Corrected Page to Proposed Tech Specs Re Pressurizer Safety Valves
ML18153C256
Person / Time
Site: Surry  Dominion icon.png
Issue date: 06/15/1990
From:
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
Shared Package
ML18153C255 List:
References
NUDOCS 9006220032
Download: ML18153C256 (2)


Text

.i

'..r ATTACHMENT 1 SURRY POWER STATION CORRECTED PAGE FOR PROPOSED TECHNICAL SPECIFICATION CHANGE

e TS 3.1-3

e.

Reactor power shall not exceed 50% of rated power with only two pumps in operation unless the overtemperature ~T trip setpoints have been changed in accordance with Section 2.3, after which power shall not exceed 60% with the inactive loop stop valves open and 65% with the inactive loop stop valves closed.

f.

When all three pumps have been idle for > 15 minutes, the first pump shall not be started unless:

(1) a bubble exists in the pressurizer or (2) the secondary water temperature of each steam generator is less than 50°F above each of the RCS cold leg temperatures.

2.

Steam Generator A minimum of two steam generators in non-isolated loop shall be operable when the average reactor coolant temperature is greater than 350°F.

3.

Pressurizer Safety Valves

a.

Three valves shall be operable when the head is on the reactor I vessel and the reactor coolant average temperature is greater than 350°F, the reactor is critical, or the Reactor Coolant System is not connected to the Residual Heat Removal System.

b.

Valve lift settings shall be maintained at 2485 psig + 1 percent*

For the remainder of Cycle 1 O operation for both units the valve lift settings shall be maintained at 2485 +5,-1 percent.

Amendment Nos.