appendix R post-fire ~

shutdown requirements not be given consideration in establishi~g the requirements for the Improved Standard*Technical Specifications.

DISCUSSION It appears that the basis for the Staff position centers on the Staff's statements that "Probabilistic risk assessments have generally confirmed that fires are a major contributor to core damage*

events" and that "Because fire (either inside or outside the control room) can be a significant contributor to the core melt frequency and because uncertainties with fire initiation frequency can be signit1cant.

11 While it i~ acknowledged that fires are a' significant contributor in probabilistic risk assessments, these risk assessments.are not generally driven by fires in the control room because the control room is continuously manned. Also, the Staff position offers no evidence that the proposed Technical Specifications would reduce the risk from f1res.

Technical Specifications may not necessarily improve the reliability of equipment in risk assessments when factors such as testing and failure to return equipment to service are considered. Also, the remote shutdown panels have such a limited role in the post-fire safe shutdown capabiiity, improvement in the reliability of this equipment may have no impact on the risk assessments.

2/19/92

Both the:: Branch T.c:chnical Position CMEB 9.5-1, "Guidelines for Fire Protection for Nuclear Power Plants;, am.I° Appenc!ix R to 10 CFR 50, "Fire Protection for Nuclear Po\\1,.*er Facilities Operating_ prior to fanuarJ 1, 1979," describe the m~:lllS for ensuring a safe shutdown capability.

Basically, four me:uis

  • are provided* for ensuring a post-fire safe shutdown capability: -1)

S~paration by a fire barrier having a 3-hour rating; 2) Separatio*n by a horizont:l..l distµice of more than 70 feet with protection from.fire detectors and an automatfo fire suppression system;

3) Enclosure in a fire barrier having a 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> rating wi~ protection from fire detectors and an automatic fire suppression system; and 4) Providing an alternative or dedicated shutdown capability with protection from fire detector and a fixed fire suppression system (Apperidix R only). The cold shutdown portion of the safe shutdown capability also has the option of allowing post-fire repairs to. ensure the safe shutdown* capability. Each.of the means for ensuring a post-fire safe
  • shutdown capability are integrated with various fire. pro.tection features including barriers, detectors and suppression. Even the alternate and dedicated shutdown per Appendix R requires detection and suppression and fire barriers to achieve physical independence. In the event of a "design basis" fire, the reliability of the post-fire shutdown equipment will be-immaterial if the fire protection measures fail.

In ensuring a post-fire.safe shutdown capability, most plant areas ar.e:protected by either separation by a 3-hour fire rated banier, separation by more than 20 feet, or 1.. hour fire rated enclosures. Alternate and dedicated shutdown capability is gen~rally limited to the control room,

  • cable spreading room and one or two other f'jre areas. For plant areas not utilizing alternate and dedicated shutdown, Appendix R and the Branch Technical Position does not require that safe shutdown be limited to equipment covered by Technical Specification. And, Generic Letter 88-

. 12 recommends remov~ of these fire protection ~easures from the Technical Specifications.

With respect to safe shutdown eq~ipment, most, if not all; major equipment used for post..;..fire safe -shutdown is covered by current Technical Specifications.. But, the same may not be true of the controls and indication used for these plant areas. For example, a typical PWR has several channels of steam generator level, both wide range and narrow range, all of which are not covered by Technical Specifications. Only one channel of steam generator level, preferably wide range, needs to be protected to ensure *a post-fire safe shutdown capability. Similar conditions exist with the ~iagnostic instrumentation especially when local instrumentation is used.

For controls, not all flow paths of a system are covered by Technical Specifications. Systems such as eves may rely upon a flow path that is not covered by Technical Specifications. Also, manual operation of valves is utilized as part of most post-fire shutdown capabilities. Very seldom is the capability to manually operate a motor, air or solenoid-oper:i.ted valve included in the Technical Specifications. The Staff has not proposed that the balance of the post-fire shutdown capability be added to Technical Specifications. Thus, not all the equipment us~ for fires outside the control room would be included in Technicll Specifications.

