Informs That Util Response to NRC Bulletin 88-004, Potential Safety-Related Pump Loss, Satisfactory
ML18153C302
Person / Time
Site: Surry  Dominion icon.png
Issue date: 07/25/1990
From: Buckley B
Office of Nuclear Reactor Regulation
To: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
References
IEB-88-004, IEB-88-4, TAC-69979, TAC-69980, NUDOCS 9008010143
Download: ML18153C302 (2)


Text

July 25, 1990 e

D6ckei-~os. 50-280 and 50-281 Mr. W. L. Stewart Senior Vice President - Nuclear Virginia Electric and Power Company 5000 Dominion Blvd.

Glen Allen, Virginia 23060

Dear Mr. Stewart:

DISTRIBUTION See attached list

SUBJECT:

SURRY, UNITS 1 AND 2 - NRC BULLETIN 88-04, 11 POTENTIAL SAFETY-RELATED PUMP LOSS 11 (TAC Nos. 69979 AND 69980)

By letters dated July 11 and August 8, 1988, July 28, 1989 and June 18, 1990, you responded to NRC Bulletin 88-04, "Potential Safety-Related Pump Loss/ 1 for the Surry Power Station, Units 1 and 2.

Your response of June 18, 1990, con-firmed that the long-term actions associated with the issues in the bulletin (disassembly and inspection of one auxiliary feedwater (AFW) pump in each unit and the installation of larger minimum recirculation lines on all AFW pumps) will be completed during the end of the Cycle 10 outage for both units.

We understand that your present schedule for completion of the end-bf-Cycle 10 outages is the fourth quarter of 1990 (Unit 1) and the second quarter of 1991 (Unit 2).

In accordance with the bulletin, a written response describing the actions taken will be submitted to the NRC within 30 days of completion of the long-term actions.

You are reminded that an evaluation of your actions in re-sponse to this bulletin should be documented and maintained at the station for a minimum of 2 years.

Accordingly, your responses have addressed the issues in the bulletin, and we are closing the subject TAC numbers.

Further NRC review, if any, will be by future auditing.

cc:

See next page

~~

PM: PDII-2 BBuckley:cp 07 /25/90 Sincerely,

[Original signed by]

Bart C. Buckley, Senior Project Manager Project Directorate II-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation PM4~~1-I2 T~

I ow 01 l],,990 V o

/90

/.. -

~ *'--*.'

DISTRIBUTION:

Docket Fi le*

NRC & LPDRs PD22 Rdg File SVarga 14/E/4 Glainas 14/H/3 HBerkow BBuckley DMiller EJordan MNBB-3302 OGC ACRS(10)

MSinkule RI!

TAlexion ll/D/23 e

J