ML18153D134
| ML18153D134 | |
| Person / Time | |
|---|---|
| Site: | Surry, North Anna |
| Issue date: | 09/18/1992 |
| From: | Stewart W VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.) |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| References | |
| 92-448, 92-449, GL-88-20, NUDOCS 9209250264 | |
| Download: ML18153D134 (5) | |
Text
e e
VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 September 18, 1992 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D. C. 20555 Gentlemen:
VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 Serial No.
NL&P/CGL Docket Nos.
92-448/449 R1 50-280 50-281 50-338 50-339 License Nos. DPR-32 DPR-37 NPF-4 NPF-7 NORTH ANNA POWER STATION UNITS 1 AND 2 SCHEDULE FOR GENERIC LETTER 88-20 SUPPLEMENT 4 INDIVIDUAL PLANT EXAMINATION OF EXTERNAL EVENTS FOR SEVERE ACCIDENT VULNERABILITIES Virginia Electric and Power Company responded to Generic Letter (GL) 88-20 Supplement 4, "Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities," by a December 20, 1991 letter (Serial No.91-410). The IPEEE program planned for Surry and North Anna Power Stations was presented in that letter and remains the same.
On June 24, 1992 and June 26, 1992, the NRC requested identification of our IPEEE submittal schedule for Surry and North Anna, respectively, by September 18, 1992.
These N RC letters also requested justification if the requested submittal date of June 1994 from GL 88-20 Supplement 4 is not going to be satisfied. This letter provides our planned IPEEE submittal schedule, along with justification for the schedule.
Internal Fire Analyses The fire PRAs for Surry and North Anna will be performed in a staggered fashion.
Because the North Anna Individual Plant Examination (IPE) is nearing completion, we intend to perform the fire analysis for this station immediately upon completion of its IPE.
The Surry IPE was submitted to the NRC on August 30, 1991 (Serial No. 91-134A). A review of design changes made since the preparation of the Surry IPE and an upgrade of the model, as required, are necessary. The Surry IPE model upgrade will 9209250264 920918 PDR ADOCK 05000280 P
PDR 240014
be* performed in parallel with the North Anna fire PRA. The Surry fire PRA will begin after the model upgrade has been completed.
The schedule and milestones for the fire analyses are as follows:
Milestone North Anna Surry Fire Project Plan 01/29/93 06/30/93 Surry IPE Model Upgrade N/A 10/29/93 Fire Induced Vulnerability Evaluation 05/28/93 01/14/94 (FIVE) Phases I and II FIVE Phases 111 and IV 11/19/93 04/29/94 Draft Report 02/15/94 06/30/94 Report Submittal to NRC 06/30/94 12/17/94 High Winds, Floods, Transportation and Nearby Facility Accidents The evaluation of these external events will be conducted in parallel with the fire analyses for each station. The schedule and milestones are as follows:
Milestone North Anna
~
External Events Project Plan 01/31/93 07/31/93 Review of Licensing Basis 03/31/93 08/31/93 Bounding Analyses 05/31/93 01/31/94 PRA (if needed) 10/31/93 03/31/94 Draft Report 02/15/94 06/30/94 Report Submittal to NRC 06/30/94 12/17/94 Seismic Analyses As previously indicated, the seismic portion of the IPEEE for Surry and North Anna is being coordinated with the resolution of Unresolved Safety Issue (USI) A-46, "Seismic Qualification of Equipment in Operating Plants." Virginia Electric and Power Company has previously informed the NRC that the seismic verification plant walkdowns required to resolve USI A-46 will be completed by the second refueling outage after receipt of the final SER supplement (SSER-2). The schedule for the seismic IPEEE and USI A-46 activities is provided in our letter Serial No.92-384, dated September 18, 1992.
- The schedule for the seismic IPEEE is summarized as follows:
Milestone End of Second Refueling Outage after Issuance of SSER-2*
Seismic IPEEE Submittal to NRC North Anna
.5JJ.rol U1 -12/15/94 U1 -11/02/95 U2 - 06/13/95 U2 - 05/31 /96**
12/31 /95 11 /30/96 The plant walkdowns for the USI A-46 and seismic IPEEE programs at Surry and North Anna are expected to be completed by the identified dates, based on the current outage schedule.
- For Surry Unit 1, May 31, 1996 is the end date of the third refueling outage after receipt of Generic Letter 87-02 Supplement 1, "Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46." The justification for not completing the seismic walkdowns by the end of the second refueling outage is indicated in letter Serial No.92-384.
IPEEE Report Preparation NUREG-1407, "Procedural and Submittal Guidance for the Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities," provides IPEEE report preparation guidelines. The recommended Table of Contents indicates that a single report for external events is requested. It is our intention to submit the external event analyses except seismic as one report for each station based on the identified schedule. The seismic analysis for each station will be separately submitted based on the identified schedule.
If you have questions or require additional information, please contact us.
Very truly yours,
~\\ ~;1 --l-tJ{ l ) iS!ilJ~I ~
W. L. Stewart Senior Vice President - Nuclear
i i
cc:
U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, N. W.
Suite 2900 Atlanta, Georgia 30323 Mr. M. W. Branch NRC Senior Resident Inspector Surry Power Station Mr. M. S Lesser NRC Senior Resident Inspector North Anna Power Station Mr. W. H. Rasin NUMARC Suite 300 1776 Eye Street NW Washington, DC 20006
COMMONWEAL TH OF VIRGINIA )
)
COUNTY OF HENRICO
)
The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by W. L. Stewart who is Senior Vice President -
Nuclear, of Virginia Electric and Power Company. He is duly authorized to execute and file the foregoing document in behalf of that Company, and the statements in the document are true to the best of his knowledge and belief.
Acknowledged before me this /f 7JI day of ~1mku, 19~.
My Commission Expires:
( ~
3/
, 19~.
£.zx.~
Notary Public (SEAL)'