2/ 19/92"

.-\\s the St~ff accurately pointed out, the post-fire shutdown -capability for the control room has "little tlexibilit.* minimal diversity, and generally no redundancy". i'.fiQ.we~not note.that the ame are true of most !ant.areas and the control room has the adclifioMl enefit of continuous manning not found in other pl:i.nt areas. Further, b.oth Appendix Rand the Branch Technical Position provide quite a bit of latitude.in the design of alternate/dedicated and remote capabilities. On one side ef the spectrum, an alternate/dedicated shutdown capability could consist of one panel that. provides complete control and indication of the post-fire shutdown capability. The other end of the spectrum would be an alternate/dedicated shutdown c:i.pability that has the instrumentation spread out. in se'leral *different locations with controls being performed manually at the equipment. The actual alternate and dedicated designs are spread between the two extremes. Generally, alternate/dedicated capabilities rely upon the coordination of two operators at different panels (for e.umple: remote shutdown panel and a local diesel generator panel) supplemented by tw~ to four operators performing manual actions*

throughout the plant. As proposed, the Staff positi.on would result in *a greater Technical Specification impact on the plant designs that *are closer to the one panel capability. The proposed position does not address manual operation of equipment nor does it address communication equipment and emergency lighting.

From a risk assessment viewpoint, improvements to the reliability of remote shutdown panels may v,ery well be insignificant when the post-fire shutdown capability is dependent upon manual operations performed tinder adverse conditions.

As a side note the proposed position does not address the instrumentation required by IE

'.µtformation Notice 84-09 and does not address support equipment such as 'HV AC. Also the position is silent en the need to incll!de that equipment which

  • provides pro~tion from tire induced failures of associated circuits.

Finally, while the Staffhas been consistent in their issuance of generic letters, the Staff has not b~n consistent in. implementation. To *date only a few plai:its have implemented Technical Specifications for alternate/dedicated shutdown equipment and the Technical Specifications that have been issued address only ~ portion of the post-fire safe shutdown equipment. In response to Generic Letter 81-12, only a few licensees proposed Technical Specifications. At that time, the Staff was advising licensees to defer Technical Specifications until the Staff could formulate a position. Most of the original SER' s written for Appendix R avoided the issue of Technical Specifications. Given that the Staff has allowed many of the plants to operate 4 to 5 years with some 8 to 9 years to complete modifications related to Appendix R and has allowed a majority of the plants to operate until now, 10 years after Appendix R was issued, without the proposed*

Technical Specifications, what risk is being addressed by the Stafrs proposed position?

Appendix R did not directly require that the post-fire alternate/dedicated shutdown equipment be covered by Technical Specifications. Also, since Appendix R permitted use of non-safety related equipm~nt, the Appendix R -requirements, in a sense, recognized that the \\

alternate/dedicated equipment being added to the plants' capabilities may not be covered by Technical Specifications. With the improvement in plant safety achieved by the post-fire safe shutd.own capabilities, the improvement gained from Technical Specifications may very well be

  • insignificant.

2/19/92

CONCLUSION In summary, the control room fire scenario fs generally not the driver in fire *risk assessments.

Technical Specifications do not necessarily (in risk asse.ssments) improve the reliability of equipment and thereby I reduce risk. And, the weaknesses in post-fire safe shutdown capabilities

  • (multiple manual actions perfonned under adverse conditions) ar~ not addressed by the proposed position. The* proposed Technical Specifications appear inconsistent with decisions behind.

Generic Letter 88-12 for removal of the fire protection requirements from the Technical Specifications. The proposed position is incomplete in its attempt at reducing the risk from f'ires. And the industry may be better served if the entire safe shutdown equipment from m~ual'

. operation of valves to repair equipment and emergency lighting and communication equip~ent is included in an administrative program along with the fire prptection measures, like those in the plants which have implemented GL'86-10 and GI 88-12 *

\\

2/19/92